Question

In: Computer Science

Q) You are the manager of a project to build a data centre with the following...

Q)

You are the manager of a project to build a data centre with the following characteristics:

• The project team has to install one server a week for three months.

• The project is scheduled to last for three months.

• The total budget for this project is SAR 60,000

• Each server is planned to cost SAR 5,000.

Answer the succeeding questions based on the following information:

  • It is the beginning of the project's month two and your team has installed only three servers.
  • Planned value = SAR 20,000
  • Actual cost = SAR 22,000
  • Earned value = SAR 15,000

  1. Calculate the cost variance, schedule variance, cost performance index, and schedule performance index for the project.

  1. Is the Project ahead of schedule or behind schedule? Is it under budget or over budget?

Solutions

Expert Solution

>>Answer

>.Given

Please refer to the detailed explanation.


Explanation:

Planned value to date = SAR 20,000

Actual cost to date = SAR 22,000

Earned value to date = SAR 15,000

Q.1) Cost Variance = Earned Value to date - Actual Cost to date

Cost Variance = 15000 - 22000

Cost Variance (CV) = -SAR 7000

Schedule Variance = Earned Value to date - Planned Value to date

Schedule Variance = 15000 - 20000

Schedule Variance (SV) = -SAR 5000

Cost Performance Index = Earned Value to date / Actual Cost to date

Cost Performance Index = 15000 / 22000

Cost Performance Index (CPI) = 0.682

Schedule Performance Index = Earned Value to date / Planned Value to date

Schedule Performance Index = 15000 / 20000

Schedule Performance Index (SPI) = 0.750

Q.2) If Schedule Variance > 0, the project is ahead of the schedule

If Schedule Variance < 0, the project is behind the schedule

If Schedule Variance = 0, the project is on the schedule

Similarly,

If SPI > 1, the project is ahead of the schedule

If SPI < 1, the project is behind the schedule

If SPI = 1, the project is on the schedule

Here, both Schedule Variance < 0 and SPI < 1.

Hence, the project is behind the schedule.

If CV > 0, the project is under budget

If CV < 0, the project is over budget

If CV = 1, the project is on budget

Similarly, If CPI > 1, the project is under budget

If CPI < 1, the project is over budget

If CPI = 1, the project is on budget

Here, both Cost Variance < 0 and CPI < 1.


Related Solutions

You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Scenario: You are the project manager assigned to build and decorate a model home. What might...
Scenario: You are the project manager assigned to build and decorate a model home. What might be an example of a lead you encounter when scheduling work activities? Also, what might be an example of a lag?
As the manager of a large distribution centre, you are responsible for conducting an annual inventory...
As the manager of a large distribution centre, you are responsible for conducting an annual inventory count. The DC maintains 13000 SKU’s with a total value of $4,250,000.00 on the day of the inventory. Annual sales are $28,000,000.00. The ABC analysis has A items at 10% with 80% of the value, B is 10% items with 10% of the value and C items constitute the balance. Inventory carrying cost is 20%. All items are maintained on shelving designed to be...
Given a project with the following characteristics, answer the following questions: You are the project manager...
Given a project with the following characteristics, answer the following questions: You are the project manager of a project to upgrade the generators at cell phone towers. Your project is scheduled to last for 12 months. It is the beginning of month 4. Your crews are to upgrade 8 cell phone towers per month for 12 months. Each generator is planned to cost $40,000 which includes equipment, labor, and fueling costs. You have upgraded 30 cell phone towers and your...
You are a project manager evaluating the following three projects               Year                Project A &
You are a project manager evaluating the following three projects               Year                Project A                       Project B                       Project C               0                     -$150,000                      -$300,000                      -$150,000               1                     $110,000                       $200,000                       $120,000               2                     $110,000                       $200,000                       $90,000 The relevant discount rate ( r ) is 12% a year Calculate the PI for each of the three projects. Calculate the NPV for each of the three projects. If the projects were independent, and according to the PI rule, which project(s) would you...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...
XYZ company is considering investing in Project Q or Project U. Project Q generates the following...
XYZ company is considering investing in Project Q or Project U. Project Q generates the following cash flows: year “zero” = 281 dollars (outflow); year 1 = 211 dollars (inflow); year 2 = 330 dollars (inflow); year 3 = 318 dollars (inflow); year 4 = 196 dollars (inflow). Project U generates the following cash flows: year “zero” = 230 dollars (outflow); year 1 = 150 dollars (inflow); year 2 = 105 dollars (inflow); year 3 = 201 dollars (inflow); year...
Course Project Week 4 For this next part of the project you will build the Income...
Course Project Week 4 For this next part of the project you will build the Income Statement and Balance Sheet for the Bike Repair & Maintenance Shop (BRMS) for 2018. Use the information below and add another sheet to your Excel Workbook. BRMS Information for 2018 In 2017, the repair shop was opened in October and ended the year with a ($10,500) operating loss. Supply Inventory of parts & supplies maintained   $3,000 Replacement parts are ordered as they are used....
5) A project manager at System Design Corporation has collected the following data on the size...
5) A project manager at System Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 300,000 lines of code. Use a scatter plot to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system. Module Size in 1000 lines of code Number...
You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT