In: Operations Management
a. resource buffer
b. free buffer
c. feeding buffer
d. project buffer
Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the first 3 years, what is true?
a. Both projects are equally attractive.
b.The first project is more attractive by app. 7%.
c. The second project is more attractive by app. 5%.
d. The first project is more attractive by app. 3%.
3. Your project management team includes two external consultants each from a different company.You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives.
Which stage of team development can be difficult to overcome in such a situation?
a Storming from Forming, Storming, Norming, Performing
b Panic from Enthusiasm, Panic, Hope, Solution
c Kickoff from Assignment, Kickoff, Training, Communicating
d Frustration from Direction, Frustration, Cooperation, Collaboration
4. During a project, earned value analysis is performed, resulting in the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
a CV: 120,000 SV: 100,000
b CV: 100,000 SV: 120,000
c CV: -100,000 SV: -120,000
d CV: -120,000 SV: -100,000
Answer 1: (b) free buffer is typically not referred to as a buffer type in critical chain project management.
Answer 2: (b)The first project is more attractive by app. 7%.
Explanation:
Project 1 |
Project 2 |
|
1 |
120000 |
15000 |
2 |
120000 |
125000 |
3 |
120000 |
220000 |
NPV of project 1 = Total discount benefit – Total discount cost
= 120000/(1+0.05)1+120000/(1+0.05)2+120000/(1+0.05)3- 250000
= 326789.7 – 250000 = 76789
NPV of project 2 = Total discount benefit – Total discount cost
= 15000/(1+0.05)1+125000/(1+0.05)2+220000/(1+0.05)3- 250000
= 317708 – 250000 = 67708
Therefore, Project 1 is more attractive to start with as NPV of project 1 is more.
Answer 3: (a) Storming from Forming, Storming, Norming, Performing stage of team development can be difficult to overcome in such a situation.
Answer 4:(d) CV: -120,000 SV: -100,000 results are correct.
Explanation:
Cost Variance (CV) = Earn Value – Actual Cost
= 523000 - 643000
= -120000
Schedule Variance (SV) = Earn Value – Planned Value
= 523000 - 623000
= -100000
PLEASE GIVE A POSITIVE FEEDBACK AND UP RATE MY ANSWER, THANK YOU.