In: Math
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine Hours Due Date (days) |
||
1 |
A/3, B/2, C/2 |
3 |
2 |
C/2, A/4 |
2 |
3 |
B/6, A/1, C/3 |
4 |
4 |
C/4, A/1, B/2 |
3 |