In: Operations Management
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine Hours Due Date (days) |
||
1 |
A/3, B/2, C/2 |
3 |
2 |
C/2, A/4 |
2 |
3 |
B/6, A/1, C/3 |
4 |
4 |
C/4, A/1, B/2 |
3 |
Which department is the bottleneck?
Calculate the machine utilization?
SOLUTION:
(1)
GRANT CHART IS given for you to understand the problem easily
which department is the botteleneck :
empty white boxes refers to idle time of machines
so for machine A idle time is = 9
for machine B idle time is = 8
for machine C idle time is = 7
hence machine A is botteleneck
( 2 )
calculating machine utilization :
formule = total processing time / total hours ) * 100
* total processing time = total hours - total idle time
* total hours = no of hours * number of machines
by grant chart we get toknow that no of hours = 18
no of machines = 3
* total hours = 18 * 3
= 54 hours
* total idle time = 9 + 8 + 7
= 24
now total processing time = 54 -24 = 30 HOURS
FINALLY MACHINE UTILIZATION = ( TOTAL PROCESSING TIME / TOTAL HOURS ) * 100
= ( 30 / 54 ) *100
= 55 %
IF U HAVE ANY DOUBTS PLZ COMMENT , IF U LIKE THE ANSWER PLZ THUMB UP THANQ