Question

In: Computer Science

What do you think about adding a project buffer for the entire project, as critical chain...

What do you think about adding a project buffer for the entire project, as critical chain scheduling suggests?

What are some ethical considerations when using slack and buffers?

Solutions

Expert Solution

The Critical Chain/Buffer Management (CC/BM) approach aims at the construction of latest start schedules where the project activities use aggressive time estimates and puts a clear focus on the determination of a realistic project deadline. In order to keep the probability high that the project deadline will be met, the CC/BM approach protects the project duration and the critical chain of the project using various buffers. This buffered scheduling approach is the topic of this article and is discussed along the following dimensions:

  • Project buffer: A unique and single buffer to protect the project deadline
  • Feeding buffer: Multiple buffers to protect parts of the critical chain
  • Resource buffer: Multiple artificial buffers that act as warning signals to assure the availability of resources

A single project buffer is added at the end of the project network between the last activity and the project deadline. Any delays on the critical chain will partly consume this buffer without having an effect on the project completion date. Consequently, a project buffer acts as a protection of the project completion date which might be variable due to changes in activity durations on the critical chain. Its size should depend on the expected changes and variability of the activities on the critical chain. Figure 2 displays the unique project buffer at the end of the project displays a project network with 8 activities and a latest start schedule with a project duration of 12 time units. The numbers above each node in the network are used to refer to the aggressive activity duration estimate (see ”Aggressive activity time estimates: protecting against activity delays”) while the label below the node refers to a renewable resource that is required to perform the activity. The renewable resources A, B, C, D and F have an availability of one, while the renewable resource E availability is restricted to two units. The construction of the resource feasible latest start schedule is discussed in ”Critical Chain/Buffer Management: (Dis-)advantages of scheduling projects as-late-as-possible”.

Project practitioners “do not engage in or condone behavior that is designed to deceive others, including but not limited to, making misleading or false statements, stating half-truths, providing information out of context or withholding information that, if known, would render our statements misleading or incomplete.”The intentional modification of project or supplier integrated master schedules (IMS), or scheduling inputs or outputs, in a manner designed to mislead stakeholders, hide factual information, win the job or contract, mask performance problems, inflate margin, buy time to fix problems without executive leadership involvement, or other similar goals.

• Preferential Sequencing: structuring IMS logic to favor one stakeholder’s position or interests over another’s • Duration Padding: adding an artificial time buffer “just in case” • Duration Compression: arbitrarily reducing durations to offset the impact of late or slipping predecessor tasks • Hiding Slack: using constraints, lags, improper logic or inflated durations to mask slack • Abusing Project Logic: intentionally manipulating dependencies to mask schedule issues or potential problems • Excluding Scope from the IMS: intentionally not including tasks in the IMS to show an artificially early project completion


Related Solutions

________ is typically not referred to as a buffer type in critical chain project management. a....
________ is typically not referred to as a buffer type in critical chain project management. a. resource buffer b. free buffer c. feeding buffer d. project buffer A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of...
You are about to close a project. What do you think worked well, or didn’t work...
You are about to close a project. What do you think worked well, or didn’t work well for this project
What do you think about adult and childhood obesity?  What do you really think is at the...
What do you think about adult and childhood obesity?  What do you really think is at the “heart” of the weight-loss crisis in America? When you see a 250-pound 10-year-old in public, what do you think? Do you make any assumptions? Do you think the parents are guilty of causing this obesity? If the parents are not guilty, then what are the underlying causes?
what are the strengths and the weaknesses do you think about project cost forecasting? write your...
what are the strengths and the weaknesses do you think about project cost forecasting? write your answer in 200 words .
Think of Groups: 1. What do you understand about groups? 2. Explain five (5) critical attributes...
Think of Groups: 1. What do you understand about groups? 2. Explain five (5) critical attributes (properties) of groups; examples are necessary
what do you think about Epocrates application?
what do you think about Epocrates application?
what do you think about the statement “history repeats itself”? Do you think this is accurate?...
what do you think about the statement “history repeats itself”? Do you think this is accurate? What information guides you to this conclusion?
What do you think about Erikson's theory in regards to Adolescence? How do you think it...
What do you think about Erikson's theory in regards to Adolescence? How do you think it is connected to the three different areas of development (Physical, Cognitive, and Emotional/Social) during this period? please explainn
What do you think is most challenging about collecting candid feedback on project successes and failures?...
What do you think is most challenging about collecting candid feedback on project successes and failures? How can you ensure a productive lessons learned process to best impact future projects in a positive manner? Does this change if your team will work together again in the future versus a "one and done" project?
What do you think is the biggest ethical issue in supply chain? What would you suggest...
What do you think is the biggest ethical issue in supply chain? What would you suggest to prevent or rectify this issue?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT