Sequence the jobs shown below by using a Gantt chart. Assume that the move time between...

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine Hours                                  Due Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

Which department is the bottleneck?

Calculate the machine utilization?

Solutions

Expert Solution

SOLUTION:

(1)

GRANT CHART IS given for you to understand the problem easily  

which department is the botteleneck :

empty white boxes refers to idle time of  machines

so for machine A idle time is = 9

for machine B idle time is = 8

for machine C idle time is = 7

hence machine A is botteleneck  

( 2 )

calculating machine utilization :

formule = total processing time / total hours ) * 100

* total processing time = total hours - total idle time

* total hours = no of hours * number of machines

  

by grant chart we get toknow that no of hours = 18

no of machines = 3

* total hours = 18 * 3

= 54 hours

* total idle time = 9 + 8 + 7

= 24

now total processing time = 54 -24 = 30 HOURS

FINALLY MACHINE UTILIZATION = ( TOTAL PROCESSING TIME / TOTAL HOURS ) * 100

= ( 30 / 54 ) *100

= 55 %

IF U HAVE ANY DOUBTS PLZ COMMENT , IF U LIKE THE ANSWER PLZ THUMB UP THANQ


Related Solutions

Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress. Discuss the significance of the two paths or what they mean to the project. Activity immediate predecessors normal time budget organizational unit percent complete A - 4 $90 U1 100 B A 2 $35 U2 100 C A 6 $75 U2 40 D B 3 $60 U1 80 E C 10 $80 U1 0...
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project....
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project. Outline the six main steps of the PERT method for project management. Explain why it is important to consider project budgets and other resources in project design.
discuss how using a Gantt chart in a project charter can be an effective method in...
discuss how using a Gantt chart in a project charter can be an effective method in project management. Please provide a case study to demonstrate your point. OR, this can be based on experience. If you are basing this on experience, you will need to be able to cite the project and share its details.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual. Project: Vacation Team: "Workgroup 1", "Individual" Start/End: February 19 - May 26 START A. February 19: Vacation participation must be confirmed Time allotted: 7 days i. Confirm participation Time needed: 1 day ii. Research vacation deals Time needed: 1 days iii. Decide on destination Time needed: 2 days iv. Create travel list Time needed: 1 day Slack available: 2 days B. February...
Hi Guys! How do I prepare gantt chart including activities and time for a project developing...
Hi Guys! How do I prepare gantt chart including activities and time for a project developing a website?
Write sequence of the DNA strand that would be complementary to the DNA sequence shown below....
Write sequence of the DNA strand that would be complementary to the DNA sequence shown below. Label the 3' and 5' ends ofthe new strand. 3'   T A C C G A T G G    5'
Using the data shown, you will create two charts. The first chart is a bar chart...
Using the data shown, you will create two charts. The first chart is a bar chart that will display % growth in different job titles between 2010 and 2020Est. The second chart will be a pie chart showing the 2020Est. Jobs in different categories as a % of overall 2020Est. jobs. Computer-Related Jobs 2010 2020 Est. % Change Systems Analysts         544,400         664,800 Software App Developers         520,800         664,500 Programmers         363,100         406,800 Network/System Admins         347,200...
  Quarterly billing for water usage is shown below. Assume the time series has seasonality with a...
  Quarterly billing for water usage is shown below. Assume the time series has seasonality with a long term trend. Year Quarter 1 2 3 4 Winter   64   66   68   73 Spring 103 103 104 120 Summer 152 160 162 176 Fall   73   72   78   88 Forecast the next four quarters: FWinter = 81.625, FSpring = 126.375, FSummer= 175.375, FFall= 92.625 FWinter = 80.625, FSpring = 120.375, FSummer= 175.375, FFall= 90.625 FWinter = 82.625, FSpring = 120.375, FSummer= 174.375, FFall= 90.625...
For each sequence given below, find a closed formula for an, the nth term of the sequence (assume...
For each sequence given below, find a closed formula for an, the nth term of the sequence (assume the first terms here are always a0) by relating it to another sequence for which you already know the formula. −1,0,7,26,63,124,… an=(n^3)-1 −1,1,7,17,31,49,… an=2n^2-1 0,10,30,60,100,150,..... an=10*((n(n+1))/2) 2,3,6,14,40,152,… an= The first three are correct I can't figure out the last one.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT