Question

In: Operations Management

Explain the logic used to determine which activity to reduce on a Project Network based on...

Explain the logic used to determine which activity to reduce on a Project Network based on the cost slope and other relevant information.

Solutions

Expert Solution

Answer:

Solution of network is defined as the options to improve the network execution and achieve the desired project result.

The network is the diagram of the project tasks which are sequenced as per their order of execution. The tasks are arranged in the sequence of the execution order with meeting the precedence requirements.

The solutions of a network can be done in many ways as per the network paths available. The longest network path is the critical path of the network wich provides the longest solution for the network.

The other non-critical paths, which are having the lead-times lower than the critical paths, bit these do leads to the solution to the network.

Thus the network has many solutions based on the different paths of the network which can be executed to complete the network project diagram.

Elements of Project Cost: The elements of project cost are the elements which contributes the cost of the projects. These elements are as below

  • Labor Cost: The labor cost is the cost of the labor required in project tasks execution.
  • Resources Cost: The resource cost is the cost of the resources required in project execution, without resource, the project cannot be executed on time.
  • Equipments Cost: The equipments cost is the cost of the equipments required in the project tasks execution. These are the essential equipments which are required for the project.
  • Managerial or Consultation Cost - The managerial or consultation cost of the project is basically the cost element related to general management and Consultation required for the project.
  • Project Training Cost – The training cost of project is linked with the resource development cost of project.

On the basis of above discussed cost we have to minimize cost of the project if cost is higher of project. One other thing that can be good in reduction of overall cost of project is Time. Time play an important role so if we can minimize the time of project so we can reduce the cost of project.

Time aspect is the main aspect in the project network. Every organization needs to finish their project as soon as possible. There are two activities in the project the one is critical activities and other one is non critical activities. Non critical activity are the activity that can be good option for finish them soon and focus towards only critical activities so that we can complete our project as soon as possible.

Time factor is also a main factor in reduction of the cost of project.


Related Solutions

Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project....
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project. b. Determine the critical path using the expected time for each activity (you can use Excel), and the expected project duration. c. What is the probability that the project will be finished in 3 weeks? In 4 weeks? Time estimates (days) Activity Predecessor a m b a -- 1 3 5 b -- 2 3 5 c -- 2 4 7 d a 1...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity A to K is descried as follows: A with a duration of 2 month; B has immediate predecessor of A with total duration of 4 month; C has immediate predecessor of (A) with total duration of 2 month; (D) has immediate predecessor of B with total duration of 2month; (E) has immediate predecessor of B and C with total duration of 4 month; (F)...
Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all...
Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity L....
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
explain why a glucose test strip may be used to determine the enzymatic activity of lactase
explain why a glucose test strip may be used to determine the enzymatic activity of lactase
Which network path is the critical path of this project?
Which network path is the critical path of this project?
differences and similarities between activity-based budget and project-based budget
differences and similarities between activity-based budget and project-based budget
Read the case on which your Portfolio Project is based and determine all items that will...
Read the case on which your Portfolio Project is based and determine all items that will be excluded from gross income. In an MS Excel spreadsheet, list all excluded items in column A. In column B, explain why the item is excluded. You may reference the specific tax law, the text (make sure you include the page number), or a link to another trusted source. A trusted source is either supported by the IRS or academic literature (that includes textbooks)...
Read the case on which your Portfolio Project is based and determine all items that will...
Read the case on which your Portfolio Project is based and determine all items that will be excluded from gross income. In a MS Excel spreadsheet, list all excluded items in column A. In column B, explain why the item is excluded. You may reference the specific tax law, the text (make sure you include the page number), or a link to another trusted source. A trusted source is either supported by the IRS or academic literature (that includes textbooks)...
Read the case on which your Portfolio Project is based and determine all items that will...
Read the case on which your Portfolio Project is based and determine all items that will be excluded from gross income. In a MS Excel spreadsheet, list all excluded items in column A. In column B, explain why the item is excluded. You may reference the specific tax law, the text (make sure you include the page number), or a link to another trusted source. A trusted source is either supported by the IRS or academic literature (that includes textbooks)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT