An MRP exercise is being implemented over an 8-week period and the following relevant information is provided:

One (1) unit of A is made of two (2) units of B and three (3) units of C. One (1) unit of B is made up of three (3) units of D and two (2) units of E. One(1) unit of C is made up of two (2) units of B and two (2) units of D. Items A, C and E have one (1) week lead time. Items B and D have lead times of two (2) weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, C and E and a lot size of 100 is used for items B and D. Items A and D have beginning inventories of twenty (20) and forty ( 40) units respectively; all other items have zero beginning inventory. We are scheduled to receive ten (10) units of item B in week two (2) and twenty (20) units of item D in week one (1). There are no other scheduled receipts.

  1. Draw the product structure tree with low level coding. [5 marks]
  2. Draw the corresponding time-phased diagram showing lead times to scale. [5 marks]
  3. If fifty (50) units of A are required in Week eight (8), determine the necessary planned order releases for all components {five(5) schedules} [15 marks]

Solutions

Expert Solution

(a)

(b)

(c)

Item: A Week 1 2 3 4 5 6 7 8
OH = 20 Gross requirements 0 0 0 0 0 0 0 50
LT = 1 Scheduled receipts 0 0 0 0 0 0 0 0
Q = L4L Projected ending inventory 20 20 20 20 20 20 20 20 0
Net requirements 0 0 0 0 0 0 0 30
Planned receipts 0 0 0 0 0 0 0 30
Planned orders 0 0 0 0 0 0 30 0
Item: B Week 1 2 3 4 5 6 7 8
OH = 0 Gross requirements 0 0 0 0 0 0 240 0
LT = 2 Scheduled receipts 0 10 0 0 0 0 0 0
Q = 100* Projected ending inventory 0 0 10 10 10 10 10 70 70
Net requirements 0 0 0 0 0 0 230 0
Planned receipts 0 0 0 0 0 0 300 0
Planned orders 0 0 0 0 300 0 0 0
Item: C Week 1 2 3 4 5 6 7 8
OH = 0 Gross requirements 0 0 0 0 0 0 90 0
LT = 1 Scheduled receipts 0 0 0 0 0 0 0 0
Q = L4L Projected ending inventory 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 0 90 0
Planned receipts 0 0 0 0 0 0 90 0
Planned orders 0 0 0 0 0 90 0 0
Item: D Week 1 2 3 4 5 6 7 8
OH = 40 Gross requirements 0 0 0 0 900 180 0 0
LT = 2 Scheduled receipts 20 0 0 0 0 0 0 0
Q = 100* Projected ending inventory 40 60 60 60 60 60 80 80 80
Net requirements 0 0 0 0 840 120 0 0
Planned receipts 0 0 0 0 900 200 0 0
Planned orders 0 0 900 200 0 0 0 0
Item: E Week 1 2 3 4 5 6 7 8
OH = 0 Gross requirements 0 0 0 0 600 0 0 0
LT = 1 Scheduled receipts 0 0 0 0 0 0 0 0
Q = L4L Projected ending inventory 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 600 0 0 0
Planned receipts 0 0 0 0 600 0 0 0
Planned orders 0 0 0 600 0 0 0 0

Related Solutions

Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and...
Question 2 Materials Requirements Planning An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B, two (2) unit of C, and two (2) units of D. B is composed of two (2) units of E and one (1) unit of D. C is made of two (2) units of B and three (3) units of E. E is made of...
An MRP exercise is being implemented over an 8-week period and the following relevant information is...
An MRP exercise is being implemented over an 8-week period and the following relevant information is provided: One (1) unit of A is made of two (2) units of B and three (3) units of C. One (1) unit of B is made up of three (3) units of D and two (2) units of E. One(1) unit of C is made up of two (2) units of B and two (2) units of D. Items A, C and E...
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
Contrast dependent and independent demand, and trace the development of material requirements planning (MRP)
a. A key element in Materials Resource Planning (MRP) in a production environment is ‘Safety Stock’....
a. A key element in Materials Resource Planning (MRP) in a production environment is ‘Safety Stock’. Why is it necessary to maintain a safety stock of end items and lower level items, despite the availability of sophisticated tools and techniques for MRP? Give one example of safety stock for end item, and one example of safety stock for lower level item. b. What is analogous to safety stock in ‘services operations’ environment?
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
The patient came to your exercise sessions 80% of the time during the 8 week period....
The patient came to your exercise sessions 80% of the time during the 8 week period. Since she only needed to comply by 70%, she was granted the lap band surgery. After 12 weeks, she has lost 50 pounds and has eliminated her insulin and cholesterol medications but is still on the hypertension meds. Her knees also are starting to feel better. You meet with this person post-surgery for an exercise assessment and the post surgery program. This time, she...
Freight car loadings over an 18-week period at a busy port are as follows: Week Number...
Freight car loadings over an 18-week period at a busy port are as follows: Week Number Week Number Week Number 1 360 7 430 13 505 2 375 8 450 14 515 3 390 9 470 15 545 4 375 10 455 16 560 5 390 11 475 17 575 6 400 12 495 18 590 a. Determine a linear trend line for expected freight car loadings. YˆY^ =  +  t b. Use the above trend equation to predict expected loadings for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT