Question

In: Finance

What is the NPV for a project if its cost of capital is 0 percent and...

What is the NPV for a project if its cost of capital is 0 percent and its initial after-tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4?
Select one:
a. $6,700,000
b. $137,053
c. $1,700,000
d. $371,764

Which of the following is TRUE?
Select one:
a. The Gordon model assumes that the value of a share of stock equals the future value of the current price of share that it is expected to remain constant over an infinite time horizon.
b. The marginal cost of capital is a relevant cost of capital for evaluating a firm's future investment opportunities.
c. The Gordon model is based on the premise that the value of a share of stock is equal to the sum of all future dividends it is expected to provide over an infinite time horizon.
d. The cost of retained earnings will always equal the cost of preferred stock.

Please Solve As soon as
Solve quickly I get you two UPVOTE directly
Thank's
Abdul-Rahim Taysir

Solutions

Expert Solution

First Question :
As the cost of capital is zero, there will be no discounting of the future cash flows
The NPV will be the sum of all positive cash flows less the initial investment.
Year After Tax operating Cash flows/(Cost)
Calculation of NPV Year 0                                         (5,000,000)
Year 1                                           1,800,000
Year 2                                           1,900,000
Year 3                                           1,700,000
Year 4                                           1,300,000
Total                                           1,700,000
NPV is $1,700,000

Ans c is correct.

Ans 2.

Option a. is FALSE as Gordon's model assumes that the stock price is equal to the present value of all the future earning obtainable from a stock , not the future value of current price which will remain static over a time horizon.

Option b. is TRUE. The Marginal cost of Capital is the cost of the additional capital that is needed to fund a future project. Therefore the marginal cost is relevant for evaluating a future investment opportunity.

option c is FALSE. The Gordon Model is based on the premise that the value of a stock is the PRESENT VALUE of all the future dividends that the stock will earn not the value of future dividends it will earn.

Option d. is FALSE: The cost of retained earning is approximately the same as the cost of Equity or expected return required by the Equity investors , not equal to the cost of preferred stoc.

So the Option b is only TRUE.


Related Solutions

What is the NPV for the following project if its cost of capital is 15 percent...
What is the NPV for the following project if its cost of capital is 15 percent and its initial after tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $2,000,000 in year 1, $2,000,000 in year 2, $2,000,000 in year 3 and $1,410,000 in year 4? a. 1,700,000 b. 372622 c.-137,053 d. none of the above
What is the NPV for a project whose cost of capital is 15 percent and initial...
What is the NPV for a project whose cost of capital is 15 percent and initial after-tax cost is $5,000,000 and is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4? Group of answer choices a) $1 700,000 b) 371,764 c) -4,862,947 d) -137,053
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$8,100 $3,370 $4,200 $1,540 $320
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
A firm is considering the following projects. Its opportunity cost of capital is 12%. Project 0...
A firm is considering the following projects. Its opportunity cost of capital is 12%. Project 0 1 2 3 4 A -8,500 +1,875 +1,875 +4,750 0 B -4,500 0 +4,500 +3,750 +4,750 C -8,500 +1,875 +1,875 +4,750 +8,500 1) What is the payback period on each project? 2) What is the discounted payback period on each project?
Compute the NPV for Project M if the appropriate cost of capitalis 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)Project MTime:012345Cash flow:–$2,900$650$780$820$900$400NPV:Should the project be accepted or rejected?rejectedaccepted
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT