Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
| 
 Job Work Center/Machine Hours Due Date (days)  | 
||
| 
 1  | 
 A/3, B/2, C/2  | 
 3  | 
| 
 2  | 
 C/2, A/4  | 
 2  | 
| 
 3  | 
 B/6, A/1, C/3  | 
 4  | 
| 
 4  | 
 C/4, A/1, B/2  | 
 3  |