Questions
What are some key things to consider when preparing to conduct a topographic survey? With the...

What are some key things to consider when preparing to conduct a topographic survey?

With the understanding that a higher resolution of data is going to generally cost more money, what is one suggestion you have to reduce the amount of time required to perform your proposed survey?

How many data points are necessary to provide an acceptable topographic survey? How might this vary based on the phase of the project (e.g., preliminary planning, construction drawings, final as-built drawings)?

What is one possible use of a topographic survey?

In: Civil Engineering

This is the previous example the answer is there in cgegg: A confined aquifer has been...

This is the previous example the answer is there in cgegg:

A confined aquifer has been fully penetrated with a well of 200 mm diameter The thickness of the aquifer is 25 m. If you know that the well was pumped at a constant rate of 2000 m3/day and the steady state drawdown in the well is 8 m and the drawdown in a piezometer 100 m from the well is 1.4 m. Calculate the following:

  1. Aquifer transmissivity, hydraulic conductivity of the aquifer material and the radius of influence of the well.
  2. If the aquifer is unconfined, Do the calculation again assuming that the saturated thickness is 25 m.

c. Assume the well efficiency is 85 %, calculate the values of T, K and R.

........Design the well in the previous example for the case of confined aquifer by finding the following:

  1. Screen length and size.
  2. Delivery pipe diameter.
  3. Calculate the power needed for this well.
  4. Draw schematic diagram for the well and define all parts.

Assume any missing data.

In: Civil Engineering

A rectangular cross section beam (A) made of steel constructed in an industrial building between two...

A rectangular cross section beam (A) made of steel constructed in an industrial building
between two columns which are “X” m apart. The beam is acting as a support for one end of
a pair of crane wheel (B). The distance b/w wheels are “Y” m. The crane is used to lift max.
of Z tonnes of load which is having hook at the centre of crane. Draw shear force and B.M
diagram of the beam.
Case i) If the crane wheels are positioned at equal distances from centre of the beam.
Case ii) If one of the crane wheels is exactly at the centre.
Case iii) If one of the crane wheels comes exactly over a column.
Also find the max. bending stresses in the beam for the first case considering the depth (d)
as twice the width of the beam.
where X=4.8m,Y=0.8, Z =9 tonnes, Depth (d) = 500mm

In: Civil Engineering

structure design A load that has been applied to a structure could sometimes be regarded as...

structure design
A load that has been applied to a structure could sometimes be regarded as favourable. Explain this concept with an example.

In: Civil Engineering

A client needs to fill and compact a trench that has the following dimensions 150 x...

A client needs to fill and compact a trench that has the following dimensions 150 x 50 x 1.5 ft. The sub is going to use a dump truck that can carry 12 CY, and travels at an average speed of 40 mph. The borrow pit is located 45 miles from the construction site. The truck driver makes $50/hr and works 8 hours per day. Loading time for the truck is 30 minutes and unloading time is 5 minutes. The sub has to rent the truck at $500 per day + a driver @ $50/hour. The cost of soil $20 per BCY. The soil has a swell factor of 18% and a compaction factor of 12%. What will it cost to backfill this trench if the sheeps foot operator make the same as the driver and fuel cost $1,250.00?

In: Civil Engineering

The columns for a building in central Long Island are to be made of concrete with...

The columns for a building in central Long Island are to be made of concrete with the
following specifications:
• Design compressive strength: 4500 psi, based on 20 tests of samples having a
standard deviation of 600 psi
• Non-air entrained, and clear space between rebar: 1.5 inch
• Fine aggregate: G = 2.350, FM = 2.5
• Coarse aggregate: G = 2.65, bulk density = 3000 lb/cy

Determine the following:
i. w/c ratio, largest nominal max. coarse aggregate size, % coarse aggregate, % air
(2 pts.)
ii. weight of water, weight of cement, and weight of coarse aggregate to be used per
cubic yard of concrete (1 pt.)
iii. weights and volumes of water, cement, air, coarse aggregate, and fine aggregate
needed to mix a 15-yard batch of this mix (3 pts.)
Also:
• Specify two admixtures that might be used for this mix based on the provided
information, and why to use it. (2 pts.)
• Why we might create a composite of this concrete poured into a PVC (polyvinyl
chloride) sleeve for these columns? (Give specific reasons based on the
characteristics of the individual materials.) (2 pts.)

In: Civil Engineering

The columns for a building in central Long Island are to be made of concrete with...

The columns for a building in central Long Island are to be made of concrete with the following specifications: • Design compressive strength: 4500 psi, based on 20 tests of samples having a standard deviation of 600 psi • Non-air entrained, and clear space between rebar: 1.5 inch • Fine aggregate: G = 2.350, FM = 2.5 • Coarse aggregate: G = 2.65, bulk density = 3000 lb/cy Determine the following: i. w/c ratio, largest nominal max. coarse aggregate size, % coarse aggregate, % air (2 pts.) ii. weight of water, weight of cement, and weight of coarse aggregate to be used per cubic yard of concrete (1 pt.) iii. weights and volumes of water, cement, air, coarse aggregate, and fine aggregate needed to mix a 15-yard batch of this mix (3 pts.) Also: • Specify two admixtures that might be used for this mix based on the provided information, and why to use it. (2 pts.) • Why we might create a composite of this concrete poured into a PVC (polyvinyl chloride) sleeve for these columns? (Give specific reasons based on the characteristics of the individual materials.) (2 pts.)

In: Civil Engineering

PROBLEM 5 If the general contractor of a project fails to pay its subcontractors, the subcontractors...

PROBLEM 5

If the general contractor of a project fails to pay its subcontractors, the subcontractors may file a lien against the owner’s property, and the project owner is required to pay the subcontractors. To avoid the lien against the property and payment to the subcontractors, what measures could the owner do?

In: Civil Engineering

Discuss in detail at least five benefits that can result from safe design of drainage pipes...

Discuss in detail at least five benefits that can result from safe design of drainage pipes and culverts

In: Civil Engineering

1. VECTOR PROBLEM: The helicopter travels to accommodate the tourists among the three islands of the...

1. VECTOR PROBLEM: The helicopter travels to accommodate the tourists among the three islands of the Philippines. It moves from the first island going to the second island with a distance of 4.76 km, 37° N of E. It then sails from the second island going to the last island in a direction of 69° W of N. Lastly, the helicopter goes back to the first island pointing in the direction of 28° E of S. Solve for the distance travelled:

(a) from second to third island; and

(b) from the first to third island

In: Civil Engineering

If a batch of parts made from a precipitation hardenable alloy have been overaged, they can...

If a batch of parts made from a precipitation hardenable alloy have been overaged, they can be salvaged by

In: Civil Engineering

When the amount that has been earned (BCWP) is consistently below the actual cost to date...

  1. When the amount that has been earned (BCWP) is consistently below the actual cost to date (ACWP), it can be concluded that the project is under cost.

True

False

QUESTION 2

16.6       The main purpose of an audit of a construction company’s financial statements is to:

Confirm that the statement was prepared in accordance with GAAP rules

Prepare income tax returns

Check the arithmetic used in the financial statement

Find employee malfeasance

QUESTION 3

16.5       From the project lifecycle, we can learn all of the following except:

Early CM involvement helps to optimized time and cost management

Material and labor expenditures should be leveled to manage cash flow

Project risk declines with time

Cost of change increases with time

QUESTION 4

16.3       Which of the following best describes the challenges in managing demobilization?

Managing labor productivity for smaller, fussier tasks and managing worker expectations

Maintaining the project owner's attention

Slow government approvals

Subcontractors are unwilling to complete work until finally paid

QUESTION 5

16.1       When the amount that has been earned (BCWP) is consistently below the amount that was supposed to be earned (BCWS), it can be concluded that the project is behind schedule.

True

False

QUESTION 6

16.7      Cost estimating and the resulting data are used for all purposes except:

    Financial Management of the CM Company


       Planning the project


    Monitoring and controlling costs


      Costing to win the project


  1. 16.4       Closeout procedures can also benefit the construction manager’s long-term performance in all ways except:

       Lessons learned from the project can improve performance on similar future projects.


The closeout documents are the construction manager's property, so the owner must work with the construction manager when future renovations or additions are performed

      The closeout interview between senior construction management personnel and the project owner increases the likelihood of future construction work.


    Retention of excellent contract document records can benefit the project owner in future renovations.

In: Civil Engineering

The Environment Bureau of HKSAR Government has recently proposed legislation for the proper management of waste...

The Environment Bureau of HKSAR Government has recently proposed legislation for the proper management of waste electrical and electronic equipment (Hong Kong WEEE) in Hong Kong, and has consulted public views. Do you think Hong Kong WEEE should copy from the EU WEEE or China WEEE Directives? Justify your answers in 6 bullet points (or short paragraphs).

In: Civil Engineering

Give a real world example where a structure collapsed or became structurally unsafe, or settled excessively...

Give a real world example where a structure collapsed or became structurally unsafe, or settled excessively due to insufficient soil strength.

In: Civil Engineering

What soil type or types are most prone to frost heave and why? What are the...

  1. What soil type or types are most prone to frost heave and why? What are the conditions that can lead to frost heave?

In: Civil Engineering