Question

In: Accounting

Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During...

Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During 2017, Concord, Inc. incurred costs of $1,547,340, billed its customers for $1,085,000, and collected $1,013,000. At December 31, 2017, the estimated additional costs to complete the project total $3,003,660. Prepare Concord’s 2017 journal entries using the percentage-of-completion method.

Solutions

Expert Solution

Date Accounts Debit Credit
2017.. Construction in process $ 1,547,340.00
        Cash $ 1,547,340.00
(To record cost of Construction incurred during year)
2017.. Accounts receivables $ 1,085,000.00
        Billing on contract $ 1,085,000.00
(To record billing to customer)
2017.. Cash $ 1,013,000.00
       Accounts Receivables $ 1,013,000.00
(To record receipt of cash)
Dec 31 2017.. Construction expenses $ 1,547,340.00
Construction in process $     651,100.00
          Construction revenue $        2,198,440
(To record construction revenue)

Working

Working 2017
A Contract Price $        64,66,000
B Cost Incurred to Date $        15,47,340
C Estimated cost yet to be incurred to complete the contract $        30,03,660
D = B+C Total Cost $        45,51,000
E = (D/B) x 100 % of Complition 34%
F = A x E Revenue to date $        21,98,440
G Revenue of Previous year $                       -  
H = F - G Net Revenue this year $        21,98,440
I Cost to date $        15,47,340
J Cost to date of previous year $                       -  
K = I - J Net Cost for the year $        15,47,340
L = H - K Gross Profits $          6,51,100

Related Solutions

Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred costs of $280,300, billed its customer for $216,200, and collected $176,500. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Waterway’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred...
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred costs of $277,100, billed its customer for $215,200, and collected $173,900. At December 31, 2017, the estimated additional costs to complete the project total $161,000. Prepare Swifty’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
----- began the process of self-constructing an office building in 2017. In order to provide for...
----- began the process of self-constructing an office building in 2017. In order to provide for partial financing of the total construction cost, the company issued a 15-month $400,000, 12% note, dated January 1, 2017. Also on Jan. 1, 2017 --- paid ----- Construction Corp. $500,000 as the first installment for the overall building contract which called for the following additional payments made on a a timely basis: 1-Jun-17 $    900,000 1-Oct-17 $ 1,000,000 In addition to the construction note,...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below. 2020 2021 2022 Actual costs incurred during each individual year $10,000,000 15,000,000 12,500,000...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000. Below is a summary of events for 2017 and 2018: 2017 2018 Costs incurred during the year $ 712,500 $1,138,250 Estimated costs to complete 1,037,500 0 Billings during the year 850,000 1,150,000 Cash collections during the year 750,000 1,000,000 ABC Construction Co. recognizes...
Big Red Engineering Associates entered into a 3 year contract to construct an office building at...
Big Red Engineering Associates entered into a 3 year contract to construct an office building at a contract price of $1,700,000. With the construction data below prepare the necessary journal entries to record cost incurred, billings to customers, cash collections, and the end of year adjusting entry applicable to percentage of completion method:                                                  Year 1                    Year 2                    Year 3 Construction cost incurred       250,000                 900,000                  210,000 Estimated cost to complete   1,000,000                  287,500                       0 Progress Billings                      190,000               1,200,000                  310,000 Collections...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT