Question

In: Operations Management

Given the following information concerning jobs awaiting processing at a single work center, what is the...

Given the following information concerning jobs awaiting processing at a single work center, what is the processing sequence using the critical ratio (CR) rule?

JOB Processing time at this operation (hrs)
at this
operation (hrs.)
Processing time
remaining at other
operations (hrs.)
Final
due
date ( hrs.)
D 4 4 9
A 8 6 38
O 6 10 24
I 3 8 20
N 5 14 32

Solutions

Expert Solution

we know that

Critical ratio = ( Due date - Today's Date ) / Total shop time remaining

In this Case

Due date - Today's Date = Time remaining until a Job's Due date which is given by "Final due date (hrs) ----B

Total shop time remaining = Processing time remaining at other operations (hrs) ------A

So CR = B / A

Below is the Critical ratio calculation for all the jobs

Job Processing time at this operation (Hrs) Processing time remaining at other operations (hrs) ---(A) Final due date (hrs) ----(B) Critical ratio = B / A
D 4 4 9 2.25
A 8 6 38 6.33
O 6 10 24 2.4
I 3 8 20 2.5
N 5 14 32 2.28

Now sequence should be arrived by arranging the critical ratio in an increasing order

So 2.25 < 2.28 < 2.4 < 2.5 < 6.33

The processing sequence should be

D --> N --> O --> I --> A

Sequence Job CR
1 D 2.25
2 N 2.28
3 O 2.4
4 I 2.5
5 A 6.33

P.S --Kindly give thumbs up --This will motivate me to provide more and more quality answers!


Related Solutions

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was...
A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was received, its processing time and due date are given in the following table. It is now the beginning of day 13. job day job was received job processing time (days) job due day A 1 6 41 B 2 10 25 C 7 2 19 D 8 9 31 E 9 1 18 Calculate the average throughput time and, for each job, the number...
The 4M company has a work center with a single turret lathe. Jobs arrive at this...
The 4M company has a work center with a single turret lathe. Jobs arrive at this work center according to a Poisson process at a mean rate of 2 jobs per day, The lathe processing time has an exponential distribution with a mean of 0.25 day per job. a) On average, how many jobs are waiting.in the work center? b) On average, how long will a job stay in the center? c).Since each job takes a big space, the waiting...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm...
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time and due date for each job are in the Table 4 below. Recommend the best job sequence to the manufacturer using THREE (3) dispatching rules scenario analysis. Table 4: Jobs Information Jobs Information Processing Time (days) Due Date (days) Job 1 3.25...
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
You are given the following information concerning Black Hills Enterprises:
You are given the following information concerning Black Hills Enterprises:Debt: There are 10,200 number of bonds outstanding with 7.2 percent coupon rate. It has 23 years to maturity and a quoted price of 107 percentage of the par value. These bonds pay interest semiannually.Common stock: 285,000 shares of common stock selling for $65.70 per share. The stock has a beta of .97 and will pay a dividend of $3.90 next year. The dividend is expected to grow by 5.2 percent...
You are given the following information concerning the tradesmade on a particular stock. Calculate the...
You are given the following information concerning the trades made on a particular stock. Calculate the money flow for the stock based on these trades. (Leave no cells blank - be certain to enter "0" wherever required. A negative value should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to the nearest whole dollar.)PriceVolume$59.9659.973,50059.953,00059.943,40058.953,55060.234,30060.144,600
Pierce & Company provides the following information concerning the work in process at its plant: •...
Pierce & Company provides the following information concerning the work in process at its plant: • Beginning inventory was partially complete (materials are 100 percent complete; conversion costs are 61 percent complete). • Started this month, 59,300 units. • Transferred out, 50,200 units. • Ending inventory, 18,700 units (materials are 100 percent complete; conversion costs are 15 percent complete). Required: a. Compute the equivalent units for materials using FIFO. b. Compute the equivalent units for conversion costs using FIFO.
Pierce & Company provides the following information concerning the work in process at its plant:  ...
Pierce & Company provides the following information concerning the work in process at its plant:   • Beginning inventory was partially complete (materials are 100 percent complete; conversion costs are 59 percent complete). • Started this month, 60,700 units. • Transferred out, 49,300 units. • Ending inventory, 21,700 units (materials are 100 percent complete; conversion costs are 14 percent complete).   Required: a. Compute the equivalent units for materials using FIFO.   b. Compute the equivalent units for conversion costs using FIFO....
ABC Company manufactures and sells a single product. The following information is available concerning the operations...
ABC Company manufactures and sells a single product. The following information is available concerning the operations for 1999. a. The company's single product sells for $60 per unit. Budgeted sales in units for the next four quarters are: 1999    Quarter 1        3,000 Budgeted sales in units 1999    Quarter 2        3,500 Budgeted sales in units                1999    Quarter 3        4,000 Budgeted sales in units 1999    Quarter 4        4,500 Budgeted sales in units 2000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT