Question

In: Operations Management

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was...

A contractor has ten jobs awaiting processing at a bottleneck workstation. The day the job was received, its processing time and due date are given in the following table. It is now the beginning of day 13.

job day job was received job processing time (days) job due day
A 1 6 41
B 2 10 25
C 7 2 19
D 8 9 31
E 9 1 18

Calculate the average throughput time and, for each job, the number of days overdue using the following priority sequencing rules:

(1) First-come-first-serve

(2) Earliest due date

(3) Shortest processing time

(4) The client waiting for job B has informed the contractor that its due date is now day 33. How will this information affect your choice of priority rule?

Solutions

Expert Solution

First come first serve method= The jobs will be arranged as they come so the sequence will be A-B-C-D-E

In Out Due date Lateness
A 0 6 41 0
B 6 6+10=16 25 0
C 16 16+2=18 19 0
D 18 18+9=27 31 0
E 27 27+1=28 18 10

Average throughput time = 5/28=0.178

Activity Overdue
A 0
B 0
C 0
D 0
E 10

2= In the earliest due date, the jobs will be arranged as per their due dates. The jobs with the least due date will be completed first. So the sequence will be

E-C-B-D-A

In Out Due date Lateness
E 0 1 18 0
C 1 1+2=3 19 0
B 3 3+10=13 25 0
D 13 13+9=22 31 0
A 22 22+6=28 41 0

Average throughput time =5/41 =0.12

Activity Overdue
A 0
B 0
C 0
D 0
E 0

3= In the shortest processing time, the job with the least processing time will be processed first, so the sequence will be as below=E-C-A-D-B

In Out Due date Lateness
E 0 1 18 0
C 1 1+2=3 19 0
A 3 3+6=9 41 0
D 9 9+9=18 31 0
B 18 18+10=28 25 3

Average throughput time=5/25 =0.2

Activity Overdue
A 0
B 0
C 0
D 0
E 3

Answer 4=, In this case, the priority rule of Earliest Due Date will have the changed sequence of the jobs so the new sequence will be=E-C-D-B-A


Related Solutions

A particular single-machine workstation has a capacity of 1,000 units per day and variability is moderate,...
A particular single-machine workstation has a capacity of 1,000 units per day and variability is moderate, such that V = (SCV of arrivals + SCV of effective process time)/2 = 1. Demand is currently 900 units per day. Suppose management has decided that cycle times should be no longer than 1.5 times the average process time. A) What is the current cycle time in multiples of the process time? (i.e. if the current cycle time was 2 times longer than...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job Cost Sheets are placed on the Answers Sheets. Company applies factory overhead using activity based costing. The predetermined overhead rates for activities are as follows:                                                                                           Machine Setup Activity                      Inspection Activity Overhead Rate                                                                 $120 per machine setup                    $75 per inspection    On the space provided on the answer sheet, provide journal entries for the following transactions. Complete Job Cost Sheets as needed. If you wish, you may...
Compute the capacity (bottleneck rate) in jobs per hour (jph) of the following configurations and record...
Compute the capacity (bottleneck rate) in jobs per hour (jph) of the following configurations and record your numerical answers (in order) to the nearest tenth of jph. (Enter numbers only): a. A station with two (2) machines operating in parallel with 5-minute process times (te) at each machine. b. A balanced line with two (2) series single-machine stations, both with average processing times (te) of 10 minutes. c. A line with four (4) single machine stations in series, where the...
Assume that you have a set of jobs where each has only a processing time that...
Assume that you have a set of jobs where each has only a processing time that you need to schedule on a single machine. Explain how you should schedule the jobs to minimize the sum of completion (finish) times. Write a proof that your schedule is optimal.
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
Suppose Bob has been offered two jobs- an indsutry job and a teaching job. Hes considering...
Suppose Bob has been offered two jobs- an indsutry job and a teaching job. Hes considering taking the industry job. The teaching job has a salary of $60,000. in addition to the salary, Tobias values the flexibility of the teaching job at $20,000 a year. The industry job requires relocating, and the moving costs are $5,000. The industry job requires buying more fancy clothes and those costs will be $500. The industry job pays $100,000 i. What is the explicit...
List specific jobs that should be segregated in the purchases processing system.
List specific jobs that should be segregated in the purchases processing system.
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:    Job A256 Job A257 Job A258 Job A260 Beginning balance $ 1,060 $ 530 $ 0 $ 0 Charged to the jobs during October: Direct materials $ 2,820 $ 4,040 $ 1,530 $ 3,780 Direct labor $ 1,150 $ 880 $ 520 $ 310 Manufacturing overhead applied...
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:    Job A256 Job A257 Job A258 Job A260 Beginning balance $ 1,050 $ 540 $ 0 $ 0 Charged to the jobs during October: Direct materials $ 2,840 $ 4,000 $ 1,420 $ 3,770 Direct labor $ 1,240 $ 840 $ 530 $ 360 Manufacturing overhead applied...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT