In: Accounting
QUESTION ONE:
Comprehensive Standard Cost Variances
Clarissa McWhirter, vice-president of Cyprus Company, was pleased to see a small variance on the income statement after the trouble the company had been having in controlling manufacturing costs. She noted that the $12,250 overall manufacturing variance reported last period was well below the 3% limit that had been set for variances. The company produces and sells a single product. The standard cost card for the product follows:
Standard Cost Card -Per Unit
Direct materials, 4 metres at $3.50 per metre $14
Direct labour, 1.5 direct labour-hours at $12 per direct labour-hour 18
Variable overhead, 1.5 direct labour-hours at $2 per direct labour-hour 3
Fixed overhead, 1.5 direct-labour hours at $6 per direct labour-hour 9
Standard cost per unit 44
The following additional information is available for the year just completed:
a. The company manufactured 20,000 units of product during the year.
b. A total of 78,000 metres of material was purchased during the year at a cost of $3.75 per metre. All of this material was used to manufacture the 20,000 units. There were no beginning or ending inventories for the year.
c. The company worked 32,500 direct labour-hours during the year at a cost of $11.80 per hour.
d. Overhead cost is applied to products on the basis of standard direct labour-hours. Data relating to manufacturing overhead costs follow:
Denominator activity level (direct labour-hours) 25,000
Budgeted fixed overhead costs (from the flexible budget) $150,000
Actual fixed overhead costs $148,000
Actual variable overhead costs $68,250
Required:
All figures are in $
Material Variance
Standard ( 1 unit) |
Actual (20,000 unit) |
||||
Quantity |
Price |
Cost |
Quantity |
Price |
Cost |
4 meter |
3.50 |
14 |
78000 |
3.75 |
292500 |
Material Price Variance
Actual Quantity * Actual Price - Actual Quantity * Standard Price
78000 * 3.75 - 78000 * 3.50
292500 - 273000
19500 (Adverse)
Material Quantity Variance
Actual Quantity * Standard Price - Standard Quantity * Standard Price
78000 * 3.50 - 80000 * 3.50
273000 - 280000
7000 (Favourable)
Note - For 1 unit, 4 meter of standard material is required, so for 20,000 unit (20,000 * 4) i.e. 80,000 would be the standard material
Labour Variance
Standard ( 1 unit) |
Actual (20,000 unit) |
||||
Hours |
Rate |
Cost |
Hours |
Rate |
Cost |
1.5 hours |
12 |
18 |
32500 hours |
11.80 |
383500 |
Labour Rate Variance
Actual Hours * Actual Rate - Actual Hours * Standard Rate
32500 * 11.80 - 32500 * 12
6500 ( Favourable)
Labour Efficiency Variance
Actual Hours * Standard Rate - Standard Hours * Standard Rate
32500 * 12 - 30,000 * 12
30000 (Adverse)
Fixed Overhead
Fixed Overhead Budget Variance
Actual Fixed Overhead - Budgeted Fixed Overhead
148000 - 150000
2000 (Favourable)
Fixed Overhead Volume Variance
Budgeted fixed overhead – Fixed overhead applied
Fixed component of predetermined overhead rate = Budgeted fixed overhead/budgeted hours
150000/25000 = 6 per hour
Fixed overhead applied = Fixed component of predetermined overhead rate × Standard hours allowed for actual output
6 * ( Actual Output * Standard Hour per unit )
6 *(20000 * 1.5 )
180000
So, Fixed Overhead Volume variance =
150000 - 180000
30000 (Adverse)
Variable Overhead
Variable Overhead Spending Variance
(Standard Rate * Actual Hour) - Actual Variable Overhead cost
2 * 32500 - 68250
65000 - 68250
3250 (Adverse)
Variable Overhead Efficiency Variance
Standard Rate * ( Actual Hours - Standard Hours )
2 * (30000 - 32500)
5000 (Favourable)
Material Price Variance |
(19500) |
Material Quantity Variance |
7000 |
Labour Rate Variance |
6500 |
Labour Efficiency Variance |
(30000) |
Variable Overhead Spending Variance |
(3250) |
Variable Overhead efficiency Variance |
5000 |
Fixed overhead budget variance |
2000 |
Fixed overhead volume variance |
(30000) |
NO, Everyone should not be congratulated as job is not well done
the net manufacturing variance is 28000 adverse, which is way more than the 12250