Question

In: Accounting

Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is...

Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is incomplete and the contractor is confused about how to transfer profit or loss in the P/L account. Being a student of cost accounting, you are required to state the rules regarding the transfer of profits to profit and loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %) to the contractor.

Solutions

Expert Solution

In the construction contract , the revenues are matched with the costs in the period in which they are incurred.
However, construction contracts are long-term in nature and hence, the revenue and costs are carried over from one accounting period to another.

In case when the % of completion of contract is identifiable over the period of contract , the revenue should be recorded based on the percentage of the completion in Profit & Loss Account.

In case when % of completion is not identifiable then revenue should be equal to total cost incurred.

Let us assume the contract Revenue be 10 lacs & total contract cost 8 Lacs

and % of completion for the respective year is as follow

Year % of completion Total Revenue Total Cost Profit to be transaferred to P& L
2019-20 20% 200000 160000 40000
2020-21 50% 500000 400000 100000
2021-22 75% 750000 600000 150000
2022-23 90% 900000 720000 180000

Related Solutions

ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building...
ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building for its customer on its customer’s land for $20 million. The completion is expected to be in two years’ time. ABC’s policy is to bill its clients based on 60% in the first year and the balance upon completion of the project. ABC has a 31st December financial year end. It has adopted FRS 115 Revenues from Contracts with Customers and adopts the input...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Majid and Rashid are partners in a firm. Their capital accounts as on 1st April 2019...
Majid and Rashid are partners in a firm. Their capital accounts as on 1st April 2019 showed a balance of OMR 100,000 and OMR 200,000 respectively. On 1st July 2019 Majid introduced additional capital of OMR 40,000 and Rashid OMR 50,000. On 1st October Majid withdrew OMR 20,000 and 1st January 2020 Rashid withdrew OMR 10,000 from their capitals. Interest on capital is 6% and interest on drawings is 8% per annum the accounting period ends on March 31st every...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000. Below is a summary of events for 2017 and 2018: 2017 2018 Costs incurred during the year $ 712,500 $1,138,250 Estimated costs to complete 1,037,500 0 Billings during the year 850,000 1,150,000 Cash collections during the year 750,000 1,000,000 ABC Construction Co. recognizes...
Cussatt Construction Company had a contract starting April 2018, to construct a $48,000,000 building that is...
Cussatt Construction Company had a contract starting April 2018, to construct a $48,000,000 building that is expected to be completed in September 2020, at an estimated cost of $44,000,000. At the end of 2018, the costs to date were $20,240,000 and the estimated total costs to complete had not changed. The progress billings during 2018 were $4,800,000 and the cash collected during 2018 was $6,400,000. Cussatt uses the percentage-of-completion method. For the year ended December 31, 2018, Cussatt would recognize...
On April 1, Paine Co. began construction of a small building. Payments of $234,960 were made...
On April 1, Paine Co. began construction of a small building. Payments of $234,960 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building by completing the schedule below: Date Expenditures Capitalization Period Weighted-Ave. Accum. Expend. $ $    $
On April 1, Paine Co. began construction of a small building. Payments of $180,000 were made...
On April 1, Paine Co. began construction of a small building. Payments of $180,000 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building by completing the schedule below:             Date               Expenditures       Capitalization Period      Weighted-Average Expenditures Question 2 On March 1, Mocl Co. began construction of a small...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in terms of which the construction company undertook to build one Medical Suite Block, consisting of 50 suites of 3 rooms, a waiting room, Doctors consulting room, reception area and kitchenette. The contract stipulated that the building would be completed by 15 December 2015. The contracting parties also agreed to the following: a) If the hostels are not completed by 15 December 2015, Build-IT Building...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT