In: Finance
A company has the following 2 projects: Projects C0 C1 C2 C3 A -36 20 20 20 B -50 25 25 25 Assume that the discount rate is 10%. How much is the difference between the NPV values of these 2 projects (i.e., NPV of Project A minus NPV of Project B)? A) 0.57 B) 1.57 C) 3.67 D) 4.67 E) 13.17
A company uses Internal Rate of Return (IRR) criteria to analyze the following two mutually exclusive projects:
Project |
C0 |
C1 |
C2 |
C3 |
NorthEast |
-1100 |
1000 |
350 |
50 |
SouthWest |
-1100 |
0 |
300 |
1500 |
Assume that this company’s opportunity cost of capital (i.e., Hurdle rate for IRR analysis) is 10%. Then,
(i) (ii)
A) Project NorthEast 20%
B) Project SouthWest 19%
C) Project SouthWest 30%
D) Project SouthWest 26%
E) Project NorthEast 24%
Project A
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $13.74
Project B
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $12.17.
Therefore, the difference between the NPV of the two projects is = $13.74 - $12.17
= $1.57.
Hence, the answer is option b.
Project Northeast
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 20.46%.
Project Southwest
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 19.08%.
i.Project Northeast should be accepted based on IRR analysis since it has the highest internal rate of return.
ii.The IRR of the accepted project is 20.46% 20%
Hence, the answer is option a.
In case of any query, kindly comment on the solution.