How does water in the granular backfill in the wall change /affect the design of an MSE wall?
a) Unit weight of granular fill
b) Total overturning/sliding forces
c) Corrosion rate of reinforcement
d) What would be your choice of soil behind the wall to minimize water-related problems.
In: Civil Engineering
What is the purpose of instrumentation of deep excavation projects? Explain briefly the following instruments and state what they measure.
a) Inclinometers
b)Piezometers
c)Extensometers
d)Strain gauges
In: Civil Engineering
A 15-m simply supported beam is subjected to a
uniformly increasing load of zero, 3m from the left support, to
30kN/m at the right support. A 20kN point load is also acting 1
meter from the left support. The cross section of the beam is 500mm
x 800mm. Assume that tendons are applied in constant eccentricity
of e = 150mm. Determine:
Moment at midspan
Maximum Moment
Stress of the section where moment is maximum, assuming the effective Jacking Force to be 1000kN. Use three Methods:
Basic-concept Method
Load-Balancing Method
C-line Method
In: Civil Engineering
Lightweight Aggregate Production
1-how much of the materials should be melted at the sintering temperature selected in light aggregate production(what extent should the melting minerals?(feldspars etc.), how many of them protected their solid structures(water should not exceed)) What should these values be for minimum grain density and maximum compressive strength? Which materials can be used in this sense? how lightness and strength are affected when flying ash is used?
2-What should be optimum aggregate diameter in lightweight aggregate production? how the strength is affected when the size increases? how grain density is affected when the size increases?Why is that?According to which standard to lightweight aggregate strength test?
3-What is the effect of sintering time and temperature in light aggregate production
4-What should be the most appropriate drying process in light aggregate production?Why is that? Provide information on changes in light aggregate with drying(volume,strength etc.)
In: Civil Engineering
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
In: Civil Engineering
In: Civil Engineering
a) What is the best material to build a base and frame for a trebuchet other than using oak? Provide reasons and explanation. if possible, consider the price of the material
b) What is the best material to build an arm material for a trebuchet other than using pine wood? Provide reasons and explanation. If possible, consider the price of the material
In: Civil Engineering
QUESTION 5
If the flow hydrograph as listed in the Table Q5 passes through a stream reach from A to B, for which K = 8.0 hr and x = 0.3
Table Q5
Time (hr) |
0 |
6 |
12 |
18 |
24 |
30 |
36 |
42 |
48 |
54 |
60 |
66 |
Inflow (m3 /s) |
40 |
65 |
165 |
250 |
240 |
205 |
170 |
130 |
115 |
85 |
70 |
50 |
In: Civil Engineering
write a research about maintenance and technical issues in running a wastewater treatment plant .
In: Civil Engineering
Q
QUESTION 2
The data in the table below was produced by a storm of 2-hour duration considered to have uniform intensity over a catchment. If the catchment area is 10,400 hectare, determine the unit hydrograph for the catchment.
Use fixed base separation method for the baseflow separation.
Table Q2
Time |
Flows, Q |
(hour) |
(m3/s) |
0600 |
40 |
0800 |
35 |
1000 |
170 |
1200 |
260 |
1400 |
266 |
1600 |
226 |
1800 |
188 |
2000 |
157 |
2200 |
130 |
2400 |
108 |
2600 |
91 |
2800 |
76 |
3000 |
64 |
3200 |
54 |
3400 |
46 |
3600 |
38 |
3800 |
32 |
4000 |
27 |
In: Civil Engineering
QUESTION 1
The daily stream flow data for a particular catchment having an area of 6500 km2 are given in the table below. Separate the baseflow using Straight line method, Fixed base method, and recession Separation method.
Calculate the total direct runoff for each method.
Table Q1
Time |
Flows, Q |
(days) |
(m3/s) |
1 |
1 600 |
2 |
1 550 |
3 |
5 000 |
4 |
10 300 |
5 |
8 600 |
6 |
6 500 |
7 |
5 000 |
8 |
3 800 |
9 |
2 800 |
10 |
2 200 |
11 |
1 850 |
12 |
1 600 |
13 |
1 330 |
14 |
1 300 |
15 |
1 280 |
In: Civil Engineering
Year |
Pi(cm) |
Year |
Pi(cm) |
1999 |
44.2 |
2010 |
39.2 |
2000 |
47.6 |
2011 |
38.3 |
2001 |
38.5 |
2012 |
46.1 |
2003 |
35.8 |
2013 |
33.1 |
2004 |
40.2 |
2014 |
35.0 |
2005 |
41.2 |
2015 |
39.3 |
2006 |
39.8 |
2016 |
42.0 |
2007 |
39.7 |
2017 |
41.7 |
2008 |
40.5 |
2018 |
37.7 |
2009 |
42.5 |
2019 |
36.6 |
Please clarify each step of the solution.
In: Civil Engineering
Year |
Pi(cm) |
Year |
Pi(cm) |
1999 |
44.2 |
2010 |
39.2 |
2000 |
47.6 |
2011 |
38.3 |
2001 |
38.5 |
2012 |
46.1 |
2003 |
35.8 |
2013 |
33.1 |
2004 |
40.2 |
2014 |
35.0 |
2005 |
41.2 |
2015 |
39.3 |
2006 |
39.8 |
2016 |
42.0 |
2007 |
39.7 |
2017 |
41.7 |
2008 |
40.5 |
2019 |
37.7 |
2009 |
42.5 |
2019 |
36.6 |
How many times was the P10 (normal) exceeded in the 20-year annual precipitation record given in Problem 1 ?
Please clarify each step of the solution
In: Civil Engineering
Compare AASHTO with the ASTM and come with a conclusion which one is more restricted? And do you think it is a valid restriction? And is the restriction valid for our infrastructure durability ?
In: Civil Engineering
In: Civil Engineering