Question

In: Finance

3. Consider a project with a 6-year life. The initial cost to set up the project...

3. Consider a project with a 6-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 6 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project.

You estimated sales of 57,000 units per year at a price of $167 each. The variable cost per unit is estimated to be $133.6 and fixed costs are $240,000 per year.

You expect unit sales, prices, variable and fixed costs to be within 15% of your estimates.

The required return is 12% and the tax rate is 34%.

You expect unit sales, prices, variable and fixed costs to be within 15% of your estimates.

The required return is 13% and the tax rate is 34%.

1)What is the NPV in the base case?

2) What is the NPV in the pessimistic case?

3)What is the NPV in the optimistic case?

Solutions

Expert Solution

1) At first we calculate Initial outlay of the project

Initial outlay = Cost of the machine + Net working Capital

Hence initial outlay = 1200000 + 120000 = 1320000

Depreciation each year is 1200000/6=200000

Now let's calculate Cash flow after tax = (sales - Cost- Depreciation)*(1-t) + depreciation

= (9519000-7615200-240000-200000)(1-.34) + 200000

=1166108

Now let's calculate terminal cash flow= post tax salvage value + working capital

= 240000*.66+120000=278400

This terminal cash flow will be received at the end of 6 years

Now NPV = Cash inflow/(1+i)t - initial outlay

i = 12% t= time period

Hence by applying the above formula we get NPV =3615391

2) Pessimistic Case( sales, variable cost and fixed cost be 15% less than the estimate)

Here only cash flow after tax will change, the rest i.e initial investment and terminal cash flow will remain same.

Therefore sales =9519000*.85=8091150

Variable cost =7615200*.85=6472920

Fixed cost = 240000*.85=204000

Cash flow after tax= (8091150-6472920-204000-200000)(1-.34)+200000=1001391

Hence by applying the above formula of NPV taking i= 12% we get NPV =$2938172

3) NPV in optimistic case( sales ,variable cost and fixed cost will be 15% more than the estimate)

Here also only cash flow after tax will change and rest will remail same

Sales =9519000*1.15= 10946850

Variable cost =7615200*1.15= 8757480

Fixed cost = 240000*1.15=276000

Hence cash flow after tax = (10946850-8757480-276000-200000)(1-.34)+200000 = 1330824

Hence by applying the above formula for NPV(taking i= 12%) we get NPV =$4292606


Related Solutions

Consider a project with a 6-year life. The initial cost to set up the project is...
Consider a project with a 6-year life. The initial cost to set up the project is $450,000. This amount is to be linearly depreciated to zero over the life of the project. The firm expects to be able to sell the equipment for $90,000 after 6 years. The price per unit is $380, variable costs are $304 per unit and fixed costs are $45,000 per year. The project has a required return of 12% and a tax rate of 28%....
Consider a project with a 6-year life. The initial cost to set up the project is...
Consider a project with a 6-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 6 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 63,000 units per year at a price of $160 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 52,000 units per year at a price of $177 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 52,000 units per year at a price of $177 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 77,000 units per year at a price of $137 each. The...
Consider a project with a 5-year life. The initial cost to set up the project is...
Consider a project with a 5-year life. The initial cost to set up the project is $100,000. This amount is to be linearly depreciated to zero over the life of the project and there is no salvage value. The required return is 13% and the tax rate is 34%. You've collected the following estimates: Base case Pessimistic Optimistic Unit sales per year (Q) 8,000 6,000 10,000 Price per unit (P) 50 40 60 Variable cost per unit (VC) 20 35...
Consider the project where the initial cost is $200,000, and the project has a 5-year life....
Consider the project where the initial cost is $200,000, and the project has a 5-year life. There is no salvage. Depreciation is straight-line (Depreciation = 200,000/5 = 40,000) Unit Sales = 6000, Price per unit = $80 (Sales = 6,000 x 80) Variable cost per unit = $60 (Variable Costs = 6,000 x 60)The required return is 12%, and the tax rate is 21%  What are the cash flow each year, NPV and IRR in each case, if we...
Abandonment option: Consider a 3-year project with a 14.00% cost of capital. The initial investment is...
Abandonment option: Consider a 3-year project with a 14.00% cost of capital. The initial investment is $1,000 and the expected cash flows are $400 per year. a. Calculate NPV and determine whether or not to undertake this project. b. Suppose instead that we have more information on the expected cash flows. First, there is a 40.00% probability that the project is a success and the cash flows will be $700 and a 60.00% probability that the project is a failure...
Aramark is considering a 3-year project with an initial cost of $570,000. The project will not...
Aramark is considering a 3-year project with an initial cost of $570,000. The project will not directly produce any sales but will reduce operating costs by $147,000 a year. The equipment is classified as MACRS 7-year property. The MACRS table values are .1429, .2449, .1749, .1249, .0893, .0892, .0893, and .0446 for Years 1 to 8, respectively. At the end of the project, the equipment will be sold for an estimated $295,000. The tax rate is 25 percent and the...
A firm is considering a project with a 5-year life and an initial cost of $1,000,000....
A firm is considering a project with a 5-year life and an initial cost of $1,000,000. The discount rate for the project is 10%. The firm expects to sell 2,500 units a year for the first 3 years. The after-tax cash flow per unit is $120. Beyond year 3, there is a 50% chance that sales will fall to 900 units a year for both years 4 and 5, and a 50% chance that sales will rise to 3,000 units...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT