Which of the following statement is an incorrect observation from the Moody’s diagram?
For a given relative roughness, the friction factor increases with increasing Reynolds number until the zone of complete turbulence is reached. |
||
As the relative roughness increases, the value of the Reynolds number at which the zone of complete turbulence begins also increases. |
||
Within the zone of complete turbulence, the Reynolds number has no effect on the friction factor. |
||
For a given Reynolds number of flow, as the relative roughness is increased, the friction factor decreases. |
In: Civil Engineering
A piston–cylinder device contains steam that undergoes a reversible thermodynamic cycle. Initially the steam is at 400 kPa and 350oC with a volume of 0.3 m3. The steam is first expanded isothermally to 150 kPa, then compressed adiabatically to the initial pressure, and finally compressed at the constant pressure to the initial state. Determine (a) the net work and heat transfer for the cycle after you calculate the work and heat interaction for each process and (b) show the cyclic process on a PV diagram
In: Civil Engineering
How to assemble an Acceleration Response Spectra according to design code ASCE-7
In: Civil Engineering
A series of consolidated, undrained triaxial tests were carried out on specimens of a saturated clay under no back pressure. The test data at failure are summarized:
Confining pressure kPa Deviator stress kPa Pore water pressure kpa
150 192 80
300 341 154
450 504 222
A series of consolidated, undrained triaxial tests were carried out on specimens of a saturated clay under no back pressure. The test data at failure are summarized:
Confining pressure kPa Deviator stress kPa Pore water pressure kpa
150 192 80
300 341 154
450 504 222
In: Civil Engineering
In: Civil Engineering
What will be the length (L in meter) of a rectangular footing to support rectangular column 20x70 cm and carries a dead load of 625 kN and live load of 426 kN. The net allowable bearing pressure is 155 kPa. The design should be according to (ACI) code with the following parameters: fc’ = 28 MPa, fy = 420 MPa.
In: Civil Engineering
The parameter most often used to characterize the response of a catchment to a rainfall event is the time of concentration.
1 . What are the two commonly accepted definitions of the time of concentration?
2. Describe the various methods used to estimate the time of concentration.
In: Civil Engineering
In: Civil Engineering
A simply supported beam 10-m long is acted upon by a uniformly distributed dead load of 20 kN/m and a uniformly distributed live load of 48 kN/m throughout its span.
Design the footings of each columns located at the supports using the following data
Assume that:
Determine the following for the designed footings on the left and the right side of the beam:
BONUS:
In: Civil Engineering
In: Civil Engineering
a) List four steps employed in Deterministic Seismic Hazard Analysis (DSHA) method
b) How is Probabilistic Seismic Hazard Analysis (PSHA) different from Deterministic Seismic Hazard Analysis (DSHA)
In: Civil Engineering
a) Give reasons why moment magnitude Mw is the most common used method to define the size of an earthquake.
Data on a major earthquake are as follows:
· Depth of fault rupture is 25 km
· Length of the surface faulting is 800 km
· Average slip along the fault is 5 m
· Shear modulus of material along the fault plane is 2x1010 N/m2
b) Calculate the seismic moment, Mo
c) Compute the moment magnitude of the earthquake (note, Mo in dyne-cm; one Newton-m = 107 dyne-cm)
In: Civil Engineering
In: Civil Engineering
2) A circular sewer is to carry a flow rate of
0.07m3
/s when flowing full. The sewer is
to be laid on a slope of 0.006. With n = 0.013, calculate the pipe
size and velocity
of flow. Compare the nomogram and theoretical values.
In: Civil Engineering
Risk management is a key part of project management. List five key features of a road infrastructure risk management plan. Name three significant risks usually involved in a road project and briefly describe them. (Target length to answer this question is approximately 300 words)
In: Civil Engineering