Question

In: Finance

Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A...

Consider projects A and B:

Cash Flows (dollars)

Project C0 C1 C2 NPV at 10%
A −33,000 23,400 23,400 +$7,612
B −53,000 36,000 36,000 +9,479

a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)

Solutions

Expert Solution

Project A

IRR is the rate at which NPV=0. ie: PV of inflows = PV of outflows. It is calculated by trial and error method.

Lets find NPV at say 26%.

Year Cashflow PVF@26% Cashflow*PVF
0              (33,000) 1              (33,000.00)
1                23,400 0.7937                18,571.43
2                23,400 0.6299                14,739.23

NPV = PV of Inflows-PV of Outflows

= (18571.43+14739.23)-33000

= 33310.66-33000

= $310.66

Since NPV is positive, Take a higher rate say 27%

Year Cashflow PVF@27% Cashflow*PVF
0              (33,000) 1              (33,000.00)
1                23,400 0.7874                18,425.20
2                23,400 0.6200                14,508.03

NPV = PV of Inflows-PV of Outflows

= (18425.20+14508.03)-33000

= 32933.23-33000

= -66.77

Now we got two rates R1 and R2 such that NPV at R1(NPV1) is higher and NPV at R2(NPV2) is lower.

IRR = R1 + ((NPV1 x (R2 - R1)) / (NPV1 - NPV2))

= 26+((310.66*(27-26))/(310.66+66.77)

= 26+(310.66/377.43)

= 26.82%

Project B

IRR is the rate at which NPV=0. ie: PV of inflows = PV of outflows. It is calculated by trial and error method.

Lets find NPV at say 23%.

Year Cashflow PVF@23% Cashflow*PVF
0              (53,000) 1              (53,000.00)
1                36,000 0.8130                29,268.29
2                36,000 0.6610                23,795.36

NPV = PV of Inflows-PV of Outflows

= (29268.29+23795.36)-53000

= 53063.65-53000

= $63.65

Since NPV is positive, Take a higher rate say 24%

Year Cashflow PVF@24% Cashflow*PVF
0              (53,000) 1              (53,000.00)
1                36,000 0.8065                29,032.26
2                36,000 0.6504                23,413.11

NPV = PV of Inflows-PV of Outflows

= (29032.26+23413.11)-53000

= 52445.37-53000

= -554.63

Now we got two rates R1 and R2 such that NPV at R1(NPV1) is higher and NPV at R2(NPV2) is lower.

IRR = R1 + ((NPV1 x (R2 - R1)) / (NPV1 - NPV2))

= 23+((63.65*(24-23))/(63.65+554.63)

= 23+(63.65/618.28)

= 23.10%


Related Solutions

Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C3 -100      40        60        50          The investor expected rate of return is 10%. The cost of capital is 12%. Required: What will you choose to be the discount rate? Why? Please calculate the payback period (PP) and return on investment (ROI). Please calculate NPV,PVI and IRR.. Make decision based on the above calculation and explain the reasons. David said that the profit is the same as...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.) PRoject A % Project B %
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT