Question

In: Accounting

On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...

On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 326,000
September 1, 2021 $ 477,000
December 31, 2021 $ 477,000
March 31, 2022 $ 477,000
September 30, 2022 $ 326,000


Dreamworld had $5,900,000 in 12% bonds outstanding through both years.

What was the final cost of Dreamworld's warehouse?

Solutions

Expert Solution

Step 1:-

Calculate the Weighted average expenditure and interest capitalization for 2021

Year 2021
Date Expenditure * Weight Average
January 1, 2021 326,000 12/12 = 326,000
September 1, 2021 477,000 04/12 = 159,000
December 31, 2021 477,000 0/12 = 0
Accumulated expenditures 1,280,000 485,000

Interest Capitalization = $58,200 ($485,000 * 12%)

Step 2:-

Calculate the weighted average expenditure and interest capitalization for 2022

Date Expenditure * Weight Average
Accumulated Expenditures as of 12/31/2021 1,280,000 12/12 = 1,280,000
Interest Charges for 2021 58,200 12/12 = 58,200
March 31, 2022 477,000 06/12 = 238,500
September 30,2022 326,000 0/12 = 0
Accumulated expenditures 2,141,200 1,576,700

The weighted average expenditure and interest capitalization is as follows:-

Accumulated Expenditures as of 09/30/22 2,141,200
Interest capitalization for 2022 189,204 ($1,576,700* 12%
Total capitalized cost 2,330,404

The final cost of Dreamworld's warehouse is $2,330,404


Related Solutions

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $50,000 None...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 336,000 September 1, 2018 $ 504,000 December 31, 2018 $ 504,000 March 31, 2019 $ 504,000 September 30, 2019 $ 336,000 Dreamworld had $6,800,000 in 10% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was: a. $72,000 b. $63,000 c. $54,000 d. $36,000
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 307,000 September 1, 2018 $ 459,000 December 31, 2018 $ 459,000 March 31, 2019 $ 459,000 September 30, 2019 $ 307,000 Dreamworld had $5,300,000 in 13% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building was completed on June 30, 2016. Cash outlays for the $5 million project were as follows: 2015 January 1                        $1,000,000 March 1                          $600,000 June 30                           $800,000 September 30               $750,000 December 1                   $600,000 2016 March 31                        $800,000 June 30                           $450,000 (final payment) Total payments             $5,000,000 On January 1, 2015 Costco obtained a $3 million dollar construction loan with a 5% interest rate. Costco’s other long-term...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT