Question

In: Operations Management

Below is a list of jobs that must be accomplished to complete the new project. Assume...

Below is a list of jobs that must be accomplished to complete the new project. Assume the company wants to complete the project as early as possible, a) what is the added project cost?

You need not to show the network diagram.

    

Activity

Immediate Predecessor

Normal Time (Days)

Crash Time (Days)

Normal Cost

Crash Cost

A

None

8

7

$45

$50

B

A

3

1

$60

$65

C

A

11

9

$110

$150

D

A

6

5

$50

$90

E

B

9

6

$90

$120

F

E

2

1

$20

$40

G

C, D

5

4

$80

$100

H

D

7

6

$70

$100

I

E, G

4

4

$40

$40

J

H

8

7

$110

$120

K

F, I, J

15

13

$150

$250

b) What is project management?

______________________________________________________________________________________________________________________________________________________

Solutions

Expert Solution

PLEASE RATE POSITIVE IF YOU LIKE MY ANSWER TO ENCOURAGE MY EMPLOYMENT

Activity Normal Time (A) Crash Time (B) Normal Cost ( C) Crash Cost (D) Crashing Cost
(D-C)
Slope =Crash cost per day
(D-C/A-B)
A 8 7 45 50 5 5
B 3 1 60 65 5 2.5
C 11 9 110 150 40 20
D 6 5 50 90 40 40
E 9 6 90 120 30 10
F 2 1 20 40 20 20
G 5 4 80 100 20 20
H 7 6 70 100 30 30
I 4 4 40 40 0
J 8 7 110 120 10 10
K 15 13 150 250 100 50
Path Pathlength
ABEFK 37
ABEIK 39
ACGIK 43
ADGIK 38
ADHJK 44
Crashing critical activity A with least slope
Path Pathlength
ABEFK 36
ABEIK 38
ACGIK 42
ADGIK 37
ADHJK 43
Crashing J
Path Pathlength
ABEFK 36
ABEIK 38
ACGIK 42
ADGIK 37
ADHJK 42
Crashing H, C and K
Path Pathlength
ABEFK 34
ABEIK 36
ACGIK 37
ADGIK 34
ADHJK 39
Crashing D and G
Path Pathlength
ABEFK 34
ABEIK 36
ACGIK 38
ADGIK 35
ADHJK 38
Further crashing will not reduce critical path length and hence no benefit of crashing further

Therefore added project cost is crashing cost of A,D,H,J,K, C and G

= 5+40+30+10+100+40+20

= $245 Answer

b)

Project management is the management of project activities using knowledge, skills, methods, tools and techniques to achieve the project activities in a controlled and planned fashion. It is a process-driven approach to plan, manage and organize the efforts to accomplish project activities


Related Solutions

What has Steve jobs accomplished in his lifetime
What has Steve jobs accomplished in his lifetime
The jobs listed below need to be completed. Assume that it is now day 140. If...
The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule and earliest due date rule, a. what is the job processing sequence for each rule? b. what is the average flow time for each rule? c. what is the utilization for each rule? d. what is the average job lateness for each rule? e. what is the average number of jobs in a...
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months Unit 4 Project: Activity Description Est $ Architectural Design 50,000...
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between...
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Which department is the bottleneck? Calculate the machine utilization?
Consider the table given below for a fixed memory allocation scheme: Given the jobs list information...
Consider the table given below for a fixed memory allocation scheme: Given the jobs list information and memory information in the table below, answer the questions that follow: Job Number Memory Requested                         Memory Block Memory Block Size Job 1 600 Block 1 1200 Job 2 920 Block 2 300 Job 3 1100 Block 3 930 Job 4 700 Block 4 950             (Assume all jobs are in a waiting queue in the order given, also assume that the memory...
Assume that for this project to be completed, five independent tasks must be completed. These tasks...
Assume that for this project to be completed, five independent tasks must be completed. These tasks are proceeding in parallel by five different subcontractors. To keep it simple, let's assume that each task takes between 1 and 5 months to complete (uniformly distributed, i.e. equally likely to take any amount of time between 1 and 5 months). So, the mean time to complete each task is 3 months and the probability of any given task taking 3 months or longer...
The thiosulfate tirant must be standardized. What does this mean and how is it accomplished? What...
The thiosulfate tirant must be standardized. What does this mean and how is it accomplished? What is a primary standard?
teams must be developed by management, how is this accomplished?  What are some strategies used?  
teams must be developed by management, how is this accomplished?  What are some strategies used?  
Choose from the following list of words to complete the paragraph below. Not all terms will...
Choose from the following list of words to complete the paragraph below. Not all terms will be used, and none of them can be used more than once. positive     intermediate     free   negative   substrate   product   activation   thermal An enzyme reduces the_____________ energy of a reaction, causing it to occur more frequently at a given temperature than it would otherwise. This does not alter the________ energy of the reactants or products. If the ΔG of a reaction is____________ , the reaction is spontaneous....
2. The more complete the transfer, the more likely tax goals will be accomplished. True False...
2. The more complete the transfer, the more likely tax goals will be accomplished. True False 5. Larry just completed signing all the documents and transferring stocks and bonds worth $400,000 in trust to Martin. The irrevocable trust terms require the income to be accumulated or distributed to John and Jane in such portion as Martin thinks reasonable. When both John and Jane are deceased the trust is to terminate and the assets distributed to Wally. Wally's right to receive...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT