Question

In: Statistics and Probability

Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2....

Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2.



a. Determine the expected duration of the project. (Round intermediate calculations to 2 decimal places and final answer to 1 decimal place.)

Expected Duration            

b. Compute the probability that the project will take at least 18 days. (Round intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.)

Probability            

Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The complication is that Mr. T wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Note: No activity can be crashed more than two weeks.

CRASHING COSTS
Activity Immediate
Predecessor
Normal Time (weeks) 1st Week 2nd Week
K 9 $ 410 $ 415
L K 7 125
N K 5 45 45
M L 4 300 350
J N 6 50
Q J,M 5 200 225
P Q 8
Y Q 7 85 90
Z P 6 90
End Y,Z


Develop a crashing schedule. (Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)

Project Length Shorten Activity Crash Cost
39 wk
38 (Click to select)  Z  N and L  Q  P  M and N
37 (Click to select)  Z  N and L  Q  P  M and N
36 (Click to select)  Z  N and L  Q  P  M and N
35 (Click to select)  Z  N and L  Q  P  M and N
34 (Click to select)  Z  N and L  Q  P  M and N

Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B.

TIME IN DAYS
Activity Immediate
Predecessor
Optimistic Most Likely Pessimistic
A 5 6 7
B 8 8 11
C A 6 8 11
D 9 12 15
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I


b.
What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.)

Days Probability
24 days or less
21 days or less


c.
Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21. (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.)

Probability
Day 24
Day 21

Solutions

Expert Solution

1)
Network diagram is not provided.

2)
Crashing Schedule




3)








Related Solutions

1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days.
Supplemental assignment for MGMT8300: Network Diagram and the Critical Path 1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days. 2. What is the critical path? 3. How long will it take to complete the project if everything goes according to plan? 4. Choose an activity that is not on the critical path. How many days longer should it take in order for the critical...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for 40 secondary school students in country A. A second selection of usual travel times to​ school, in​ minutes, was randomly selected for 40 students in country B. Complete parts​ a) and​ b). Sample Country A   Sample Country B 45   29 5   10 4   9 14   30 50   5 21   8 21   7 19   15 21   10 21   36 24   16 36   10 14   24...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.   Activity Duration mobilize 1 remove siding 4 excavate/form slab 7 place slab 4 set support beam 1 stud wall up 6 install siding 4 install windows 5 set raffers 4 install roof 6 finish trim 4 paint siding 7 move out 1
1. Use the data given in the table below to construct a temperature-composition diagram for cyclohexane...
1. Use the data given in the table below to construct a temperature-composition diagram for cyclohexane toluene mixture (see p. 134 in the textbook for an example of such plot). Based on your plot, what is the composition of the distillate obtained by simple distillation of 20 mole percent cyclohexane and 80 mole percent toluene? Show your work on the plot (submit your plot). T ⁰C Mol % Cyclohexane Liquid Mol % Cyclohexane Vapor 110.7 0 0 108.3 4.1 10.2...
Data from a small bookstore are shown in the accompanying table. The manager wants to predict...
Data from a small bookstore are shown in the accompanying table. The manager wants to predict Sales from Number of Sales People Working. Complete parts a through h below. Number of ales peaople working sale (in $1000) 2 10 3 12 5 14 8 15 10 19 10 21 13 21 14 22 17 22 19 27 x(bar)= 10.1 y(bar)=18.3 SD(x)=5.74 SD(y)=5.33 A) find the slope etimate, b1. B) What does b1 mean, in thi context? C) Find the intercept,...
A table is assembled using three components, as shown in the accompanying product structure tree. The...
A table is assembled using three components, as shown in the accompanying product structure tree. The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units at the beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections are scheduled at the beginning of day 2. There are 120 legs on hand. An additional 10 percent of the order size on legs is added...
The table below shows the means and standard deviations of the survival times (in days) of...
The table below shows the means and standard deviations of the survival times (in days) of some cancer patients who were treated with the same medication. Use these statistics to answer the question below. Type of Cancer Patient Mean Standard Deviation Breast 1395.9 1239.0 Bronchial 211.6 209.9 Colon 457.4 427.2 Ovarian 884.3 1098.6 Stomach 286.0 346.3 Which type of cancer patients      (a) had the highest average survival time?        (b) had the lowest average survival time?        (c) had the most consistent...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded while riding a bicycle. He recorded every time he rode and randomly picked five laps through each mile of a​ 3-mile loop. Use a .05 significance level to test the claim that it takes the same time to ride each of the miles. Mile 1 194 205 203 202 201 Mile 2 198 201 200 196 200 Mile 3 215 211 209 212 209...
Derive the state diagram, state table, state assignment table, and logic network using D flip-flops for...
Derive the state diagram, state table, state assignment table, and logic network using D flip-flops for the following circuit: A FSM has two input, w1 and w2, and an output z. The machine has to generate z=1 when the previous four values of w1 and w2 are the same; otherwise z=0. Overlapping patterns are allowed. An example of the desired behavior is: w1: 0 1 1 0 1 1 1 0 0 0 1 1 0 w2: 1 1 1...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT