In: Statistics and Probability
Given the accompanying network diagram, with times shown in
days. Use Table B1 and Table B2.
a. Determine the expected duration of the project.
(Round intermediate calculations to 2 decimal places and
final answer to 1 decimal place.)
Expected Duration
b. Compute the probability that the project will
take at least 18 days. (Round intermediate calculations to
2 decimal places and "Probability" values to 4 decimal
places.)
Probability
Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The complication is that Mr. T wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Note: No activity can be crashed more than two weeks.
CRASHING COSTS | ||||||||
Activity | Immediate Predecessor |
Normal Time (weeks) | 1st Week | 2nd Week | ||||
K | — | 9 | $ | 410 | $ | 415 | ||
L | K | 7 | 125 | — | ||||
N | K | 5 | 45 | 45 | ||||
M | L | 4 | 300 | 350 | ||||
J | N | 6 | 50 | — | ||||
Q | J,M | 5 | 200 | 225 | ||||
P | Q | 8 | — | — | ||||
Y | Q | 7 | 85 | 90 | ||||
Z | P | 6 | 90 | — | ||||
End | Y,Z | |||||||
Develop a crashing schedule. (Leave no cells blank - be
certain to enter "0" wherever required. Omit the "$" sign in your
response.)
Project Length | Shorten Activity | Crash Cost | ||
39 | wk | — | ||
38 | (Click to select) Z N and L Q P M and N | |||
37 | (Click to select) Z N and L Q P M and N | |||
36 | (Click to select) Z N and L Q P M and N | |||
35 | (Click to select) Z N and L Q P M and N | |||
34 | (Click to select) Z N and L Q P M and N | |||
Three recent college graduates have formed a partnership and
have opened an advertising firm. Their first project consists of
activities listed in the following table. Use Table B.
TIME IN DAYS | |||||||||
Activity | Immediate Predecessor |
Optimistic | Most Likely | Pessimistic | |||||
A | — | 5 | 6 | 7 | |||||
B | — | 8 | 8 | 11 | |||||
C | A | 6 | 8 | 11 | |||||
D | — | 9 | 12 | 15 | |||||
E | C | 5 | 6 | 9 | |||||
F | D | 5 | 6 | 7 | |||||
G | F | 2 | 3 | 7 | |||||
H | B | 4 | 4 | 5 | |||||
I | H | 5 | 7 | 8 | |||||
End | E, G, I | ||||||||
b.What is the probability that the project can be
completed in 24 days or less? In 21 days or less? (Round
your te and z values to 2 decimal places and "Standard
deviation" to 3 decimal places. Round your final answers to 4
decimal places.)
Days | Probability | |
24 days or less | ||
21 days or less | ||
c. Suppose it is now the end of the seventh day and that
activities A and B have been completed while activity D is 50
percent completed. Time estimates for the completion of activity D
are 5, 6, and 7. Activities C and H are ready to begin. Determine
the probability of finishing the project by day 24 and the
probability of finishing by day 21. (Round your
intermediate calculations to 3 decimal places and final answers to
4 decimal places.)
Probability | ||
Day 24 | ||
Day 21 | ||