Question

In: Finance

Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...

Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

   

  Project M
  Time: 0 1 2 3 4 5
  Cash flow –$2,000 $550 $680 $720 $800 $300

     

  NPV $   

  

Should the project be accepted or rejected?
Accepted
Rejected

Solutions

Expert Solution

Solution:
NPV     $519.90
Project should be : Accepted
Working Notes:
a b c= a x b
Year Cash Flow PVF @ 7% Present value
0 -2,000 1                        -2,000.00 d
1 550 0.93457944                      514.01869 e
2 680 0.87343873                      593.93834 f
3 720 0.81629788                      587.73447 g
4 800 0.76289521                      610.31617 h
5 300 0.71298618                      213.89585 i
NPV                             519.90 j= NPV = d+e+f+g+h+i
The project M should be accepted as NPV is positive $519.90
Notes: PVF is calculated @ 7% = 1/(1+0.07)^n     where n is the year of cash flows for which PVF is calculated.
Please feel free to ask if anything about above solution in comment section of the question.

Related Solutions

Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project M if the appropriate cost of capitalis 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)Project MTime:012345Cash flow:–$2,900$650$780$820$900$400NPV:Should the project be accepted or rejected?rejectedaccepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$8,100 $3,370 $4,200 $1,540 $320
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180 Should the project be accpeted or rejected?
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)        Project E   Time: 0 1 2 3 4 5   Cash flow –$2,000 $750 $780 $720 $500 $300        IRR %    Should the project be accepted or rejected? Accepted Rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project I Time: 0 1 2 3 4 Cash flow –$11,500 $5,580 $4,430 $1,770 $2,250 MIRR % Should the project be accepted or rejected?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT