Question

In: Advanced Math

Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and...

Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B, two (2) unit of C, and two (2) units of D. B is composed of two (2) units of E and one (1) unit of D. C is made of two (2) units of B and three (3) units of E. E is made of two (2) units of F. Items B, C, and E have one (1) week lead times; A and F have lead times of two (2) weeks; D has lead time of three( 3) weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B and F; lots of size fifty (50), fifty (50) and one hundred (100) are used for Items C, D and E respectively. Items C, E and F have on-hand (beginning) inventories of twenty (20),fifty (50) and fifty(50), respectively; all other items have zero beginning inventory. We are scheduled to receive ten (10) units of A in Week two (2), fifty (50) units of E in Week one (1), and also one hundred (100) units of F in Week one ( 1). There are no other scheduled receipts.

a) Draw the product structure tree with low level coding [5 marks]

b) Draw the corresponding time-phased diagram showing lead times to scale. [5 marks

] c) If forty (40) units of A are required in Week eight (8), determine the necessary planned order releases for all components {6 schedules}

Solutions

Expert Solution

C) Planned order release for all components are following


Related Solutions

Materials Requirements Planning QUESTION An MRP exercise is being implemented over an 8-week period and the...
Materials Requirements Planning QUESTION An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B and three (3) units of C. One (1) unit of B is made up of three (3) units of D and two (2) units of E. One(1) unit of C is made up of two (2) units of B and two (2) units of D. Items...
An MRP exercise is being implemented over an 8-week period and the following relevant information is...
An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B and three (3) units of C. One (1) unit of B is made up of three (3) units of D and two (2) units of E. One(1) unit of C is made up of two (2) units of B and two (2) units of D. Items A, C and E...
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
How would you respond to this post? Material Requirements Planning (MRP) is the process used for...
How would you respond to this post? Material Requirements Planning (MRP) is the process used for calculating the materials required to manufacture a product.  A common approach companies use is called just in case inventory which requires huge inventories to stock all materials needed for manufacturing a product before they are required (Vonderembse, 2013).  This process may sound like a great idea but is very costly in requiring extensive warehouse space and monies tied up in inventory.  If companies that utilize MRP they...
a. A key element in Materials Resource Planning (MRP) in a production environment is ‘Safety Stock’....
a. A key element in Materials Resource Planning (MRP) in a production environment is ‘Safety Stock’. Why is it necessary to maintain a safety stock of end items and lower level items, despite the availability of sophisticated tools and techniques for MRP? Give one example of safety stock for end item, and one example of safety stock for lower level item. b. What is analogous to safety stock in ‘services operations’ environment?
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT