Question

In: Operations Management

A steel product is manufactured by starting with raw material (carbon steel wire) and then processing...

A steel product is manufactured by starting with raw material (carbon steel wire) and then processing it sequentially through five operations using machines A to E, respectively (see table below). This is the only use that the five machines are put to. The hourly rates for each machine are given in the table. Answer the following questions. Use the original output rates to answer each question (i.e., disregard any changes mentioned in previous questions).

Operation: 1 2 3 4 5
Machine: A B C D E
Hourly unit output rate: 80 40 30 110 50

Consider the following questions.

a. What is the maximum output per hour of the steel product?

b. By how much would the output be improved if B was increased to 50?

c. By how much would the output be improved if C was increased to 40?

d. By how much would the output be improved if C was increased to 50?

e. What is the effect on the system if machine A can only manage an output of 20 in one hour?

f. What is the effect on the system if machine C can only manage an output of 20 in one hour?

g. What is the effect on the system if machine B is allowed to drop to an output of 20 in one hour?

Solutions

Expert Solution

In solving the below questions, one logic is very important that the overall production speed is defined by the bottleneck ( slowest operation ) in the entire system.

a. What is the maximum output per hour of the steel product?

The maximum output is depended on the bottleneck operation i.e the slowest operation which is Operation number 3 in this case on machine C which is 30 units per hour, hence the maximum output per hour is 30 units of steel wire per hour.

b. By how much would the output be improved if B was increased to 50?

If B is increased to 50, still the bottleneck operation i.e C will limit the overall output to 30. Hence because of the bottleneck of C=> the maximum output, in this case, will also be 30 units per hour

c. By how much would the output be improved if C was increased to 40?

The maximum output, in this case, would become 40 units per hour as the bottleneck i.e lowest output process would still be C and B with 40 units per hour output but the overall production would increase by 10 units to 40 units per hour due to the improvement in C.

d. By how much would the output be improved if C was increased to 50?

If C was improved to 50 units the overall production would still improve by 10 units to produce 40 units as the now the bottleneck process would be B with the production of 40 units per hour thus limiting the overall production.

e. What is the effect on the system if machine A can only manage an output of 20 in one hour?

It would reduce the overall production to 20 units per hour as A would become the slowest operation now with the production of 20 units per hour i.e A would be the bottleneck process

f. What is the effect on the system if machine C can only manage an output of 20 in one hour?

In this also the overall production would be limited to 20 units per hour as C would become the bottleneck operation.

g. What is the effect on the system if machine B is allowed to drop to an output of 20 in one hour?

In this also the overall production would be limited to 20 units per hour as B would become the bottleneck operation with an output of 20 units per hour.


Related Solutions

A steel product is manufactured by starting with raw material (carbon steel wire) and then processing...
A steel product is manufactured by starting with raw material (carbon steel wire) and then processing it sequentially through five operations using machines A to E, respectively (see table below). This is the only use that the five machines are put to. The hourly rates for each machine are given in the table. Answer the following questions. Use the original output rates to answer each question (i.e., disregard any changes mentioned in previous questions). Operation: 1 2 3 4 5...
   Problem: Delta Wire manufactures high-carbon specialty steel wire and at present employs 20,000 workers. The...
   Problem: Delta Wire manufactures high-carbon specialty steel wire and at present employs 20,000 workers. The company is currently experiencing serious problems, at least in part due to the continuing decline in value of the CDN$. Foreign competition is becoming a significant threat to Delta’s market position. At the same time, industry quality requirements have become increasingly tougher each year. One strength at Delta, however, is their level of employee education. Employee education has many payoffs, but one, in particular,...
Suppose that chemical X is manufactured using a raw material B that is available from a...
Suppose that chemical X is manufactured using a raw material B that is available from a location ... Suppose that chemical X is manufactured using a raw material B that is available from a location called the "mine." Production of one ton of X requires 1/3 of a ton of B. A firm called X ENTERPRISES, which has a contract to deliver 30 tons of X to a location called the "market," is trying to decide where to locate its...
How carbon affect hardness?? and Discuss the hardenability of each material. 1018 steel, 4140 steel, 1045...
How carbon affect hardness?? and Discuss the hardenability of each material. 1018 steel, 4140 steel, 1045 steel and 8620 steel
1. A company manufactures a product from a raw material, which is purchased at ` 54...
1. A company manufactures a product from a raw material, which is purchased at ` 54 per kg. The company incurs a handling cost of ` 350 plus freight of ` 400 per order. The incremental carrying cost of inventory of raw material is Re. 0.50 per kg per month. In addition, the cost of working capital finance on the investment in inventory of raw material is `8 per kg per annum. The annual production of the product is 94,500...
Dodson Inc. is considering purchasing some new processing equipment. The carbon steel alternative has been quoted...
Dodson Inc. is considering purchasing some new processing equipment. The carbon steel alternative has been quoted at $40,000 initially. It would have an eight-year life with residual salvage of $2,000. The operating costs would be $3,000 per year with a major overhaul at the end of the third and sixth years of $4,000. A more corrosion-resistant alternative to stainless steel is offered at $60,000 with a life of 12 years, an operating expense of $1,500 per year, and no major...
Suppose that you were to convert benzophenone (the starting material) into benzhydrol (the product) by reaction...
Suppose that you were to convert benzophenone (the starting material) into benzhydrol (the product) by reaction with NaBH4 or some comparable reducing agent. Note that no reaction occurs before the NaBH4 is added. Also note that NaBH4 does not appear on your TLC plate. On the templates provided below, sketch the TLC plates you would obtain for: a) the reaction mixture before adding the sodium borohydride; b) a sample taken from the reaction mixture when the reaction is about half...
Draw the reaction diagram from starting material to product of your specific reagent. This is for...
Draw the reaction diagram from starting material to product of your specific reagent. This is for aldol condensation using NaOH and ethanol along with benzaldehyde and a simple ketone, 3-Pentanone
Mahmood company needed 3,700 units of raw material every month starting from January till June due...
Mahmood company needed 3,700 units of raw material every month starting from January till June due to the orders which it has received from a customer and also to satisfy the regular demand the company has.The company started to place its order with different suppliers as it was not able to find a single supplier to satisfy all its needs. They have to procure the raw materials from different suppliers at the prevailing market price. In the month of January...
Case A Case B Case C Beginning inventory, raw material 96,000 7,000 Ending inventory, raw material...
Case A Case B Case C Beginning inventory, raw material 96,000 7,000 Ending inventory, raw material 198,000 33,000 Purchases of raw material 290,000 273,000 Direct material used 230,000 321,000 Direct labor 390,000 71,500 Manufacturing overhead 590,000 98,000 Total manufacturing costs 1,130,000 1,125,000 217,000 Beginning inventory, work in process 88,000 78,000 Ending inventory, work in process 123,000 4,300 Cost of goods manufactured 1,086,000 220,000 Beginning inventory, finished goods 190,000 138,000 Cost of goods available for sale 235,000 Ending inventory, finished goods...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT