Question

In: Operations Management

Given the following information concerning jobs awaiting processing at a single work center, what is the...

Given the following information concerning jobs awaiting processing at a single work center, what is the processing sequence using the critical ratio (CR) rule?

JOB Processing time at this operation (hrs)
at this
operation (hrs.)
Processing time
remaining at other
operations (hrs.)
Final
due
date ( hrs.)
D 4 4 9
A 8 6 38
O 6 10 24
I 3 8 20
N 5 14 32

Solutions

Expert Solution

we know that

Critical ratio = ( Due date - Today's Date ) / Total shop time remaining

In this Case

Due date - Today's Date = Time remaining until a Job's Due date which is given by "Final due date (hrs) ----B

Total shop time remaining = Processing time remaining at other operations (hrs) ------A

So CR = B / A

Below is the Critical ratio calculation for all the jobs

Job Processing time at this operation (Hrs) Processing time remaining at other operations (hrs) ---(A) Final due date (hrs) ----(B) Critical ratio = B / A
D 4 4 9 2.25
A 8 6 38 6.33
O 6 10 24 2.4
I 3 8 20 2.5
N 5 14 32 2.28

Now sequence should be arrived by arranging the critical ratio in an increasing order

So 2.25 < 2.28 < 2.4 < 2.5 < 6.33

The processing sequence should be

D --> N --> O --> I --> A

Sequence Job CR
1 D 2.25
2 N 2.28
3 O 2.4
4 I 2.5
5 A 6.33

P.S --Kindly give thumbs up --This will motivate me to provide more and more quality answers!


Related Solutions

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was...
A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was received, its processing time and due date are given in the following table. It is now the beginning of day 13. job day job was received job processing time (days) job due day A 1 6 41 B 2 10 25 C 7 2 19 D 8 9 31 E 9 1 18 Calculate the average throughput time and, for each job, the number...
The 4M company has a work center with a single turret lathe. Jobs arrive at this...
The 4M company has a work center with a single turret lathe. Jobs arrive at this work center according to a Poisson process at a mean rate of 2 jobs per day, The lathe processing time has an exponential distribution with a mean of 0.25 day per job. a) On average, how many jobs are waiting.in the work center? b) On average, how long will a job stay in the center? c).Since each job takes a big space, the waiting...
The table below contains information about five jobs waiting to be processed at work center. Job...
The table below contains information about five jobs waiting to be processed at work center. Job Processing Time (Days.) Days Until Due a 14 15 b 10 20 c 18 18 d 2 16 e 4 21 a. The sequence that would result using the FCFS rule is: e-b-c-d-a c-a-b-e-d a-b-c-d-e d-e-b-a-c e-d-b-a-c       b. The sequence that would result using the SPT rule is: e-b-c-d-a c-a-b-e-d a-d-c-e-b d-e-b-a-c e-d-b-a-c        c. The average flow time (completion time) using the...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm...
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time and due date for each job are in the Table 4 below. Recommend the best job sequence to the manufacturer using THREE (3) dispatching rules scenario analysis. Table 4: Jobs Information Jobs Information Processing Time (days) Due Date (days) Job 1 3.25...
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive: Job   Date Received   Due Date   Duration (days) A             275                    312                  16 B             275                    325                  40 C      275                     314                   5 D            275                     315                   3 E            275                      313                  8 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each...
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive:     Job Due Date Duration​ (days) A 315 3 B 313 8 C 312 16 D 325 40 E 314 5 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day​ (a job that begins on...
You are given the following information concerning Black Hills Enterprises:
You are given the following information concerning Black Hills Enterprises:Debt: There are 10,200 number of bonds outstanding with 7.2 percent coupon rate. It has 23 years to maturity and a quoted price of 107 percentage of the par value. These bonds pay interest semiannually.Common stock: 285,000 shares of common stock selling for $65.70 per share. The stock has a beta of .97 and will pay a dividend of $3.90 next year. The dividend is expected to grow by 5.2 percent...
A computer operator at the local data processing center decides to visit work on a Monday...
A computer operator at the local data processing center decides to visit work on a Monday evening. She has a key to the outside door, and since there is no key required for the computer room, she simply walks into the computer room. The operator, who is really one of the nation’s most notorious computer programmer/hackers (having been convicted five time for manipulating various firms’ data files), opens the documentation bookcase, located in the corner of the computer room. In...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT