Question

In: Accounting

The agreed contract price is $96,000. How should this price be allocated to performance obligations?

IFRS 16

The agreed contract price is $96,000. How should this price be allocated to performance obligations? Llama limited sells and equipment on January 01, 2019 which she bought on January 01,2016 for $6,000, and has been depreciating the equipment each year at 25% per annum on a straight line basis.

It trades this equipment in for new one costing $10,000 pays the supplier $9,200 in cash. What is the gain or loss on the disposal of the old equipment?

Unicorn Express Co. pays $80,000 to replace a major component of a factory machine. The faulty component that is replaced is sold for $4,000. The carrying amount of the machine before the replacement is $900,000, of which $20,000 relates to the faulty component being replaced.

Calculate the revised carrying amount of the machine after the replacement occurs and the profit or loss disposal of the faulty component.

Solutions

Expert Solution

1) Where a contract has multiple performance obligations, an entity will allocate the transaction price to the performance obligations in the contract by reference to their relative standalone selling prices. If a standalone selling price is not directly observable, the entity will need to estimate it. IFRS 15 suggests various methods that might be used, including:

 Adjusted market assessment approach

 Expected cost plus a margin approach

 Residual approach (only permissible in limited circumstances).

2) Carryig value on Jan 01,2016 $6,000

Depreciation 25% of 6,000 = 1,500 every year straight line

Carrying value on Jan 01,2019 = 6,000 - (1,500 * 3)

= 1,500

Gain or Loss on Disposal

Equipment Received = 10,000

Less: Cash =  9,200

Less: OldEquipment given up = 1,500

Loss = (700)

3) Carrying Amounto the nw machine is 900,000 - 20,000 + 80,000 = 960,000

Loss = 20,000 - 4,000 = 16,000


Related Solutions

The residual approach to allocate transaction prices to multiple performance obligations in a contract is appropriate...
The residual approach to allocate transaction prices to multiple performance obligations in a contract is appropriate when: Multiple Choice None of the goods and services included in the contract are not sold on a stand-alone basis. None of the answer choices are correct. The stand-alone price of all of the goods or services is known. The stand-along price of one or more of the goods or services is highly variable or uncertain. 3. A patient of Dr. Jones presents his...
Chapter 11 1) A contract is defined as a promise creating legal obligations of performance. a)...
Chapter 11 1) A contract is defined as a promise creating legal obligations of performance. a) The four elements of a valid contract are best remembered by using the pneumonic CLAC. What does CLAC stand for? b) How many parties are required for a valid contract? c) How many promises are required for a valid contract? d) At what point is a unilateral contract formed? A bilateral contract? e) Compare an express contract with an implied contract f) What is...
Based on FASB ASC 606, when a company has multiple performance obligations, how should they allocate...
Based on FASB ASC 606, when a company has multiple performance obligations, how should they allocate the transaction price?
There are five revenue recognition? criteria. 1.Identify the contract with the customer. 2.Identify the performance obligations....
There are five revenue recognition? criteria. 1.Identify the contract with the customer. 2.Identify the performance obligations. 3.Determine the transaction price. 4.Allocate the transaction price to performance obligations. 5.Recognize revenue in accordance with performance. There are some situations.a. a.An apartment owner receives a deposit of? $1200 equal to one? month's rent. b.An insurance company receives annual premiums for fire insurance on June 25 for coverage beginning July 1. c.A city transit authority issues? 200,000 monthly passes at? $80 each for sale...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          24,000         29,000 Collections to date                     4,000           14,000         25,000 The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $8,000 $10,000 $22,000 Estimated costs to complete 12,000 6,000 -0- Customer billings to date 9,000 21,000 29,000 Collections to date 4,000 14,000 25,000 If the company uses the percentage-of-completion method, an inventory/current...
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400. Joe estimated total construction costs would be $12,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                                              2020                       2021                      2022        Total costs incurred to date                                        $4,500                    $7,920                  $13,800 Estimated costs to complete                                         7,500                      5,280                     -0- Customer billings to date                                             6,600                    12,000                    16,800 Collections to date                                                      6,000                    10,500                    16,500 Instructions: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT