Question

In: Finance

What is the NPV for a project whose cost of capital is 15 percent and initial...

What is the NPV for a project whose cost of capital is 15 percent and initial after-tax cost is $5,000,000 and is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4?

Group of answer choices

a) $1 700,000

b) 371,764

c) -4,862,947

d) -137,053

Solutions

Expert Solution

Option (d) is correct

Net Present value (NPV) is the present value of future cash inflows minus the initial investment.

First we will calculate the present value of cash inflows for first 4 years as per below:

Here we will use the following formula:

PV = FV / (1 + r%)n

where, FV = Future value, PV = Present value, r = rate of interest = 15%, n= time period

For calculating the present value the given cash flows, we will calculate the present values of all the years and add them up. Now,putting the values in the above equation, we get,

PV = $1800000 / (1 + 15%) + $1900000 / (1 + 15%)2  + $1700000 / (1 + 15%)3 + $1300000 / (1 + 15%)4

PV = $1800000 / (1 + 0.15) + $1900000 / (1 + 0.15)2  + $1700000 / (1 + 0.15)3 + $1300000 / (1 + 0.15)4

PV = $1800000 / (1.15) + $1900000 / (1.15)2  + $1700000 / (1.15)3 + $1300000 / (1.15)4

PV = $2070000 + ($1900000 / 1.3225)  + ($1700000 / 1.520875) + ($1300000 / 1.74900625)

PV = $1565217.39 + $1436672.97 + $1117777.60 + $743279.22

PV = $4862947.18

So, required present value is $4862947.18

Initial investment = $5000000

Net present value (NPV) = Present value of cash flows - Initial investment

Net Present value (NPV) = $4862947.18 - $5000000 = - $137053


Related Solutions

What is the NPV for the following project if its cost of capital is 15 percent...
What is the NPV for the following project if its cost of capital is 15 percent and its initial after tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $2,000,000 in year 1, $2,000,000 in year 2, $2,000,000 in year 3 and $1,410,000 in year 4? a. 1,700,000 b. 372622 c.-137,053 d. none of the above
What is the NPV for a project if its cost of capital is 0 percent and...
What is the NPV for a project if its cost of capital is 0 percent and its initial after-tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4? Select one: a. $6,700,000 b. $137,053 c. $1,700,000 d. $371,764 Which of the following is TRUE? Select one: a. The Gordon model assumes that the value of a share of...
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$8,100 $3,370 $4,200 $1,540 $320
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
What happens to the NPV of a one-year project if fixed costs are increased from $400 to $600, the firm is profitable, has a 15 percent tax rate and employs a 12 percent cost of capital?
  What happens to the NPV of a one-year project if fixed costs are increased from $400 to $600, the firm is profitable, has a 15 percent tax rate and employs a 12 percent cost of capital?     A) NPV decreases by $178.23     B) NPV decreases by $113.04     C) NPV decreases by $151.78     D) NPV decreases by $200.00
What is the NPV for a project with the following characteristics? Initial investment is $1,700,000 Initial...
What is the NPV for a project with the following characteristics? Initial investment is $1,700,000 Initial investment is depreciated to $0 over its 10 year life Project generates incremental after-tax cash flows (OCF) of $325,000 per year over the projects life Project requires a net working capital (NWC) investment today of $40,000, which is recovered at the end of the project Assets purchased with the initial investment are expected to have a salvage value of $62,000 at the end of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT