Question

In: Operations Management

Problem 3. The following project is at the end of its 6th week. Find the cost...

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity

Predecessor

Duration (wks)

Budget at Completion    ($)

Actual Cost ($)

% Complete

a

-

2

300

400

100

b

a

3

200

250

100

c

b

3

300

300

100

d

b

5

600

200

30

e

c,d

4

400

-

0

                                                                                       $1800              $ 1150

  1. CV =
  2. SV =
  3. CPI =
  4. SPI=
  5. CR=

EAC=

Solutions

Expert Solution

Question – a:

Cost Variance = Earned Value – Actual Cost

Earned Value = 300*100% + 200*100% + 300*100% + 600*30% = 300 + 200 + 300 + 180 = 980

Actual Cost = 400 + 250 + 300 + 200 = 1150.

CV = 980 – 1150 = -170

Question – b:

Schedule Variance = Earned Value – Planned Value

To find the Planned value:

We are in the 6th week.

A should be done completely

B should be done completely.

C should have done for one week. 3 weeks cost is 300. So one week it is 100.

D should have done for one week. 5 weeks 600. So one week it is 120.

Planned Value = 300 + 200 + 100 + 120 = 720

Earned Value = 980 (from part a)

SV = 980 – 720 = 260

Question – c:

Cost Performance Index = EV/AC

EV = 980

AC = 1150

CPI = 980/1150 = 0.85

Question – d:

Schedule Performance Index = EV/PV

EV = 980

PV = 720

SPI = 980/720 = 1.36

Question – e:

Critical Ratio = Time remaining/remaining processing time = (14 – 6)/remaining processing time

Remaining processing time:

Total of activity e = 4 weeks

70% 0f d = 0.7*5 = 3.5 weeks

Total = 7.5 weeks

So CR = 8/7.5 = 1.07

Estimate at Completion = EAC = BAC/CPI

BAC = $1800

CPI = 0.85

EAC = 1800/0.85 = $2117.65

EAC = AC + (BAC – EV)

AC = 1150

BAC = 1800

EV = 980

EAC = 1150 + (1800 – 980) = 1150 + 820 = $1970

.

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!


Related Solutions

Problem 3. The following project is at the end of its 6th week. Find the cost...
Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget at Completion    ($) Actual Cost ($) % Complete a - 2 300 400 100 b a 3 200 250 100 c b 3 300 300...
Week 3: Supply and Demand: Price Elasticity Problem #2 Due Date: Due by the end of...
Week 3: Supply and Demand: Price Elasticity Problem #2 Due Date: Due by the end of Week 3 at 11:59 pm, ET. Price plays a significant role in quantity demanded and quantity supplied. Consumers and sellers respond differently to changes in the price of different types of goods and the situation. To measure the responsiveness of consumers and sellers to changes in the price of a good, some rules of thumb are given. These rules of thumb are said to...
Week 3 Term Project - Conch Republic Electronics I think you will find an Excel spreadsheet...
Week 3 Term Project - Conch Republic Electronics I think you will find an Excel spreadsheet to be the most effective way of completing this assignment. Use the attached Conch Republic Spreadsheet to help you. Conch Republic Electronics Conch Republic Electronics is a mid sized electronics manufacturer located in Key West, Florida. The company president is Shelley Couts, who inherited the company. When it was founded over 70 years ago, the company originally repaired radios and other household appliances. Over...
CIS247C WEEK 2 LAB The following problem should be created as a project in Visual Studio,...
CIS247C WEEK 2 LAB The following problem should be created as a project in Visual Studio, compiled and debugged. Copy your code into a Word document named with your last name included such as: CIS247_Lab2_Smith. Also include screen prints of your test runs. Be sure to run enough tests to show the full operation of your code. Submit this Word document and the project file (zipped). The Zoo Class This class describes a zoo including some general visitor information. We...
Problem 4:  Refer to the following distribution and find:             Cost of Textbooks                &
Problem 4:  Refer to the following distribution and find:             Cost of Textbooks                                                   Number                 $25   up to     $35                                                   2                   35   up to       45                                                   5                   45   up to       55                                                   7                   55   up to       65                                                 20                   65   up to       75                                                 16 a.  The Range?       b. The standard deviation?   Determine the Mean, Mode, Median? Boxplot and describe skewness?                                                   Are there any outliers?
WEEK 10 DISCUSSION We are now at the end of the road and your project is...
WEEK 10 DISCUSSION We are now at the end of the road and your project is coming to a completion. Before you celebrate, there are still a few more steps before you close-out this project. It is time to discuss lessons learned with your team about this project and your communication management plan. In a few paragraphs respond to the following question: Discuss the importance of conducting lessons learned meeting with the team and why it should be documented and...
1. If at the end of week three of a project you discover you that SV...
1. If at the end of week three of a project you discover you that SV is negative but SPI is 1.06. What does this mean? 2. What is the difference between percent complete and percent complete with gates Earned value (EV) measurement rules? What advantage does the latter have over the former? 3. Cost Variance (CV) and Cost Performance Index (CPI) can both be used to determine whether a project is on budget, under budget, or over budget at...
1. a. Calculate the IRR for the following project if its cost was $5,000 and the...
1. a. Calculate the IRR for the following project if its cost was $5,000 and the annual expenditures and costs were: Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 2,000 2,000 2,000 2,000 -1,000 -1,000 b. Assume a firm's WACC is 10 percent. Calculate the NPV for the following project if its cost was $5,000 and the annual expenditures and costs were: Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 2,000 2,000...
A project with a 3-year life has the following probability distributions for possible end of year...
A project with a 3-year life has the following probability distributions for possible end of year cash flows in each of the next three years: Year 1 Prob then Cash Flow 0.30 $300 0.4 $500 0.3 $700. Year 2 0.15 $100 0.35 $200 0.35 $600 0.15 $900. Year 3 0.25 $200 0.75 $800. Using an interest rate of 8 percent, find the expected present value of these uncertain cash flows. (Hint: Find the expected cash flow in each year, then...
3. Consider a project having the following activities, time, and cost:                               &nb
3. Consider a project having the following activities, time, and cost:                                                   Normal       Normal       Crash         Crash      Maximum                         Immediate          Time         Cost         Time          Cost         Time       Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced             a               none                  4            3,000             2            5,000            2             b               a                        5            5,000             3            8,000            2             c               a                        4            7,000             4            7,000            0             d               b                        4            6,000             2            8,000            2             e               c,d                     8            4,000             6            8,000            2             f               c                       ...