Question

In: Finance

Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...

Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project M
Time: 0 1 2 3 4 5
Cash flow: –$1,200 $390 $520 $560 $640 $140

NPV?

Should it be accepted or rejected

Solutions

Expert Solution

Year Cash flow Discount factor Present value
a b c=1.09^-a d=b*c
0 $       -1,200      1.0000 $ -1,200.00
1 $            390      0.9174 $      357.80
2 $            520      0.8417 $      437.67
3 $            560      0.7722 $      432.42
4 $            640      0.7084 $      453.39
5 $            140      0.6499 $         90.99
NPV $      572.28
The project should be accepted because it has positive NPV.

Related Solutions

Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Should the project be accepted or rejected? Project M Time: 0 1 2 3 4 5 Cash flow: –$1,500 $450 $580 $620 $700 $200 How do you come up with the NPV? And Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project M if the appropriate cost of capitalis 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)Project MTime:012345Cash flow:–$2,900$650$780$820$900$400NPV:Should the project be accepted or rejected?rejectedaccepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$8,100 $3,370 $4,200 $1,540 $320
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project I Time: 0 1 2 3 4 Cash flow –$11,500 $5,580 $4,430 $1,770 $2,250 MIRR % Should the project be accepted or rejected?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT