Question

In: Finance

A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.   ...

A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.

  

What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations. Round the final answer to 2 decimal places.)

  

  NPV $   

  

At a required return of 8 percent, should the firm accept this project?

Accept

or

Reject

  

What is the NPV for the project if the required return is 20 percent? (Do not round intermediate calculations. Negative answer should be indicated by a minus sign. Round final the answer to 2 decimal places.)

  

  NPV $   

  

At a required return of 20 percent, should the firm accept this project?

Accept

or

Reject

  

At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Round the final answer to 2 decimal places.)

  

  Discount rate %

Solutions

Expert Solution

1)

Present value = Annuity * [ 1 - 1 / ( 1 + R)n]] / R

Present value = 17,300 * [ 1 - 1 / ( 1 + 0.08)9]] / 0.08

Present value = 17,300 * [ 0.499751 / 0.08]

Present value = 17,300 * 6.246888

Present value = 108,071.1609

NPV = present value of cash inflows - present value of cash outflows

NPV = 108,071.1609 - 78,000

NPV =$30,071.16

b)

At required rate of return of 8%, company should accept the project the as it has a positive NPV.

c)

NPV when required rate is 20%:

Present value = Annuity * [ 1 - 1 / ( 1 + R)n]] / R

Present value = 17,300 * [ 1 - 1 / ( 1 + 0.2)9]] / 0.2

Present value = 17,300 * [ 0.806193 / 0.02]

Present value = 17,300 * 4.030967

Present value = 69,735.7205

NPV = present value of cash inflows - present value of cash outflows

NPV = 69,735.7205 - 78,000

NPV = -$8,264.28

d)

At the required rate of 20%, project should not be accepted as it has a negative NPV.

e)

IRR would be the discount rate that the company would be indifferent between accepting and rejecting project

IRR is the discount rate that makes NPV equal to zero.

-78,000 + 17,300 * [ 1 - 1 / ( 1 + R9]] / R = 0

Using trial and error method i.e, after trying different values for R, let try 16.62

-78,000 + 17,300 * [ 1 - 1 / ( 1 + 0.1662)9] / 0.1662 = 0

0 = 0

Therefore IRR is 16.62%


Related Solutions

A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? What is the NPV for the project if the required return is 20%? At a required return of 20% should the firm accept this project? At what discount rate would you be indifferent between accepting the project and rejecting it? 
A project that provides annual cash flows of $2,450 for nine years costs $10,100 today. Requirement...
A project that provides annual cash flows of $2,450 for nine years costs $10,100 today. Requirement 1: At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)   NPV   $    Requirement 2: At a required return of 25 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a)...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a) If the required return is 13 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A)...
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A) If the required return is 4 percent, what is the NPV for this project? B)Determine the IRR for this project.
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a....
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a. If the required return is 19 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a....
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.   ...
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.    Required: (a) If the required return is 9 percent, what is the NPV for this project?    (b) Determine the IRR for this project. rev: 09_18_2012, 09_26_2017_QC_C
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.   ...
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.    a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required:...
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required: (a) If the required return is 10 percent, what is the NPV for this project? (b) Determine the IRR for this project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT