In: Civil Engineering
Explain concisely the physical meaning of total stress, pore water pressure and effective stress
In: Civil Engineering
2) What is “NFPA 704 hazard diamond”? Provide the image, and explain briefly.
In: Civil Engineering
An I-section joist 450 mm x 250 mm x 20 mm is used as a strut
with one end fixed and the other end free carrying a buckling load
of 200 × 106 N. Suggest the changes to be made in the length of the
strut for a constant flexural rigidity by considering both the ends
to be hinged, both the ends to be fixed and one end fixed but the
other end hinged. Compare the values of the safe buckling load for
all end conditions. Given modulus of elasticity of the material, E
= 210 GPa and consider factor of safety = 5.
If the least radius of gyration of the column was found to be 25.96
mm, determine the values for the slenderness ratio for all four end
conditions of the column. State and verify the validity of the
Euler’s column theory based on the slenderness ratio for all the
four end conditions.
In: Civil Engineering
What factors must be considered and what limitations exist for the following loops
Slinky:
Pond:
Horizontal:
Vertical:
In: Civil Engineering
In: Civil Engineering
A section of a multilane highway is to be reconstructed to improve the level of service. The section being considered is on a 5.0% upgrade that is 3/4 mile long. The highway currently has 4-lanes (2 in each direction – all are 12-ft lanes) with a two-way left-turn lane in the middle and 4 foot shoulders on the right side. It is to be reconstructed into a 6-lane facility (3-lanes in each direction) undivided facility but, due to commercial development surrounding the highway, must remain in the current 72 foot right of way. There are currently 35 access points per mile and the free flow speed is determined to be 50 mi/h. It is known that the road currently operates at capacity with 420 trucks/buses (no recreational vehicles) during the peak hour, a peak hour factor of 0.95 and all-commuter traffic.
The redesign is to reduce the number of access points per mile to 10 and to reduce the grade to 4.0% for 3/4 mile. It is estimated that the new design will increase traffic by 13%.
In: Civil Engineering
During construction, field tests were conducted to assess the
suitability of the column to
withstand a safe buckling load of 2.5 kN assuming a factor of
safety 4 using two different hollow
columns made up of steel and concrete. Both columns have same cross
section but varying length
and different support conditions. Steel column of length 3 m having
external diameter 40 mm was
tested with one end fixed and the other end hinged, when subjected
to a compressive stress of
0.0045 MN/cm2 shortens by 3.6 mm.
If the concrete column was tested under similar loading conditions
with one end fixed and other
end free considering modulus of elasticity of concrete equal to 128
GPa, what will be the
corresponding length of the column required? As a design engineer
how do you choose the values
for the thickness of both columns and the length of the concrete
column? What will be your
interpretations regarding the relationship between the support
conditions and the buckling load
based on the test results?
In: Civil Engineering
Results obtained from a tension test on a bar of uniform cross
section 10 mm x 10 mm
subjected to an axial pull of 8000 N were tabulated. The lateral
dimensions of the bar were found
to be changed to 9.9985 mm x 9.9985 mm while using a material
having modulus of rigidity equal
to 0.8 x 107 N/cm2. By determining the values for different moduli,
identify the properties of
material and establish the relationship between them. What changes
will happen to the volume if
the length of the bar is equal to 2.5 m? Based on the results
obtained discuss how the elastic
constants are related to the deformation of the bar?
In: Civil Engineering
There is a project with three activites planned for a
year (Units are in Rial)
• ‘Activity A’ with a planned cost of 2100,
• ‘Activity B’ with a planned cost of 1500 and
• ‘Activity C’ with a planned cost of 2500.
• Activity A turned out to be more expensive (with an additional
300).
• ‘Activity B’ was done as budgeted.
• ‘Activity C’ is not finished within the year, and only 1500 was
spent on it.
• An additional activity ‘Activity D’ was needed and performed with
a cost of 500.
What is the cost variance for the given year?Also write a detailed
conclusion on the
cost performance
In: Civil Engineering
Apple LLC decides that it is going to bid on some government work. All contractors must post a bid bond when bidding on government work. Apple bids on the government work and wins. Apple posts a payment bond, as per the contract, and starts to work. After about 2 years into the job, Apple walks off the job, which was left uncompleted. Can the government collect the bond?
1. Yes, the government can collect on the bid bond that Apple took out
2. No, there is no bond available here that the government could collect on
3. No, the surety must be given the chance to mitigate their losses first
4. Yes, Apple guaranteed its work.
In: Civil Engineering
QUESTION 1
Construction professionals who came from various specialty are brought together for a specific construction project and then disbanded once construction is complete.
TASK |
QUESTION 2
Site Preparation is the first step taken to start a new project to ensure the ground is safe to undertake construction works.
TASK |
QUESTION 3
Common building components are super structures and sub structures that was classified based on occupancy and structure, design loads, common building components, their function and nominal dimensions.
TASK
o Pad or raft foundation component o Column and beam component o Flooring component o Opening (door and window) component o Wall component o Roof component
QUESTION 4
Building construction is an ancient human activity. It began with the purely functional need for a controlled environment to moderate the effects of climate. Constructed shelters were one means by which human being were able to adapt themselves to a wide variety of climates and become global species.
TASK
o Substructure – foundation o Superstructure – floor, column, beam, ceiling and roof o Components – window and door
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering