Question

In: Finance

Look at the cash flows for projects F and G given below. Cash Flows($) Project C0...

Look at the cash flows for projects F and G given below.

Cash Flows($)
Project C0 C1 C2 C3 C4 C5 C6 C7 C8 IRR (%) NPV at 10%
F (10,000 ) 6,000 6,000 6,000 0 0 0 0 0 36.3 4,921
G (10,000 ) 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 25.0 6,005


The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 8% on average. That is, the forecast for each cash flow from each project should be reduced by 8%. But a lazy financial manager, unwilling to take the time to argue with the projects’ sponsors, instructs them to use a discount rate of 18%.

a. What are the projects’ true NPVs? (Do not round intermediate calculations. Round your answers to nearest dollar amount.)




b. What are the NPVs at the 18% discount rate? (Do not round intermediate calculations. Round your answers to nearest dollar amount.)

Solutions

Expert Solution

Solution :

a. The project's True NPV's are as follows :

Project F = $ 3,727

Project G = $ 4,737

Note :

Since the cash flows of the project had been overstated by 8 %, the same have been corrected as follows :

= Cash flow * ( 1 - 0.08 )

b. The NPV's of the project at discount rate of 18 % are as follows :

Project F = $ 3,046

Project G = $ 2,233

Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.


Related Solutions

1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1&
1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1            C2            C3            C4               C5          -$7000    +$3,000   +$4,000   +$6,000     +$2,500      +$2,000 _________________________________________________________ Calculate the following:     (a) NPV (Net Present Value) at 12% discount rate                                                (b) IRR (Internal Rate of Return)                                                (c) The payback period for Project (Z)
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260 C1 110 138 C2 110 138 C3 110 138 C4 110 a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)? b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%. c. Which one would you choose if the cost of...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280 C1 120 148 C2 120 148 C3 120 148 C4 120 a.What are the internal rates of return on the two projects? b. If the opportunity cost of capital is 11%, what is the profitability index for each project?
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.) PRoject A % Project B %
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A...
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A −33,000 23,400 23,400 +$7,612 B −53,000 36,000 36,000 +9,479 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Consider the following two mutually exclusive projects withtheir expected Cash Flows ($)Project C0 C1...
Consider the following two mutually exclusive projects with their expected Cash Flows ($)Project C0 C1   C2 C3A –$100 +$60 +$60 +$60B –$100 ------ ------ +$208.35What is the cross-over rate for these two projects?a. unknown, because the discount rate is unkownb. 28%c. 36%d. 32%e. 15%
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT