Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all...

Question 01:

Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc.

• Activities H, R2, T1 start the project.

• Activity T2 can start when Activities H, E1 and S are completed.

• Activity E1 also depends on Activity R2.

• Activity X follows Activity H and precedes Activity L.

• Activity E is preceded by Activities T2 and P1.

• The predecessors to Activity G are Activities L, T2 and P1.

• The successors to Activity T1 are Activities E1, S, W and D2.

• Activity P1 cannot begin until Activity W is finished.

• Activity P2 and F follow Activities W and D2, and precede Activities E and R1.

• Activity O2 depends on T2 and P1 , and precedes Activity L.

.

Question 02:

Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM).

Solutions

Expert Solution


Related Solutions

1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days.
Supplemental assignment for MGMT8300: Network Diagram and the Critical Path 1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days. 2. What is the critical path? 3. How long will it take to complete the project if everything goes according to plan? 4. Choose an activity that is not on the critical path. How many days longer should it take in order for the critical...
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project....
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project. b. Determine the critical path using the expected time for each activity (you can use Excel), and the expected project duration. c. What is the probability that the project will be finished in 3 weeks? In 4 weeks? Time estimates (days) Activity Predecessor a m b a -- 1 3 5 b -- 2 3 5 c -- 2 4 7 d a 1...
Match the descriptions that follow with the corresponding terms. Terms Descriptions 1. Activity-Based CostingBalanced ScorecardTotal Quality...
Match the descriptions that follow with the corresponding terms. Terms Descriptions 1. Activity-Based CostingBalanced ScorecardTotal Quality Management (TQM)Research and Development, and Product DesignService IndustriesJust-In-Time (JIT) InventorySarbanes-Oxley Act (SOX)Global Reporting Initiative Inventory system in which goods are manufactured or purchased just as they are needed for sale. 2. Activity-Based CostingBalanced ScorecardTotal Quality Management (TQM)Research and Development, and Product DesignService IndustriesJust-In-Time (JIT) InventorySarbanes-Oxley Act (SOX)Global Reporting Initiative A method of allocating overhead based on each product’s use of activities in making the...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation;...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation; simple answers alone will not account for full marks) • Activity 1 can start immediately and has an estimated duration of three weeks. • Activity 2 can start after activity 1 is completed and has an estimated duration of three weeks. • Activity 3 can start after activity 1 is completed and has an estimated duration of six weeks. • Activity 4 can start...
This question is based on our three-node network where all resistances are equal. Generators are located...
This question is based on our three-node network where all resistances are equal. Generators are located at nodes 1 and 2, while the customer is located at node 3. Power flows through the network are: F(1,3) = 44 MW F(2,3) = 56 MW F(1,2) = -12 MW (i.e., 12 MW from node 2 to node 1) The transmission limit on Line (1,2) is 10 MW in either direction, so the line is overloaded by 2 MW. Assume that lines (2,3)...
Based on the descriptions given below, write the JavaScript codes to calculate the amount to be...
Based on the descriptions given below, write the JavaScript codes to calculate the amount to be paid for books purchased.  Declare all the variables used in this program.  Ask the user to key-in the book code using a prompt() method. Store the value in a variable named book_code.  Ask the user to key-in the number of books purchased using a prompt() method. Store the value in a variable named book_qty.  Ask the user whether they have...
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
Explain the logic used to determine which activity to reduce on a Project Network based on...
Explain the logic used to determine which activity to reduce on a Project Network based on the cost slope and other relevant information.
Which of the descriptions below is an example of resonant energy transfer? (Choose all that are...
Which of the descriptions below is an example of resonant energy transfer? (Choose all that are correct.) View Available Hint(s) Hint 1. opened hint Review natural frequency and resonance. Which of the descriptions below is an example of resonant energy transfer? (Choose all that are correct.) A block sliding on a horizontal surface slows down and comes to a stop due to the friction force. Soldiers marching in unison on a bridge with their steps at a frequency that is...
Test if the variables are linearly correlated. (Show all four steps use a = .01, .05...
Test if the variables are linearly correlated. (Show all four steps use a = .01, .05 and .10). N=11, Coefficient of Correlation, r: 0.89, Y-intercept, a: 72.1, Slope, b: 15.2
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT