In: Operations Management
Below is a list of jobs that must be accomplished to complete the new project. Assume the company wants to complete the project as early as possible, a) what is the added project cost?
You need not to show the network diagram.
Activity |
Immediate Predecessor |
Normal Time (Days) |
Crash Time (Days) |
Normal Cost |
Crash Cost |
A |
None |
8 |
7 |
$45 |
$50 |
B |
A |
3 |
1 |
$60 |
$65 |
C |
A |
11 |
9 |
$110 |
$150 |
D |
A |
6 |
5 |
$50 |
$90 |
E |
B |
9 |
6 |
$90 |
$120 |
F |
E |
2 |
1 |
$20 |
$40 |
G |
C, D |
5 |
4 |
$80 |
$100 |
H |
D |
7 |
6 |
$70 |
$100 |
I |
E, G |
4 |
4 |
$40 |
$40 |
J |
H |
8 |
7 |
$110 |
$120 |
K |
F, I, J |
15 |
13 |
$150 |
$250 |
b) What is project management?
______________________________________________________________________________________________________________________________________________________
PLEASE RATE POSITIVE IF YOU LIKE MY ANSWER TO ENCOURAGE MY EMPLOYMENT
Activity | Normal Time (A) | Crash Time (B) | Normal Cost ( C) | Crash Cost (D) |
Crashing Cost (D-C) |
Slope =Crash cost per day (D-C/A-B) |
A | 8 | 7 | 45 | 50 | 5 | 5 |
B | 3 | 1 | 60 | 65 | 5 | 2.5 |
C | 11 | 9 | 110 | 150 | 40 | 20 |
D | 6 | 5 | 50 | 90 | 40 | 40 |
E | 9 | 6 | 90 | 120 | 30 | 10 |
F | 2 | 1 | 20 | 40 | 20 | 20 |
G | 5 | 4 | 80 | 100 | 20 | 20 |
H | 7 | 6 | 70 | 100 | 30 | 30 |
I | 4 | 4 | 40 | 40 | 0 | |
J | 8 | 7 | 110 | 120 | 10 | 10 |
K | 15 | 13 | 150 | 250 | 100 | 50 |
Path | Pathlength |
ABEFK | 37 |
ABEIK | 39 |
ACGIK | 43 |
ADGIK | 38 |
ADHJK | 44 |
Crashing critical activity A with least slope | ||||||
Path | Pathlength | |||||
ABEFK | 36 | |||||
ABEIK | 38 | |||||
ACGIK | 42 | |||||
ADGIK | 37 | |||||
ADHJK | 43 | |||||
Crashing J | ||||||
Path | Pathlength | |||||
ABEFK | 36 | |||||
ABEIK | 38 | |||||
ACGIK | 42 | |||||
ADGIK | 37 | |||||
ADHJK | 42 | |||||
Crashing H, C and K | ||||||
Path | Pathlength | |||||
ABEFK | 34 | |||||
ABEIK | 36 | |||||
ACGIK | 37 | |||||
ADGIK | 34 | |||||
ADHJK | 39 | |||||
Crashing D and G | ||||||
Path | Pathlength | |||||
ABEFK | 34 | |||||
ABEIK | 36 | |||||
ACGIK | 38 | |||||
ADGIK | 35 | |||||
ADHJK | 38 | |||||
Further crashing will not reduce critical path length and hence no benefit of crashing further |
Therefore added project cost is crashing cost of A,D,H,J,K, C and G
= 5+40+30+10+100+40+20
= $245 Answer