Question

In: Finance

1. Compute the NPV of a project with the following information. The IRR is 9%. The...

1. Compute the NPV of a project with the following information. The IRR is 9%. The project life is 3 years. The initial cost is $19,000. In years 1 and 2 the cash inflows are $4,500 and $5,500, respectively. Cash flow in year 3 is missing. WACC is 12%.

Solutions

Expert Solution

Hi, dear

you need to take care the understanding of IRR. IRR represents the rate of return in which the cash flow will be equal to initial investment. so by comparing we can easily calculate the npv of 3rd year using X as the 3rd year cash flow.

please hit the like button to aprreciate, and for any query feel free to comment. thank you


Related Solutions

Given the following information, estimate the cash flows of this project and then compute the NPV...
Given the following information, estimate the cash flows of this project and then compute the NPV of this project. Estimated Sales: 50,000 units per year for each of the next 3 years Estimate Sale Price: $1,050 per unit Variable Cost: $1,000 per unit Fixed Costs: $1,500,000 per year Initial Investment in Plant and Machinery: $1,500,000 to be depreciated to a salvage value of $0 over the next three years. We sell the machine at $45000 in the market at the...
A project pays $500 at t=1 and 700 at t=7. Compute the NPV, IRR, Payback period...
A project pays $500 at t=1 and 700 at t=7. Compute the NPV, IRR, Payback period of the project if it costs $700 today. Assume cost of capital is 10% where required.
Calculate the NPV at 9% and the IRR for the following projects: An initial outlay of...
Calculate the NPV at 9% and the IRR for the following projects: An initial outlay of $69,724 and an inflow of 15,000 followed by four consecutive inflows of $17,000
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 NPV? Should it be accepted or rejected
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Should the project be accepted or rejected? Project M Time: 0 1 2 3 4 5 Cash flow: –$1,500 $450 $580 $620 $700 $200 How do you come up with the NPV? And Should the project be accepted or rejected?
If the IRR for a project is 20%, then the project's NPV would be:
If the IRR for a project is 20%, then the project's NPV would be:
Calculations of the NPV, IRR and the payback for the project and an analysis of the...
Calculations of the NPV, IRR and the payback for the project and an analysis of the results. I need the excel formula calculation and analysis of the questions You have identified a potential opportunity for WBC, which involves undertaking a project that will have a ten-year life. The project requires an initial purchase of equipment and furniture totalling $4,500,000, plus ancillary programming capability and machinery costing $1,500,000. The equipment and furniture will depreciate and have a salvage value of $500,000...
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required...
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 12%. Cashflow for each year Project A : Year 0= -2500 Year 1=900 Yaer 2=800 Year 3=1600 Year 4=100 Yaer 5=50 Year 6= 300 Project B Year 0 =-2500 Year 1=50 Year2= 600 Year 3=150 Year 4=900 Year 5= 500 Year 6=2500
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project...
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project provides an annual cash flow of $15,400 for nine years and costs $67,000 today. Is this a good project at 8% required return? How about 20%? Question 14 options: Yes, Yes Yes, No No, Yes No, No
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT