Question

In: Operations Management

The jobs listed below need to be completed. Assume that it is now day 140. If...

The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule and earliest due date rule,

a. what is the job processing sequence for each rule?

b. what is the average flow time for each rule?

c. what is the utilization for each rule?

d. what is the average job lateness for each rule?

e. what is the average number of jobs in a system?

Job

Processing Time (days)(PT)

Job due date (days) (DD)

A

20

180

B

30

200

C

10

175

D

16

230

E

18

210

Solutions

Expert Solution

SPT


JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

C

10

35

0 + 10 = 10

D

16

90

10 + 16 = 26

E

18

70

26 + 18 = 44

A

20

40

44 + 20 = 64

24

B

30

60

64 + 30 = 94

34

TOTAL FLOW TIME = 10 + 26 + 44 + 64 + 94 = 238

AVERAGE COMPLETION TIME = FLOW TIME / N = 238 / 5 = 47.6

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 58 / 5 = 11.6

UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 238 * 100 = 39.5

AVERAGE JOBS IN THE SYSTEM = TOTAL FLOW TIME / TOTAL PROCESSING TIME = 238 / 94 = 2.53


EDD



JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

C

10

35

0 + 10 = 10

A

20

40

10 + 20 = 30

B

30

60

30 + 30 = 60

0

E

18

70

60 + 18 = 78

8

D

16

90

78 + 16 = 94

4


TOTAL FLOW TIME = 10 + 30 + 60 + 78 + 94 = 272

AVERAGE COMPLETION TIME = FLOW TIME / N = 272 / 5 = 54.4

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 12 / 5 = 2.4

UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 272 * 100 = 34.56

AVERAGE JOBS IN THE SYSTEM = TOTAL FLOW TIME / TOTAL PROCESSING TIME = 272 / 94 = 2.89

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.


Related Solutions

A repairman has 20 jobs that need to be completed today. Usually, 70% of all jobs...
A repairman has 20 jobs that need to be completed today. Usually, 70% of all jobs are fairly straightforward, so that the time it takes to complete them is well-described by normal distribution with average 10 minutes and standard deviation 1 minute. The rest are challenging jobs, so that completion time is well-modeled with exponential distribution with average 1 hour. i. If she starts at 8am, what is the expected time when she will finish all already assigned jobs? ii....
Assume you have the following jobs to execute with one processor, with the jobs arriving in the order listed above.
i t(pi) 0 80 1 20 2 10 3 20 4 50 Assume you have the following jobs to execute with one processor, with the jobs arriving in the order listed above. Suppose a system uses FCFS scheduling. Create a Gantt chart illustrating the execution of these processes . b   What is the turnaround time for process p3? c.   What is the average wait time for the processes? Using the process load above, suppose a system uses SJN scheduling. d...
Listed below are the numbers of words spoken in a day by each member of eight...
Listed below are the numbers of words spoken in a day by each member of eight different randomly selected couples. Complete parts​ (a) and​ (b) below. Male 15,536 25,576 1419 7737 18,362 15,734 13,680 25,846 Female 24,586 12,994 17,654 17,249 12,975 17,143 16,256 18,690 a. Use a 0.01 significance level to test the claim that among​ couples, males speak fewer words in a day than females. b. find the t statistic c. find the p value?
Listed below are the numbers of words spoken in a day by each member of eight...
Listed below are the numbers of words spoken in a day by each member of eight different randomly selected couples. Complete parts​ (a) and​ (b) below. Male 15 comma 375 26 comma 556 1401 7559 18 comma 327 15 comma 076 13 comma 760 26 comma 649 Female 24 comma 523 13 comma 931 18 comma 999 17 comma 770 13 comma 431 17 comma 388 16 comma 728 18 comma 102 a. Use a 0.05 significance level to test...
Listed below are the numbers of words spoken in a day by each member of eight...
Listed below are the numbers of words spoken in a day by each member of eight different randomly selected couples. Complete parts​ (a) and​ (b) below. Male 15 comma 974 26 comma 598 1381 7732 19 comma 399 15 comma 474 14 comma 153 26 comma 609 Female 23 comma 948 13 comma 839 18 comma 810 17 comma 408 13 comma 149 16 comma 801 16 comma 434 18 comma 573 a. Use a 0.01 significance level to test...
Assume that Ali Services company bills its clients for jobs completed during the month. On October...
Assume that Ali Services company bills its clients for jobs completed during the month. On October 31, 2004, Ali Services company billed its clients $450,000 for products sold during October. During November, Ali Services company collected 20 percent of its sales billed on October 31. the cost price this products was $200,000 which is paid 80 percent in cash. What would be recorded by Ali Services company under the cash basis?
Below is a list of jobs that must be accomplished to complete the new project. Assume...
Below is a list of jobs that must be accomplished to complete the new project. Assume the company wants to complete the project as early as possible, a) what is the added project cost? You need not to show the network diagram.      Activity Immediate Predecessor Normal Time (Days) Crash Time (Days) Normal Cost Crash Cost A None 8 7 $45 $50 B A 3 1 $60 $65 C A 11 9 $110 $150 D A 6 5 $50 $90...
Assume that the transactions listed in the first column of the table below are anticipated by...
Assume that the transactions listed in the first column of the table below are anticipated by U.S. firms that have no other foreign transactions. Place an “X” in the table wherever you see possible ways to hedge the transaction exposure. Forward Contract Futures Contract Options Contract Long Short Long Short Call Put a. A Inc. plans to sell goods to Portugal, denominated in euro b. B Co. will import automobiles from Germany, denominated in euro c. C Corp has a...
2. On July 1, Kauffman Oddjobs had two jobs in process as listed below. Job Number...
2. On July 1, Kauffman Oddjobs had two jobs in process as listed below. Job Number Material costs Labor hours 501 1,068 65 504 2,280 240 Before the year began, Kauffman CFO estimated that total overhead costs for the year would be $377,000 and that he would be able to bill 65,000 direct labor hours of time. Workers at Kauffman are paid 21 per hour. It appears that actual overhead costs for the year will be $389,500 and that Kauffman...
Assume it is now December 31, 2017 and Nicole has just completed her first year of...
Assume it is now December 31, 2017 and Nicole has just completed her first year of operations at Nicole’s Getaway Spa. After looking through her trial balance, she noticed that there are some items that have either not been recorded or are no longer up-to-date. Nicole’s Getaway Spa is renting its space at a cost of $600 per month. On September 1, 2017, Nicole paid eight months’ rent in advance using cash. This prepayment was recorded in the account Prepaid...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT