In: Finance
Capital Budgeting Question:
You are considering two mutually exclusive projects for potential investment. The cash flows for the two projects are given. For both projects, the required rate of return is 12%.
Year |
Project A |
Project B |
0 |
($40,000) |
($40,000) |
1 |
$14,400 |
$0 |
2 |
$14,400 |
$0 |
3 |
$14,400 |
$0 |
4 |
$14,400 |
$70,000 |
Find the following:
1. The Net Present Value (NPV) .
2. The Internal Rate of Return (IRR) .
3. Use Excel to draw a graph of the NPV of these cash flows as a function of the discount rate (NPV Profile).
4. What is the value of cross over point?
5. What is your recommendation, which project the company shall choose? Explain the basis of your choice.
1=n | 2 | 3=1/1.12^Yr.n | 4=2*3 | 5 | 6=5*3 |
Year | Project A | PV F at 12% | PV at 12% | Project B | PV at 12% |
0 | -40000 | 1 | -40000 | -40000 | -40000 |
1 | 14400 | 0.89286 | 12857.14 | 0 | 0 |
2 | 14400 | 0.79719 | 11479.59 | 0 | 0 |
3 | 14400 | 0.71178 | 10249.64 | 0 | 0 |
4 | 14400 | 0.63552 | 9151.46 | 70000 | 44486.27 |
NPV= | 3737.83 | 4486.27 | |||
IRR= | |||||
IRR= | 16.37% | 15.02% |
1.NPV=Sum of the PVs of all cash flows including initial investment at yr.0 , ie. -CF0+(CF1/(1+r)^1)+(CF2/(1+r)^2+(CF3/91+r)^3+(CF4/(1+r)^4 |
NPV of Project A=-40000+(14400/1.12^1)+(14400/1.12^2)+(14400/1.12^3)+(14400/1.12^4)= |
3737.83 |
NPV of Project B=-40000+(70000/1.12^4)= |
4486.27 |
2. IRR is the discount rate at which the NPV =0 |
ie.-CF0+(CF1/(1+r)^1)+(CF2/(1+r)^2+(CF3/91+r)^3+(CF4/(1+r)^4=0 |
so, for Project A, equating the discounted values at r% to 0,we have, |
-40000+(14400/(1+r)^1)+(14400/(1+r)^2)+(14400/(1+r)^3)+(14400/(1+r)^4)=0 |
& solving for r, we get the IRR as |
16.37% |
for Project B, equating the discounted values at r% to 0,we have, |
-40000+(70000/(1+r)^4)=0 |
& solving for r, we get the IRR as |
15.02% |
4.Cross over point is the discount rate at which both the NPV s are equal. |
ie. Equating both the NPVs & solving for r, |
-40000+(14400/(1+r)^1)+(14400/(1+r)^2)+(14400/(1+r)^3)+(14400/(1+r)^4)=-40000+(70000/(1+r)^4) |
& solving for r, we get the cross over discount rate as |
13.16% |
Value/NPV at Cross-over rate=$ 2690 for both Projects A & B |
5. Recommendation |
At 12% discount rate, Project B is recommended. |
& |
If the discount rate is less than 15.02% project B isrecommended |
If the discount rate is between 15.02% & 16.37% project A is recommended |
In addition,
NPV profiles near cross-over rate | Cross-over rate | Recommended | ||
A | B | |||
13.50% | 2391 | 2180 | Above | project A |
13.16% | 2690 | 2690 | C/O rate | Indifferent |
13% | 2832 | 2932 | Below | Project B |