Question

In: Statistics and Probability

The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...

The following table represents a plan for a project:

PREDECESSOR
JOB(S)
TIMES (DAYS)
JOB NO. a m b
1 2 4 6
2 1 3 3 15
3 1 3 4 11
4 1 1 2 9
5 2 2 6 7
6 3 3 7 8
7 4 4 6 8
8 5,6 2 3 4
9 8 1 4 7
10 7 3 4 5
11 9,10 5 6 7

  

b. Indicate the critical path.

1-2-5-8-9-11
1-4-7-10-11
1-2-5-8
1-3-6-8-9-11

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time            days

d. You can accomplish any one of the following at an additional cost of $2,500 and if you will save $1,700 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 2 by three days.

No
Yes

2. Reduce job 6 by two days.

Yes
No

3. Reduce job 10 by two days.

Yes
No

e. What is the probability that the project will take more than 29 days to complete? (Round your answer to 2 decimal places.)

Probability           

Solutions

Expert Solution

from the given project

JOB NO. predecessor job shortest time a Most likely time m longest time b Expected time a+4m+b /6 variance in time ((b-a) /6 )2  
1 - 2 4 6 4 0.11
2 1 3 3 15 5 4
3 1 3 4 11 5 1.78
4 1 1 2 9 3 1.78
5 2 2 6 7 5.5 0.69
6 3 3 7 8 6.5 0.69
7 4 4 6 8 6 0.44
8 5,6 2 3 4 3 0.11
9 8 1 4 7 4 1
10 7 3 4 5 4 0.11
11 9,10 5 6 7 6 0.11

b) the critical path from 1--2--5---8----9------11 the duration =23,5 days

the critical path from 1---4----7----10-----11 the duration = 19 days

the critical path from 1----2---5----8 the duration = 13.5 days

the critical path from 1---3-----6-----8-----9----11 the duration = 24.5 days

c) Expected completion time of the project = 28.5 days

d) reduce job 2 by 2 days

e) expected completion time = M =28.5

dtandard deviation in completion time =1.9493

standard normal variate Z= (29 - 28.5) / 1.9493 = 0.2563

probability that the project will take more than 29 days P(D> 29) = P( Z> 0.2565 ) = 0.5+ P(0<Z<0.2565)

= 0.5 + 0.01 =0.51

51% chance that the project duration may be extend 29 days


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 1 3 5 C A 2 5 11 D A 1 8 9 E B 1 2 3 F C,D 1 6 11 G D,E 1 2 3 H F,G 2 3 3 b. What is the critical path? B-E-G-H A-C-F-H A-D-F-H A-D-G-H c. What is the expected project completion time? (Round your answer...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost...
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash by 1 day Max Days to Crash A 5 - $       300 1 B 3 - $       100 1 C 4 A $       100 1 D 3 A $       200 2 E 4 B $       400 3 F 2 D, E $       500 2 G 4 E $       300 3 H 3 C $       100 2 1. What is the critical path of this project? 2. What is the duration...
Problem 4 (designed to be used with the NORMDIST tutorial) The following table represents a plan...
Problem 4 (designed to be used with the NORMDIST tutorial) The following table represents a plan for a project: JOB NO. PREDECESSOR JOB(S) a m b A - 5 6 7 B A 3 4 5 C A 6 7 14 D A 4 5 12 E B 1 4 7 F C 2 3 4 G D 6 9 15 H E,F 4 6 8 I H 3 7 17 J G 4 5 6 K I,J 6 8...
The following table represents the number of times a person reports brushing his/her teeth and the...
The following table represents the number of times a person reports brushing his/her teeth and the person's age. Using alpha at .05, Test if there is a significant relationship. Identify the P value.                     Age   20-29     30-39     40-49    50+    Never                          19          15          4            2          Once a day.                 22          25          9            2         Twice a day               35          40         52          58     Three times a day      0         10           3          20   
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT