In: Operations Management
Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.
Activity |
Predecessor |
Duration (wks) |
Budget at Completion ($) |
Actual Cost ($) |
% Complete |
a |
- |
2 |
300 |
400 |
100 |
b |
a |
3 |
200 |
250 |
100 |
c |
b |
3 |
300 |
300 |
100 |
d |
b |
5 |
600 |
200 |
30 |
e |
c,d |
4 |
400 |
- |
0 |
We prepare a Gantt Chart to find Planned Value as shown below:
As seen from above, at end of week 6,
Activity a and b are 100% complete, Activity c is (1/3) = 33.33% complete, activity d is 1/5 = 20% complete and activity e is 0% complete
We get planned value for each activity as shown below:
Activity a = 100% * 300 = 300
b = 100% * 200 = 200
c = 33.33% * 300 = 100
d = 20% * 600 = 120
e = 0% = 0
Total Planned Value = PV = 300 + 200 + 100 + 120 + 0 = 720
Earned Value = 100% * 300 + 100% * 200 + 100% * 300 + 30% * 600 + 0% * 400 = 300 + 200 + 300 + 180 + 0 = 980
Actual cost = AC = 400 + 250 + 300 + 200 = 1,150
Total Budget at completion = 300 + 200 + 300 + 600 + 400 = 1800
BAC = $ 1800
PV = $ 720
EV = $ 980
AC = $ 1150
a. CV = EV - AC = 980 - 1150 = $ (-170)
b. SV = EV - PV = 980 - 720 = $ 260
c. CPI = EV / AC = 980 / 1150 = 0.852
d. SPI= EV / PV = 980 / 720 = 1.361
e. CR= CPI * SPI = 0.852 * 1.361 = 1.16
f. EAC = BAC / CPI = 1800 / 0.852 = $ 2,112.68
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.