Question

In: Finance

Mr tan is considering 2 potential investment projects that have similar capital requirements: Year 0 year...

Mr tan is considering 2 potential investment projects that have similar capital requirements:

Year 0 year 1 year 2 year 3 year 4
project A 4,000,000 1,600,000 1,800,000 2,000,000 2,100,000
Project B 4,200,000 500,000 1,700,000 1,900,000 2,000,000

For project A,the company cost of capital is 14%.For project B,assessed as the riskier project of the two.,a risk adjusted cost of capital of 15% is considered appropriate.

1) calculate the NPV of the 2 projects and assess the projects using the investment appraisal technique of Net present Vale.

2)Calculate the IRR of the 2 projects and assess the projects using the investment appraisal technique of Internal rate of return.

3) Is the company cost of capital suitable in the evaluation of projects with different risks? Explain

Solutions

Expert Solution

1 2
Year 0 year 1 year 2 year 3 year 4 NPV IRR
project A -4000000.00 1600000.00 1800000.00 2000000.00 2100000.00 1381861.94 29.17%
Project B -4200000.00 500000.00 1700000.00 1900000.00 2000000.00 -86985.82 14.13%

1: Select Project A since it has higher NPV

2: Select Project A since it has higher IRR.

3: Cost of capital differs given the different risks involved. Higher the risk, higher is the cost involved and lower the returns.

WORKINGS


Related Solutions

2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B....
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                          CASHFLOW                           CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $10,000                                   $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $ 15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5% A.  Calculate the payback period for each project.  State if payback is acceptable for each project and state why. B.  Calculate the NPV for each project.  State if NPV is acceptable for each project and state why. C.  Calculate the IRR for each project.  State if IRR is acceptable for each project and...
HKV company is considering investing in several projects that have varying capital requirements over the next...
HKV company is considering investing in several projects that have varying capital requirements over the next four years. The net present value of each project, cash outflows required over the years and capital available per year are given (in millions) in the table below: Plant 1 Expansion Plant 2 Expansion New Product Development Automation Annual Capital Available Year 1 8 5 4 7 20 Year 2 10 7 2 5 25 Year 3 10 10 1 5 20 Year 4...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW 1 $95,000 $112,000 2 $150,000 $95,000 3 $10,000 $85,000 4 $12,000 $65,000 5 $45,000 $10,000 6 $198,000 $15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5%. A) Calculate the payback period for each project. State if payback is acceptable for each project and state why. B) Calculate the NPV for each project. State if NPV is acceptable for each...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows for the two projects are given. For both projects, the required rate of return is 12%. Year Project A Project B 0 ($40,000) ($40,000) 1 $14,400 $0 2 $14,400 $0 3 $14,400 $0 4 $14,400 $70,000 Find the following: 1. The Net Present Value (NPV) . 2. The Internal Rate of Return (IRR) . 3. Use Excel to draw a graph of the NPV...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. If r = 10%, which project should be selected under the NPV method? b. If r = 20%, which project should be selected under the NPV method? c. Calculate each project’s PI...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. Calculate each project’s payback (PB) period if r = 10% (up to 2 decimal places). Which project should be accepted? b. Calculate each project’s discounted payback (DPB) period if r = 10%...
1. Cost and benefit of requirements to carry contingent capital or similar mechanisms 2. Cost and...
1. Cost and benefit of requirements to carry contingent capital or similar mechanisms 2. Cost and benefits of limits on size of financial institutions 3. How are foreign exchange rates determined? A simple, short answer is - by demand and supply. But what are the key factors underlying demand and supply? 4. The EMH continues to remain a hotly debated topic for over 50 years. A counter argument to the EMH is the following: If the EMH were true, then...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT