Question

In: Operations Management

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts,...

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. (Leave the cells blank, whenever zero (0) is required.)

WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements 77 52 75
On-hand 47
Net requirements
Planned-order receipt
Planned-order release
Period 1 2 3 4 5

Item: J

OH: 47

LT: 1

SS: 0

Q: L4L

Gross requirements 77 52 75
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

Solutions

Expert Solution

Below is the screenshot of the MRP schedule -

J
LT 1
Q = L4L
On Hand 1 2 3 4 5
Gross Requirement 0 77 0 52 75
Scheduled Receipts 0 0 0 0 0
Projected on Hand 47 47 0 0 0 0
Net Requirements 0 30 0 52 75
Planned Order Receipts 0 30 0 52 75
Planned Order Releases 30 0 52 75 0

Below is the screenshot of the formula applied -


Related Solutions

Given the following MRP record and an EOQ of 200 units, calculate the planned order receipts...
Given the following MRP record and an EOQ of 200 units, calculate the planned order receipts using the economic order quantity. Next, calculate the period order quantities and the planned order receipts. In both cases, calculate the ending inventory and the total inventory carried over the 10 weeks. Please show all work Week 1 2 3 4 5 6 7 8 9 10 Total Net Requirements 75 70 60 0 100 80 70 65 0 80 Planned Order Receipt Ending...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine...
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
How would you respond to this post? Material Requirements Planning (MRP) is the process used for...
How would you respond to this post? Material Requirements Planning (MRP) is the process used for calculating the materials required to manufacture a product.  A common approach companies use is called just in case inventory which requires huge inventories to stock all materials needed for manufacturing a product before they are required (Vonderembse, 2013).  This process may sound like a great idea but is very costly in requiring extensive warehouse space and monies tied up in inventory.  If companies that utilize MRP they...
Materials Requirements Planning QUESTION An MRP exercise is being implemented over an 8-week period and the...
Materials Requirements Planning QUESTION An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B and three (3) units of C. One (1) unit of B is made up of three (3) units of D and two (2) units of E. One(1) unit of C is made up of two (2) units of B and two (2) units of D. Items...
Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and...
Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B, two (2) unit of C, and two (2) units of D. B is composed of two (2) units of E and one (1) unit of D. C is made of two (2) units of B and three (3) units of E. E is made of...
Required: Supply the correct amount for each numbered item on the schedule. Round each answer to...
Required: Supply the correct amount for each numbered item on the schedule. Round each answer to the nearest dollar.(AICPA adapted) Property, plant, and equipment and intangible assets; comprehensive The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2014. The accounting department of Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing this schedule. In addition to ascertaining that the data already on the schedule are correct, you...
For each of the following, situations, indicate whether Kanban or MRP would be more effective. An...
For each of the following, situations, indicate whether Kanban or MRP would be more effective. An automobile plant producing three styles of vehicles (0.8 point) A custom job shop (0.8 point) A circuit board plant with 40,000 active part numbers (0.8 point) A circuit board with 12 active part numbers (0.8 point) A plant with one assembly line where all parts are purchased (0.8 point)
For each point a) to j) below here, please indicate the correct assertion being tested and...
For each point a) to j) below here, please indicate the correct assertion being tested and type audit evidence! a) The depreciation period of the building has been recorded and count correctly b) The vehicle in the statement of financial position do indeed belong to the company c) Long-lived asset that are used as collateral for debt must be disclosed in the notes to the financial statements d) Plantation Land of branch offices which are located in remote place indeed...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT