Question

In: Finance

1. If at the end of week three of a project you discover you that SV...

1. If at the end of week three of a project you discover you that SV is negative but SPI is 1.06. What does this mean?

2. What is the difference between percent complete and percent complete with gates Earned value (EV) measurement rules? What advantage does the latter have over the former?

3. Cost Variance (CV) and Cost Performance Index (CPI) can both be used to determine whether a project is on budget, under budget, or over budget at a particular point in time. What should a PM look for when reviewing CV and CPI information? What additional EVM analyses/calculations are supported by CPI?

Solutions

Expert Solution

Schedule variance (SV) is calculated as the difference between earned value (EV) and planned value (PV). How much value have we earned in the project based on our budget at completion (BAC) and what percentage of work has been completed and how much did we plan to have spent by this point in the project?

SV = EV – PV

If we have a negative schedule variance it means that we are behind schedule.

A positive SV indicates that we are trending ahead of schedule. A variance of zero indicates the project is exactly on schedule

SPI = EV ÷ PV

If the SPI is less than one, it indicates that the project is potentially behind schedule to-date whereas an SPI greater than one, indicates the project is running ahead of schedule. An SPI of one indicates the project is exactly on schedule.

Negative SV does not mean we are behind schedule in terms of target date at the moment. But it shows us there are some delay, and the schedule have high probablity of delay in future. Some activites are consuming the float of the schedule, more activities trends to be critical. We may have more problem with resource management.

Cost Variance can be calculated by subtracting the actual cost from earned value.

Cost Variance = Earned Value – Actual Cost

CV = EV – AC

From the above formula, we can conclude that:

  • If Cost Variance is positive, this means you are under budget.
  • If Cost Variance is negative, this means you are over budget.
  • If Cost Variance is zero, this means you are on budget.

Related Solutions

BUSINESS HIGHLIGHTS Name & Address of the Project:                SV Auditorium Kollam,Chinnakkada Nature of Project:        &nbsp
BUSINESS HIGHLIGHTS Name & Address of the Project:                SV Auditorium Kollam,Chinnakkada Nature of Project:                                       Auditorium & Marriage Hall Promoter:                                                    Mr.Siju Varghes Kollam,Chinnakkada Kollam-690547 Constitution: Proprietorship Location:                                                     Kollam,Chinnakkada The above stated information is about my business fiction. so, please answer the following question based on the above business details. Thanks in advanced. Step 2: Define 3 processes of your business and select which of these processes is the main process. State the activities included in the mine process. They must...
BUSINESS HIGHLIGHTS Name & Address of the Project:                SV Auditorium Kollam,Chinnakkada Nature of Project:        &nbsp
BUSINESS HIGHLIGHTS Name & Address of the Project:                SV Auditorium Kollam,Chinnakkada Nature of Project:                                       Auditorium & Marriage Hall Promoter:                                                    Mr.Siju Varghes Kollam,Chinnakkada Kollam-690547 Constitution: Proprietorship Location:                                                     Kollam,Chinnakkada The above stated information is about my business fiction. so, please answer the following question based on the above business details. Thanks in advanced Determine the importance of the risks selected depending on your risk assessment, Develop appropriate responses to the risk selected and then assess the developed risks
WEEK 10 DISCUSSION We are now at the end of the road and your project is...
WEEK 10 DISCUSSION We are now at the end of the road and your project is coming to a completion. Before you celebrate, there are still a few more steps before you close-out this project. It is time to discuss lessons learned with your team about this project and your communication management plan. In a few paragraphs respond to the following question: Discuss the importance of conducting lessons learned meeting with the team and why it should be documented and...
Week 1 Assignment Complete this two page assignment by the end of week 1! Download and...
Week 1 Assignment Complete this two page assignment by the end of week 1! Download and open the Word document below....fill in the blank and highlight the answer to the questions or fill in the blank. Resubmit here when you're finished by adding your completed assignment as a file! BIO 212 Assignment 1.docx BIO 212 Assignment 1 Fill in the Blank: Use the table on pg. 848-853 in your textbook to help you fill in the blank. Drug Classification Action...
Problem 3. The following project is at the end of its 6th week. Find the cost...
Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget at Completion    ($) Actual Cost ($) % Complete a - 2 300 400 100 b a 3 200 250 100 c b 3 300 300...
Assume this week is the end of 2018. It has been a wonderful year-end for you...
Assume this week is the end of 2018. It has been a wonderful year-end for you because your business Computer Servicing and Networking Business was doing great! But don't forget that you need to complete adjusting entities on Dec 31, 2018. Please give me one each example of two types of adjusting entries: 1. Deferred accounts 2. Accrued accounts Please feel free to read the text books, but make sure you use transactions of your own company. For example: 1....
You are a Derivatives Trader at a major Broker-Dealer. At the end of the week you...
You are a Derivatives Trader at a major Broker-Dealer. At the end of the week you need to calculate and submit several capital ratios for the performance of your business. You consolidate all trading activity across counterparties and asset types. You are deploying standardized metrics to calculate Risk Weighted Assets (RWA). Below are the standardized risk weights for various asset types: i. Cash, US Treasuries (0%) ii. US Bank issued paper and FHA, Fannie Mae, Freddie Mac issued paper (20%)...
At the end of this week, you reviewed a video of the attorney of Stella Liebeck...
At the end of this week, you reviewed a video of the attorney of Stella Liebeck in Liebeck v. McDonald's when discussing products liability. Liebeck spilled hot McDonald’s coffee in her lap, suffering third-degree burns. At trial, evidence showed that her cup of coffee was brewed at 190 degrees, and that, more typically, a restaurant’s “hot coffee” is in the range of 140-160 degrees. A jury awarded Liebeck $160,000 in compensatory damages and $2.7 million in punitive damages. The judge...
Course Project Week 4 For this next part of the project you will build the Income...
Course Project Week 4 For this next part of the project you will build the Income Statement and Balance Sheet for the Bike Repair & Maintenance Shop (BRMS) for 2018. Use the information below and add another sheet to your Excel Workbook. BRMS Information for 2018 In 2017, the repair shop was opened in October and ended the year with a ($10,500) operating loss. Supply Inventory of parts & supplies maintained   $3,000 Replacement parts are ordered as they are used....
1. Assume that you will deposit $4000 at the end of each of the next three...
1. Assume that you will deposit $4000 at the end of each of the next three years in a St. George bank account paying 8% interest. You currently have $7000 in the account. How much will you have in three years? In four years? 2. You are looking into an investment that will pay you $12,000 per year for the next 10 years. If you require a 15% return, what is the most you would pay for this investment? 3....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT