In: Finance
A company has the following 2 projects: Projects C0 C1 C2 C3 A -36 20 20 20 B -50 25 25 25 Assume that the discount rate is 10%. How much is the difference between the NPV values of these 2 projects (i.e., NPV of Project A minus NPV of Project B)? A) 0.57 B) 1.57 C) 3.67 D) 4.67 E) 13.17
A company uses Internal Rate of Return (IRR) criteria to analyze the following two mutually exclusive projects:
| 
 Project  | 
 C0  | 
 C1  | 
 C2  | 
 C3  | 
| 
 NorthEast  | 
 -1100  | 
 1000  | 
 350  | 
 50  | 
| 
 SouthWest  | 
 -1100  | 
 0  | 
 300  | 
 1500  | 
Assume that this company’s opportunity cost of capital (i.e., Hurdle rate for IRR analysis) is 10%. Then,
(i) (ii)
A) Project NorthEast 20%
B) Project SouthWest 19%
C) Project SouthWest 30%
D) Project SouthWest 26%
E) Project NorthEast 24%
Project A
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $13.74
Project B
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $12.17.
Therefore, the difference between the NPV of the two projects is = $13.74 - $12.17
= $1.57.
Hence, the answer is option b.
Project Northeast
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 20.46%.
Project Southwest
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 19.08%.
i.Project Northeast should be accepted based on IRR analysis since it has the highest internal rate of return.
ii.The IRR of the accepted project is 20.46% 
20%
Hence, the answer is option a.
In case of any query, kindly comment on the solution.