In: Accounting
QUESTION ONE:
Comprehensive Standard Cost Variances
Clarissa McWhirter, vice-president of Cyprus Company, was pleased to see a small variance on the income statement after the trouble the company had been having in controlling manufacturing costs. She noted that the $12,250 overall manufacturing variance reported last period was well below the 3% limit that had been set for variances. The company produces and sells a single product. The standard cost card for the product follows:
Standard Cost Card -Per Unit
Direct materials, 4 metres at $3.50 per metre $14
Direct labour, 1.5 direct labour-hours at $12 per direct labour-hour 18
Variable overhead, 1.5 direct labour-hours at $2 per direct labour-hour 3
Fixed overhead, 1.5 direct-labour hours at $6 per direct labour-hour 9
Standard cost per unit 44
The following additional information is available for the year just completed:
a. The company manufactured 20,000 units of product during the year.
b. A total of 78,000 metres of material was purchased during the year at a cost of $3.75 per metre. All of this material was used to manufacture the 20,000 units. There were no beginning or ending inventories for the year.
c. The company worked 32,500 direct labour-hours during the year at a cost of $11.80 per hour.
d. Overhead cost is applied to products on the basis of standard direct labour-hours. Data relating to manufacturing overhead costs follow:
Denominator activity level (direct labour-hours) 25,000
Budgeted fixed overhead costs (from the flexible budget) $150,000
Actual fixed overhead costs $148,000
Actual variable overhead costs $68,250
Required:
All figures are in $
Material Variance
| 
 Standard ( 1 unit)  | 
 Actual (20,000 unit)  | 
||||
| 
 Quantity  | 
 Price  | 
 Cost  | 
 Quantity  | 
 Price  | 
 Cost  | 
| 
 4 meter  | 
 3.50  | 
 14  | 
 78000  | 
 3.75  | 
 292500  | 
Material Price Variance
Actual Quantity * Actual Price - Actual Quantity * Standard Price
78000 * 3.75 - 78000 * 3.50
292500 - 273000
19500 (Adverse)
Material Quantity Variance
Actual Quantity * Standard Price - Standard Quantity * Standard Price
78000 * 3.50 - 80000 * 3.50
273000 - 280000
7000 (Favourable)
Note - For 1 unit, 4 meter of standard material is required, so for 20,000 unit (20,000 * 4) i.e. 80,000 would be the standard material
Labour Variance
| 
 Standard ( 1 unit)  | 
 Actual (20,000 unit)  | 
||||
| 
 Hours  | 
 Rate  | 
 Cost  | 
 Hours  | 
 Rate  | 
 Cost  | 
| 
 1.5 hours  | 
 12  | 
 18  | 
 32500 hours  | 
 11.80  | 
 383500  | 
Labour Rate Variance
Actual Hours * Actual Rate - Actual Hours * Standard Rate
32500 * 11.80 - 32500 * 12
6500 ( Favourable)
Labour Efficiency Variance
Actual Hours * Standard Rate - Standard Hours * Standard Rate
32500 * 12 - 30,000 * 12
30000 (Adverse)
Fixed Overhead
Fixed Overhead Budget Variance
Actual Fixed Overhead - Budgeted Fixed Overhead
148000 - 150000
2000 (Favourable)
Fixed Overhead Volume Variance
Budgeted fixed overhead – Fixed overhead applied
Fixed component of predetermined overhead rate = Budgeted fixed overhead/budgeted hours
150000/25000 = 6 per hour
Fixed overhead applied = Fixed component of predetermined overhead rate × Standard hours allowed for actual output
6 * ( Actual Output * Standard Hour per unit )
6 *(20000 * 1.5 )
180000
So, Fixed Overhead Volume variance =
150000 - 180000
30000 (Adverse)
Variable Overhead
Variable Overhead Spending Variance
(Standard Rate * Actual Hour) - Actual Variable Overhead cost
2 * 32500 - 68250
65000 - 68250
3250 (Adverse)
Variable Overhead Efficiency Variance
Standard Rate * ( Actual Hours - Standard Hours )
2 * (30000 - 32500)
5000 (Favourable)
| 
 Material Price Variance  | 
 (19500)  | 
| 
 Material Quantity Variance  | 
 7000  | 
| 
 Labour Rate Variance  | 
 6500  | 
| 
 Labour Efficiency Variance  | 
 (30000)  | 
| 
 Variable Overhead Spending Variance  | 
 (3250)  | 
| 
 Variable Overhead efficiency Variance  | 
 5000  | 
| 
 Fixed overhead budget variance  | 
 2000  | 
| 
 Fixed overhead volume variance  | 
 (30000)  | 
NO, Everyone should not be congratulated as job is not well done
the net manufacturing variance is 28000 adverse, which is way more than the 12250