Question

In: Accounting

Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given...

Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools:

Fabrication Department Finishing Department

Cost Driver

Maintenance $20,000 $10,000

Machine hours

Materials handling 30,000 15,000

Material moves

Machine setups 70,000 5,000

Machine setups

Inspections - 25,000

Inspection hours

$120,000 $55,000

The following activity predictions were also made for the year:

Fabrication Department Finishing Department
Machine hours 10,000 5,000
Material moves 3,000 1,500
Machine setups 700 50
Inspection hours - 1,000

It is assumed that the cost per unit of activity for a given activity does not vary between departments. Slack's president, Charles Slack, is trying to evaluate the company's product mix strategy regarding two of its five product models, ZX300 and SL500. The company has been using a company-wide overhead rate based on machine hours but is considering switching to either department rates or activity-based rates. The production manager has provided the following data for the production of a batch of 100 units for each of these models:

ZX300 SL500
Direct materials cost $12,000 $18,000
Direct labor cost $5,000 $4,000
Machine hours (Fabrication) 500 700
Machine hours (Finishing) 200 100
Materials moves 30 50
Machine setups 5 9
Inspection hours 30 60

a. Determine the cost of one unit each of ZX300 and SL500, assuming a company-wide overhead rate is used based on total machine hours.

Round rate to two decimal places.
Overhead rate based on total machine hours Answer

per machine hour

Use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number. Round cost per unit to two decimal places.

Product Costs per Unit

ZX300

SL500

Direct materials Answer Answer
Direct labor Answer Answer
Manufacturing overhead: Answer Answer
Total cost per batch Answer Answer
Number of units per batch Answer Answer
Cost per unit Answer Answer

b. Determine the cost of one unit of ZX300 and SL500, assuming department overhead rates are used. Overhead is assigned based on machine hours in both departments.

Round rate to two decimal places, if applicable.
Overhead rate based on machine hours for Fabrication Dept. $Answer

per machine hour
Overhead rate based on machine hours for Finishing Dept. $Answer per machine hour

Use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number, when needed. Round cost per unit to two decimal places, if needed.

Product Costs per Unit
Product Costs per Unit

ZX300

SL500

Direct materials Answer Answer
Direct labor Answer Answer
Manufacturing overhead:
Fabrication Dept. Answer Answer
Finishing Dept. Answer Answer
Total cost per batch Answer Answer
Number of units per batch Answer Answer
Cost per unit Answer Answer

c. Determine the cost of one unit of ZX300 and SL500, assuming activity-based overhead rates are used for maintenance, materials handling, machine setup, and inspection activities.
Round rate to two decimal places, if applicable.

Activity-based overhead rates:
Maintenance

Answer

Materials handling

Answer

Machine setup

Answer

Inspection activities

Answer

Use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number, when needed. Round cost per unit to two decimal places, if needed.

Product Costs per Unit

ZX300

SL500

Direct materials Answer Answer
Direct labor Answer Answer
Manufacturing overhead:
Maintenance activity Answer Answer
Materials handling activity Answer Answer
Machine setups activity Answer Answer
Inspections activity Answer Answer
Total cost per batch Answer Answer
Number of units per batch Answer Answer
Cost per unit Answer Answer

Solutions

Expert Solution

Part 1

Overhead (120000+55000) $                        175,000
Divided by: total machine hours (10000+5000)                               15,000
Overhead rate per machine hour $                             11.67
Overhead rate allocated to Model ZX300 ((500+200)*11.67) $                       8,169.00
Overhead rate allocated to Model SL500 ((700+100)*11.67) $                       9,336.00
ZX300 SL500
Direct materials $                                     12,000 $                           18,000
Direct labor $                                       5,000 $                             4,000
Manufacturing overhead $                                       8,169 $                             9,336
Total cost per batch $                                     25,169 $                           31,336
Divided by: Number of units per batch                                               100                                     100
Cost per unit $                                  251.690 $                        313.360
Cost per unit (rounded) $                                     251.69 $                           313.36

Part 2

Fabrication Finishing
Overhead $                                  120,000 $                           55,000
Divided by: total machine hours (10000+5000)                                         10,000                                 5,000
Overhead rate per machine hour $                                       12.00 $                             11.00
Overhead applied to ZX300 Fabrication Finishing Total
Machine hours                                               500                                     200
Multiply: Overhead rate per machine hour $                                       12.00 $                             11.00
Overhead applied $                                       6,000 $                             2,200 $                  8,200
Overhead applied to SL500 Fabrication Finishing Total
Machine hours                                               700                                     100
Multiply: Overhead rate per machine hour $                                       12.00 $                             11.00
Overhead applied $                                       8,400 $                             1,100 $                  9,500
ZX300 SL500
Direct materials $                                     12,000 $                           18,000
Direct labor $                                       5,000 $                             4,000
Manufacturing overhead $                                       8,200 $                             9,500
Total cost per batch $                                     25,200 $                           31,500
Divided by: Number of units per batch                                               100                                     100
Cost per unit $                                  252.000 $                        315.000
Cost per unit (rounded) $                                     252.00 $                           315.00

Part 3

Activity Centers Fabrication Finishing Total Activity Costs
Maintenance $                                     20,000 $                           10,000 $                30,000
Materials handling $                                     30,000 $                           15,000 $                45,000
Machine setup $                                     70,000 $                             5,000 $                75,000
Inspection activities $                                              -   $                           25,000 $                25,000
Activity Centers Fabrication Finishing Total Activity Level
Maintenance                                         10,000                                 5,000                    15,000
Materials handling                                           3,000                                 1,500                      4,500
Machine setup                                               700                                       50                          750
Inspection activities                                 1,000                      1,000
Activity Centers Cost Drivers Activity Costs Divided by : Activity Level Cost driver rate
Maintenance Machine hours $                           30,000                    15,000 $                   2.00
Materials handling Material moves $                           45,000                      4,500 $                 10.00
Machine setup Machine setups $                           75,000                          750 $              100.00
Inspection activities Inspection hours $                           25,000                      1,000 $                 25.00

Part 4

Model Model ZX300
Activity Centers Cost driver rate Multiply: Activity Allocated cost
Maintenance $                                         2.00                                     700 $                  1,400
Materials handling $                                       10.00                                       30 $                      300
Machine setup $                                     100.00                                          5 $                      500
Inspection activities $                                       25.00                                       30 $                      750
Model ZX300 $                  2,950
Model Model SL500
Activity Centers Cost driver rate Multiply: Activity Allocated cost
Maintenance $                                         2.00                                     800 $                  1,600
Materials handling $                                       10.00                                       50 $                      500
Machine setup $                                     100.00                                          9 $                      900
Inspection activities $                                       25.00                                       60 $                  1,500
Model SL500 $                  4,500
ZX300 SL500
Total direct materials costs $                                     12,000 $                           18,000
Total direct labor costs $                                       5,000 $                             4,000
Overhead costs:
Maintenance $                                       1,400 $                             1,600
Materials handling $                                           300 $                                 500
Machine setup $                                           500 $                                 900
Inspection activities $                                           750 $                             1,500
Total costs $                                     19,950 $                           26,500
Units produced                                               100                                     100
Unit cost $                                     199.50 $                           265.00

Related Solutions

Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given...
Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $96 ,000 48,000 Machine hours Materials handling 144,000 72,000 Material moves Machine 336,000 24,000 Machine setups Inspections - 120,000 Inspection hours Total $ 576,000 $264 ,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection hours...
Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given...
Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 36,000 18,000 Machine hours Materials handling 54,000 27,000 Material moves Machine 126,000 9,000 Machine setups Inspections - 45,000 Inspection hours Total $ 216,000 $ 99,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection hours...
Question text Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for...
Question text Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $80,000 $70,000 Machine hours Materials handling 30,000 15,000 Material moves Machine setups 70,000 5,000 Machine setups Inspections - 25,000 Inspection hours $180,000 $115,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 10,000 5,000 Material moves 3,000 1,500 Machine setups 700 50 Inspection...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 60,000 30,000 Machine hours Materials handling 90,000 45,000 Material moves Machine 210,000 15,000 Machine setups Inspections - 75,000 Inspection hours Total $ 360,000 $165,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 54,000 27,000 Machine hours Materials handling 81,000 40,500 Material moves Machine 189,000 13,500 Machine setups Inspections - 67,500 Inspection hours Total $ 324,000 $ 148,500 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 54,000 27,000 Machine hours Materials handling 81,000 40,500 Material moves Machine 189,000 13,500 Machine setups Inspections - 67,500 Inspection hours Total $ 324,000 $ 148,500 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 54,000 27,000 Machine hours Materials handling 81,000 40,500 Material moves Machine 189,000 13,500 Machine setups Inspections - 67,500 Inspection hours Total $ 324,000 $ 148,500 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 60,000 30,000 Machine hours Materials handling 90,000 45,000 Material moves Machine 210,000 15,000 Machine setups Inspections - 75,000 Inspection hours Total $ 360,000 $165,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $ 60,000 30,000 Machine hours Materials handling 90,000 45,000 Material moves Machine 210,000 15,000 Machine setups Inspections - 75,000 Inspection hours Total $ 360,000 $165,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection...
Exercise C: Activity-Based Costing Erte, Inc. has the following predicted indirect costs and cost drivers for...
Exercise C: Activity-Based Costing Erte, Inc. has the following predicted indirect costs and cost drivers for 2017 for the given activity cost pools: Manufacture Department Finishing Department Cost Driver Maintenance $30,000 $15,000 Machine hours Materials handling $40,000 $25,000 Material moves Machine setups $80,000 $5,000 Machine setups Inspections $0 $20,000 Inspection hours Total 150,000 $65,000 The following activity predictions were also made for the year: Manufacture Department Finishing Department Machine hours 15,000 8,000 Materials moves 5,000 3,500 Machine setups 900 150...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT