Question

In: Math

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between...

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine Hours                                  Due Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

  1. Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
  2. What is the makespan? (Marks 0.5)
  3. How much machine idle time is there? (Marks 0.5)
  4. How much idle time (waiting time) is there for each job? (Marks 0.5)
  5. When is each job delivered? (Marks 0.5)
  6. Which department is the bottleneck? (Marks 0.5)
  7. Calculate the machine utilization? (Marks 0.5)

Solutions

Expert Solution


Related Solutions

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between...
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Which department is the bottleneck? Calculate the machine utilization?
Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move...
Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5) What is the make span? (Marks 0.5) How much...
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress. Discuss the significance of the two paths or what they mean to the project. Activity immediate predecessors normal time budget organizational unit percent complete A - 4 $90 U1 100 B A 2 $35 U2 100 C A 6 $75 U2 40 D B 3 $60 U1 80 E C 10 $80 U1 0...
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project....
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project. Outline the six main steps of the PERT method for project management. Explain why it is important to consider project budgets and other resources in project design.
1. What is the difference between a Gantt chart and a PERT chart in the production...
1. What is the difference between a Gantt chart and a PERT chart in the production management? 2. How is the marketing concept tied to the relationship and social eras of marketing? 3. What are the Marketing mix and how does business apply them into the markets?
1. What are the strengths and weaknesses of using a Gantt chart for representing a project...
1. What are the strengths and weaknesses of using a Gantt chart for representing a project plan? How about a Network diagram and a PERT diagram? When they should be used ? Is one method “better” than the other? Should we combine them together? Please No handwritten work.
discuss how using a Gantt chart in a project charter can be an effective method in...
discuss how using a Gantt chart in a project charter can be an effective method in project management. Please provide a case study to demonstrate your point. OR, this can be based on experience. If you are basing this on experience, you will need to be able to cite the project and share its details.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual. Project: Vacation Team: "Workgroup 1", "Individual" Start/End: February 19 - May 26 START A. February 19: Vacation participation must be confirmed Time allotted: 7 days i. Confirm participation Time needed: 1 day ii. Research vacation deals Time needed: 1 days iii. Decide on destination Time needed: 2 days iv. Create travel list Time needed: 1 day Slack available: 2 days B. February...
Hi Guys! How do I prepare gantt chart including activities and time for a project developing...
Hi Guys! How do I prepare gantt chart including activities and time for a project developing a website?