Question

In: Operations Management

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was...

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was received, its processing time and due date are given in the following table. It is now the beginning of day 13.

job day job was received job processing time (days) job due day
A 1 6 41
B 2 10 25
C 7 2 19
D 8 9 31
E 9 1 18

Calculate the average throughput time and, for each job, the number of days overdue using the following priority sequencing rules:

(1) First-come-first-serve

(2) Earliest due date

(3) Shortest processing time

(4) The client waiting for job B has informed the contractor that its due date is now day 33. How will this information affect your choice of priority rule?

Solutions

Expert Solution

First come first serve method= The jobs will be arranged as they come so the sequence will be A-B-C-D-E

In Out Due date Lateness
A 0 6 41 0
B 6 6+10=16 25 0
C 16 16+2=18 19 0
D 18 18+9=27 31 0
E 27 27+1=28 18 10

Average throughput time = 5/28=0.178

Activity Overdue
A 0
B 0
C 0
D 0
E 10

2= In the earliest due date, the jobs will be arranged as per their due dates. The jobs with the least due date will be completed first. So the sequence will be

E-C-B-D-A

In Out Due date Lateness
E 0 1 18 0
C 1 1+2=3 19 0
B 3 3+10=13 25 0
D 13 13+9=22 31 0
A 22 22+6=28 41 0

Average throughput time =5/41 =0.12

Activity Overdue
A 0
B 0
C 0
D 0
E 0

3= In the shortest processing time, the job with the least processing time will be processed first, so the sequence will be as below=E-C-A-D-B

In Out Due date Lateness
E 0 1 18 0
C 1 1+2=3 19 0
A 3 3+6=9 41 0
D 9 9+9=18 31 0
B 18 18+10=28 25 3

Average throughput time=5/25 =0.2

Activity Overdue
A 0
B 0
C 0
D 0
E 3

Answer 4=, In this case, the priority rule of Earliest Due Date will have the changed sequence of the jobs so the new sequence will be=E-C-D-B-A


Related Solutions

Given the following information concerning jobs awaiting processing at a single work center, what is the...
Given the following information concerning jobs awaiting processing at a single work center, what is the processing sequence using the critical ratio (CR) rule? JOB Processing time at this operation (hrs) at this operation (hrs.) Processing time remaining at other operations (hrs.) Final due date ( hrs.) D 4 4 9 A 8 6 38 O 6 10 24 I 3 8 20 N 5 14 32
A particular single-machine workstation has a capacity of 1,000 units per day and variability is moderate,...
A particular single-machine workstation has a capacity of 1,000 units per day and variability is moderate, such that V = (SCV of arrivals + SCV of effective process time)/2 = 1. Demand is currently 900 units per day. Suppose management has decided that cycle times should be no longer than 1.5 times the average process time. A) What is the current cycle time in multiples of the process time? (i.e. if the current cycle time was 2 times longer than...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job Cost Sheets are placed on the Answers Sheets. Company applies factory overhead using activity based costing. The predetermined overhead rates for activities are as follows:                                                                                           Machine Setup Activity                      Inspection Activity Overhead Rate                                                                 $120 per machine setup                    $75 per inspection    On the space provided on the answer sheet, provide journal entries for the following transactions. Complete Job Cost Sheets as needed. If you wish, you may...
Assume that you have a set of jobs where each has only a processing time that...
Assume that you have a set of jobs where each has only a processing time that you need to schedule on a single machine. Explain how you should schedule the jobs to minimize the sum of completion (finish) times. Write a proof that your schedule is optimal.
Suppose Bob has been offered two jobs- an indsutry job and a teaching job. Hes considering...
Suppose Bob has been offered two jobs- an indsutry job and a teaching job. Hes considering taking the industry job. The teaching job has a salary of $60,000. in addition to the salary, Tobias values the flexibility of the teaching job at $20,000 a year. The industry job requires relocating, and the moving costs are $5,000. The industry job requires buying more fancy clothes and those costs will be $500. The industry job pays $100,000 i. What is the explicit...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
There are eight different jobs in a printer queue. Each job has a distinct tag which...
There are eight different jobs in a printer queue. Each job has a distinct tag which is a string of three upper case letters. The tags for the eight jobs are: { LPW, QKJ, CDP, USU, BBD, PST, LSA, RHR } How many different ways are there to order the eight jobs in the queue so that job USU comes somewhere before CDP in the queue (although not necessarily immediately before) and CDP comes somewhere before BBD (again, not necessarily...
1. Alice has 2 jobs that she will process sequentially. The first job takes an exponential...
1. Alice has 2 jobs that she will process sequentially. The first job takes an exponential amount of time with a mean of 15 minutes. Once the first job is completed, then we start working on the second job. The second job also takes an exponential amount of time to complete with a mean of 15 minutes. (a) Let T be the total time to complete both jobs. Give the distribution of T, its mean and its standard deviation. (b)...
An inspector has the job of checking a screw-making machine at the start of each day....
An inspector has the job of checking a screw-making machine at the start of each day. She finds that the machine needs repairs pairs one day out of ten. When the machine does need repairs, all the screws it makes are defective. Even when the machine is working properly, 5% of the screws it makes are defective; these defective screws are randomly scattered through the day's output. Use a calculator to get approximate answers to the following lowing questions. What...
ABC Manufacturing Inc. ends the month with two jobs still in progress. Job 5 has $10,000...
ABC Manufacturing Inc. ends the month with two jobs still in progress. Job 5 has $10,000 of materials, $2,000 of direct labor and $8,000 of manufacturing overhead allocated. Job 6 was $30,000 of materials, $2,000 of direct labor and $10,000 of manufacturing overhead allocated. The cost of goods sold for the month was $40,000 and of that 30% was overhead. There were no finished goods in stock as the month ends. If the manufacturing overhead is underallocated by $10,000, which...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT