The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule and earliest due date rule,
a. what is the job processing sequence for each rule?
b. what is the average flow time for each rule?
c. what is the utilization for each rule?
d. what is the average job lateness for each rule?
e. what is the average number of jobs in a system?
Job |
Processing Time (days)(PT) |
Job due date (days) (DD) |
A |
20 |
180 |
B |
30 |
200 |
C |
10 |
175 |
D |
16 |
230 |
E |
18 |
210 |
SPT
JOB |
PROCESSING TIME |
DUE TIME |
FLOW TIME |
JOB LATENESS |
C |
10 |
35 |
0 + 10 = 10 |
|
D |
16 |
90 |
10 + 16 = 26 |
|
E |
18 |
70 |
26 + 18 = 44 |
|
A |
20 |
40 |
44 + 20 = 64 |
24 |
B |
30 |
60 |
64 + 30 = 94 |
34 |
TOTAL FLOW TIME = 10 + 26 + 44 + 64 + 94 = 238
AVERAGE COMPLETION TIME = FLOW TIME / N = 238 / 5 = 47.6
AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 58 / 5 = 11.6
UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 238 * 100 = 39.5
AVERAGE JOBS IN THE SYSTEM = TOTAL FLOW TIME / TOTAL PROCESSING TIME = 238 / 94 = 2.53
EDD
JOB |
PROCESSING TIME |
DUE TIME |
FLOW TIME |
JOB LATENESS |
C |
10 |
35 |
0 + 10 = 10 |
|
A |
20 |
40 |
10 + 20 = 30 |
|
B |
30 |
60 |
30 + 30 = 60 |
0 |
E |
18 |
70 |
60 + 18 = 78 |
8 |
D |
16 |
90 |
78 + 16 = 94 |
4 |
TOTAL FLOW TIME = 10 + 30 + 60 + 78 + 94 = 272
AVERAGE COMPLETION TIME = FLOW TIME / N = 272 / 5 = 54.4
AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 12 / 5 = 2.4
UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 272 * 100 = 34.56
AVERAGE JOBS IN THE SYSTEM = TOTAL FLOW TIME / TOTAL PROCESSING TIME = 272 / 94 = 2.89
** Leaving a thumbs-up would really help me out. Let me know if you face any problems.