Questions
A single-storey brick veneer house (single layer of brick on a timber frame) has a front...

A single-storey brick veneer house (single layer of brick on a timber frame) has a front corner lounge-room with a floorplan measuring 4.0 m by 3.8 m. The ceiling is 3.0 m high. The building fabric of the two exterior walls comprises a 12 mm thick layer of plaster, a 100 mm air gap and the exterior house bricks (110 mm thick). One of these walls has a window measuring 2.7 m wide by 1.35 m high, featuring a 3-mm thick glass pane installed in the mid-1950s. The floor is carpet over 19 mm thick pine floorboards, and the house is on stumps with a ventilated air gap between the ground and the floorboards. The ceiling is 12 mm plasterboard covered with a 50 mm thick layer of loose fill insulation in the roof cavity. This house is located in suburban Melbourne.

Estimate the cost to heat the interior of this room to 21°C all year round using a mid-level residential gas central heating system. Assume the under-floor and roof cavity temperatures are equal to the outside temperature.

In: Civil Engineering

A building company has been awarded the contract to undertake the construction works for a multi-storey...

A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel.

The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis.

You have been asked by the contractor to advise their company with regard to a number of issues on the project, in advance of the construction works.

  1. (a) What details would you provide to the contractor in relation to the options and methods available to dewater the soil on the project, to facilitate both the basement construction and trench excavations for utility ducting installation on the site? How would the range of dewatering methods be combined to produce a suitable solution?

  2. (b) Given the basic information available in relation to the location and ground conditions on this site, describe the particular options that you would recommend to the contractor for use on this specific site to assist in supporting the sides of the deep excavations during the basement construction.

In: Civil Engineering

Procedure in lab work (without explanation) with formula to find the given properties of fluid: 1.Density,...

Procedure in lab work (without explanation) with formula to find the given properties of fluid:

1.Density, ρ         

2.Specific Density, γ

3.Specific Gravity, sg

4.Dynamic Viscosity, μ

5.Kinematic Viscosity, η

In: Civil Engineering

Assessment 9.0: Soil Mechanics Produce a 300 word report which identifies the cause and effect of...

Assessment 9.0: Soil Mechanics Produce a 300 word report which identifies the cause and effect of slips in embankments and cuttings and the affect it might have on safety of the line. The report should include the theory behind soil mechanics – soil saturation, subsidence, inappropriate mineral extraction, overloading of embankment by neighbouring construction and subterranean fires. Include a range of potential solutions to embankment stability risks.

Would prefer in Text as don't understand the handwriting on here.

In: Civil Engineering

1. Design a simply supported slab resting on masonry walls of thickness 250mm each with its...

1. Design a simply supported slab resting on masonry walls of thickness 250mm
each with its opposite edges supported (L = 4.75m). Take concrete grade
32MPa; steel grade 500N; permanent load (G) = 1.5kPa; imposed load (Q) =
2kPa; ψs = 0.7 & ψl
= 0.4; γconc = 25kN/m3
; ∆=span/500 (HOMEWORK)

In: Civil Engineering

Discuss the argument whether lumpsum is 100% risk free for the owner or not with an...

Discuss the argument whether lumpsum is 100% risk free for the owner or not with an
example.

In: Civil Engineering

The soil profile at a site consists of a clay layer 10 m thick, sandwich between...

The soil profile at a site consists of a clay layer 10 m thick, sandwich between two sand layers. The top sand layer has a density of 1.9 Mg/m3 and is 5 m thick. Below this layer is a 10 m thick clay layer with a saturated density of 1.8 Mg/m3 and a saturated water content 42%. The deeper sand layer has a saturated density of 1.9 Mg/m3 and extend to the depth investigated at the site. The water table was detected at the top of the clay layer.

The results of a consolidation test performed on a sample recovered from the mid point of the clay layer indicated the following properties for the clay:

Effective pre-consolidation pressure of 130 kPa;

Compression index Cc = 0.40;

Re-compression index Cr = 0.03; and

Consolidation coefficient Cv = 0.544 * 10-2 cm2/sec.

The site is being proposed to be graded by compacting an additional layer.

The new compacted layer will impose a total stress increment of 75 kPa on the present ground surface. It is desired to obtain the following information:

Estimate the ultimate consolidation settlement due to grading;

Estimate the time in weeks that it will take to reach the average degree of consolidation Uave = 90%; and

At the time calculated in 2.), estimate the excess pore pressure still present at the mid-point of the clay layer.

In: Civil Engineering

The soil profile at a site consists of a clay layer 10 m thick, sandwich between...

The soil profile at a site consists of a clay layer 10 m thick, sandwich between two sand layers. The top sand layer has a density of 1.9 Mg/m3 and is 5 m thick. Below this layer is a 10 m thick clay layer with a saturated density of 1.8 Mg/m3 and a saturated water content 42%. The deeper sand layer has a saturated density of 1.9 Mg/m3 and extend to the depth investigated at the site. The water table was detected at the top of the clay layer.

         The results of a consolidation test performed on a sample recovered from the mid point of the clay layer indicated the following properties for the clay:

  1. Effective pre-consolidation pressure of 130 kPa;
  2. Compression index Cc = 0.40;
  3. Re-compression index Cr = 0.03; and
  4. Consolidation coefficient Cv = 0.544 * 10-2 cm2/sec.

The site is being proposed to be graded by compacting an additional layer.

The new compacted layer will impose a total stress increment of 75 kPa on the present ground surface. It is desired to obtain the following information:

  1. Estimate the ultimate consolidation settlement due to grading;
  2. Estimate the time in weeks that it will take to reach the average degree of consolidation Uave= 90%; and
  3. At the time calculated in 2.), estimate the excess pore pressure still present at the mid-point of the clay layer.

In: Civil Engineering

1. A 3.5 m clear span singly reinforced cantilever beam has a rectangular section of b=300mm...

1. A 3.5 m clear span singly reinforced cantilever beam has a rectangular section of b=300mm and D=500
mm is reinforced with 2 bars of 32 mm diameter and 1 bar of 25mm diameter in the tension zone. The
live load taken by the beam is 19 kN/m. Check if the beam is safe to carry the above load . Use M25
and Fe500.

In: Civil Engineering

produce a drawing to show a cross section of track including rails, sleepers and substructure. •...

produce a drawing to show a cross section of track including rails, sleepers and substructure.
• on the drawing identity the requirements for ballast depth and show how the axel loading is distributed throughout the infrastructure.
• interpret the engineering standards applied by the infrastructure controller, and produce a table showing examples of  
different design requirements applicable for line speeds and gross axle tonnage.
• explain the gauging requirements of the track including the interface with OLE and /or DC conductor in terms of rail geometry.
• explain the common failure modes associated with track geometry defects.

In: Civil Engineering

Define the following terms in structural steel construction: Falsework Anchor bolt Shaking out Rigging Column Beam...

  1. Define the following terms in structural steel construction:
    1. Falsework
    2. Anchor bolt
    3. Shaking out
    4. Rigging
    5. Column
    6. Beam
    7. Girder
    8. Purlin
    9. Girt
    10. Gusset plate

In: Civil Engineering

A 600 mm diameter pipe carrying 0.9 m3/s of oil (RD 0.85) has a 90o bend...

A 600 mm diameter pipe carrying 0.9 m3/s of oil (RD 0.85) has a 90o bend in the horizontal plane. The loss of head due to the bend is 1 metre of oil and the pressure at the start of the bend is 300kPa. Calculate the magnitude and angle of the resultant force exerted by the oil on the bend.

In: Civil Engineering

what is QGIS software ? what are the uses of QGIS software in surveying how it...

what is QGIS software ? what are the uses of QGIS software in surveying how it used give one example in detail ?

i need an explannation about QGIS features uses and one example ?

In: Civil Engineering

Could a sluice gate be used as a flow measuring device? Comment on the performance of...

Could a sluice gate be used as a flow measuring device?

Comment on the performance of the gate as a flow measuring device under both conditions (drowned and free)

In: Civil Engineering

List 5 ways to improve labor productivity on a construction site ?

List 5 ways to improve labor productivity on a construction site ?

In: Civil Engineering