Question

In: Statistics and Probability

The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...

The following table represents a plan for a project:

PREDECESSOR
JOB(S)
TIMES (DAYS)
JOB NO. a m b
1 2 4 6
2 1 3 3 15
3 1 3 4 11
4 1 1 2 9
5 2 2 6 7
6 3 3 7 8
7 4 4 6 8
8 5,6 2 3 4
9 8 1 4 7
10 7 3 4 5
11 9,10 5 6 7

  

b. Indicate the critical path.

1-2-5-8-9-11
1-4-7-10-11
1-2-5-8
1-3-6-8-9-11

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time            days

d. You can accomplish any one of the following at an additional cost of $2,500 and if you will save $1,700 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 2 by three days.

No
Yes

2. Reduce job 6 by two days.

Yes
No

3. Reduce job 10 by two days.

Yes
No

e. What is the probability that the project will take more than 29 days to complete? (Round your answer to 2 decimal places.)

Probability           

Solutions

Expert Solution

from the given project

JOB NO. predecessor job shortest time a Most likely time m longest time b Expected time a+4m+b /6 variance in time ((b-a) /6 )2  
1 - 2 4 6 4 0.11
2 1 3 3 15 5 4
3 1 3 4 11 5 1.78
4 1 1 2 9 3 1.78
5 2 2 6 7 5.5 0.69
6 3 3 7 8 6.5 0.69
7 4 4 6 8 6 0.44
8 5,6 2 3 4 3 0.11
9 8 1 4 7 4 1
10 7 3 4 5 4 0.11
11 9,10 5 6 7 6 0.11

b) the critical path from 1--2--5---8----9------11 the duration =23,5 days

the critical path from 1---4----7----10-----11 the duration = 19 days

the critical path from 1----2---5----8 the duration = 13.5 days

the critical path from 1---3-----6-----8-----9----11 the duration = 24.5 days

c) Expected completion time of the project = 28.5 days

d) reduce job 2 by 2 days

e) expected completion time = M =28.5

dtandard deviation in completion time =1.9493

standard normal variate Z= (29 - 28.5) / 1.9493 = 0.2563

probability that the project will take more than 29 days P(D> 29) = P( Z> 0.2565 ) = 0.5+ P(0<Z<0.2565)

= 0.5 + 0.01 =0.51

51% chance that the project duration may be extend 29 days


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following table represents the number of times a person reports brushing his/her teeth and the...
The following table represents the number of times a person reports brushing his/her teeth and the person's age. Using alpha at .05, Test if there is a significant relationship. Identify the P value.                     Age   20-29     30-39     40-49    50+    Never                          19          15          4            2          Once a day.                 22          25          9            2         Twice a day               35          40         52          58     Three times a day      0         10           3          20   
The table below shows the means and standard deviations of the survival times (in days) of...
The table below shows the means and standard deviations of the survival times (in days) of some cancer patients who were treated with the same medication. Use these statistics to answer the question below. Type of Cancer Patient Mean Standard Deviation Breast 1395.9 1239.0 Bronchial 211.6 209.9 Colon 457.4 427.2 Ovarian 884.3 1098.6 Stomach 286.0 346.3 Which type of cancer patients      (a) had the highest average survival time?        (b) had the lowest average survival time?        (c) had the most consistent...
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2....
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2. a. Determine the expected duration of the project. (Round intermediate calculations to 2 decimal places and final answer to 1 decimal place.) Expected Duration             b. Compute the probability that the project will take at least 18 days. (Round intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability             Chuck’s Custom Boats (CCB) builds luxury yachts to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT