Draw a network diagram and answer the questions below:
(Please show all your workings or explanation; simple answers alone
will not account for full marks)
• Activity 1 can start immediately and has an estimated duration of
three weeks.
• Activity 2 can start after activity 1 is completed and has an
estimated duration of three weeks.
• Activity 3 can start after activity 1 is completed and has an
estimated duration of six weeks.
• Activity 4 can start after activity 2 is completed and has an
estimated duration of eight weeks.
• Activity 5 can start after activity 4 is completed and after
activity 3 is completed. This activity takes four weeks.
. The resource working on activity 3 is replaced with another
resource who is less experienced. The activity will now take 10
weeks. How will this affect the project?
Questions are:
6. Using the original information, after some arguing between
stakeholders, a new activity 6 is added to the project. It will
take 11 weeks to complete and must be completed before activity 5
and after activity 3. Management is concerned that adding the
activity will add 11 weeks to the project. Another stakeholder
argues the time will be less than 11 weeks. Who is correct?
7. Based on the information in number 6 above, how much longer will
the project take?