Question

In: Accounting

HKV company is considering investing in several projects that have varying capital requirements over the next...

  1. HKV company is considering investing in several projects that have varying capital requirements over the next four years. The net present value of each project, cash outflows required over the years and capital available per year are given (in millions) in the table below:

Plant 1 Expansion

Plant 2 Expansion

New Product Development

Automation

Annual

Capital Available

Year 1

8

5

4

7

20

Year 2

10

7

2

5

25

Year 3

10

10

1

5

20

Year 4

7

3

1

5

15

NPV of each

Project

45

20

10

20

Each project must be done in full (with the corresponding cash flows for all the years) or not done at all. Any available money not spent in a given year is then available to spend the following year. Help the company find the optimal investment plan that would maximize the total net present value. (Recall the Capital Budgeting example in Section 3.2. There are some similarities between the example and this problem, but some differences – this is a BIP problem.)

  1. Formulate the problem as a binary integer programming (BIP) problem in spreadsheet form. Solve the spreadsheet model. What is the optimal investment plan? What is the total net present value of the optimal investment plan?
  2. Additional constraint is considered: the New Product Development is selected only if Plant 2 Expansion project is also adopted. Formulate and solve the spreadsheet model. What is the optimal investment plan? What is the total net present value of the optimal investment plan?
  3. From question b, considering one more constraint: Plant 1 Expansion and Plant 2 Expansion cannot be both selected. Formulate and solve the spreadsheet model. What is the optimal investment plan? What is the total net present value of the optimal investment plan?
  4. Formulate the problem (c) as a binary integer programming (BIP) problem in algebraic form.
  5. (Practice; will not be graded) If the cash available in year 1 varies between 10 and 30 million dollars, how would that affect the optimal solution and the optimal total net present value of the investment plan? Use the Analytics Solver to conduct the Parameter Analysis and interpret the report generated.

Solutions

Expert Solution

Give this answer a thumbs up, It really helps!

(a)

The spreadsheet formulas are shown below

The solver parameters are shown below

The result is shown below

(b) The new solver parameter is shown below

The result is shown below

(c) The new solver parameter is shown below

The result is shown below

(d)

The formulation for part b can be written as

Maximize 45X1 + 20X2 + 10X3 + 20X4

Subject to

8X1 + 5X2 + 4X3 + 7X4 <= 20

10X1 + 7X2 + 2X3 + 5X4 <= 25

10X1 + 10X2 + 1X3 + 5X4 <= 20

7X1 + 3X2 + 1X3 + 5X4 <= 15

X2 >= X3

X1, X2, X3, X4 = {0,1}


Related Solutions

Your company is considering investing in one of two mutually exclusive projects. The cost of capital...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital is 11%. The first project Has $25,000 annual cash inflows, a 10-year life, and will cost $120,000 at time zero. The second project has a 7-year life, Annual cash inflows of $20,000 per year, and a cost of $75,000 at time zero. Which project has the highest NPV. Assuming that these projects will most likely be repeated indefinitely into the future, which project would...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital is 11%. The first project Has $25,000 annual cash inflows, a 10-year life, and will cost $120,000 at time zero. The second project has a 7-year life, Annual cash inflows of $20,000 per year, and a cost of $75,000 at time zero. Which project has the highest NPV. Assuming that these projects will most likely be repeated indefinitely into the future, which project would...
Project Selection Your company is prepared to undertake several new projects over the next five years....
Project Selection Your company is prepared to undertake several new projects over the next five years. Each Division has submitted a number of project proposals that include the annual budgets and anticipated profit. Your company’s annual budgets for the next five years are as follows. (Amounts are X$1000) YEAR 2016 2017 2018 2019 2020 FUNDS 3500 4500 4000 3450 4500 The project proposals (for a total of fifteen possible projects) are as follows: Project 2016 2017 2018 2019 2020 Profit...
Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year. The projects,...
Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and the number of support personnel required for each project, and the expected profits for each project are summarized in the following table: Project 1 2 3 4 5 6 Engineers Required 20 55 47 38 90 63 Support Personnel Required 15 45 50 40 70 70 Profit ($1,000,000s) 1.0 1.8 2.0 1.5 3.6 2.2 Formulate an integer program that...
Mr tan is considering 2 potential investment projects that have similar capital requirements: Year 0 year...
Mr tan is considering 2 potential investment projects that have similar capital requirements: Year 0 year 1 year 2 year 3 year 4 project A 4,000,000 1,600,000 1,800,000 2,000,000 2,100,000 Project B 4,200,000 500,000 1,700,000 1,900,000 2,000,000 For project A,the company cost of capital is 14%.For project B,assessed as the riskier project of the two.,a risk adjusted cost of capital of 15% is considered appropriate. 1) calculate the NPV of the 2 projects and assess the projects using the investment...
Mr Tommy Tan is considering two potential investment projects that have similar capital requirements: Year 0...
Mr Tommy Tan is considering two potential investment projects that have similar capital requirements: Year 0 Year 1 Year 2 Year 3 Year 4 Project A (4,000,000) 1,600,000 1,800,000 2,000,000 2,100,000 Project B (4,200,000) 500,000 1,700,000 1,900,000 2,000,000 For Project A, the company cost of capital is assumed to be 14%. For Project B, assessed as the riskier project of the two, a risk-adjusted cost of capital of 15% is considered appropriate. Calculate the IRR of the two (2) projects...
Question 1    Mr Tommy Tan is considering two potential investment projects that have similar capital requirements:...
Question 1    Mr Tommy Tan is considering two potential investment projects that have similar capital requirements:                               Year 0                   Year 1                   Year 2                   Year 3                   Year 4 Project A (4,000,000)        1,600,000        1,800,000        2,000,000        2,100,000        Project B (4,200,000)        500,000           1,700,000        1,900,000        2,000,000 For Project A, the company cost of capital is assumed to be 14%. For Project B, assessed as the riskier project of the two, a risk-adjusted cost of capital of 15% is considered appropriate. (b) Calculate the IRR of...
The president of Hill Enterprises, Terri Hill, projects the firm’s aggregate demand requirements over the next...
The president of Hill Enterprises, Terri Hill, projects the firm’s aggregate demand requirements over the next 8 months as follows: Dec 1,600 Jan. 1,400 May 2,200 Feb. 1,600 June 2,200 Mar. 1,800 July 1,800 Apr. 1,800 Aug. 1,800. Her operations manager is considering a new plan, which begins in January with 200 units on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is...
A company is considering investing in project X. The company has a cost of capital of...
A company is considering investing in project X. The company has a cost of capital of 10% p.a. Project X is a 9-year project with an initial cost of 400,000. The project will generate the following cash flows at the end of the years: Years Cash flows 1 90,000 2 80,000 3 50,000 4 50,000 5 50,000 6 50,000 7 50,000 8 50,000 9 15,000 a)    Calculate the payback period (in years) for project X. Round your answer to 2 decimal...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’ forecasted cash flows are shown as below. WACC is 10%. Year 0 1 2 3 4 Project L CF ($) -1,000    700 500 200 0 Project S CF ($) -1,200 100 300 800 1,000 a. Calculate the NPVs for both projects. b. Calculate the IRRs for both projects. c. Calculate the Discounted Paybacks for both projects. [Draw a timeline] d. Based on your...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT