In: Operations Management
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast between dependent and independent demand:-
Independent demand | Dependent demand |
These demands are stable once allowances are made for seasonal variations, | These demands are generally for product required for sub-assembly. |
These are the demand for items that are considered end goods which directly goes to customer. | Dependent demands are the demand for items that are used to make another items and sometimes considered to be parts of another items. |
Independent demand is influenced by market conditions and is not related to inventory decisions. | In case of dependent demand production depends upon the materials its made up of. |
MRP that is Material requirements planning is a production planning and inventory control system. It integrates data from production schedules. Basically it is a computerized system used to develop plans for ordering and producing dependent demand items. MRP uses two basic principles:-