In: Accounting
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is incomplete and the contractor is confused about how to transfer profit or loss in the P/L account. Being a student of cost accounting, you are required to state the rules regarding the transfer of profits to profit and loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %) to the contractor.
In the construction contract , the revenues are matched with the
costs in the period in which they are incurred.
However, construction contracts are long-term in nature and hence,
the revenue and costs are carried over from one accounting period
to another.
In case when the % of completion of contract is identifiable over the period of contract , the revenue should be recorded based on the percentage of the completion in Profit & Loss Account.
In case when % of completion is not identifiable then revenue should be equal to total cost incurred.
Let us assume the contract Revenue be 10 lacs & total contract cost 8 Lacs
and % of completion for the respective year is as follow
Year | % of completion | Total Revenue | Total Cost | Profit to be transaferred to P& L |
2019-20 | 20% | 200000 | 160000 | 40000 |
2020-21 | 50% | 500000 | 400000 | 100000 |
2021-22 | 75% | 750000 | 600000 | 150000 |
2022-23 | 90% | 900000 | 720000 | 180000 |