Question

In: Accounting

2. A Plus Company uses activity-based costing to determine the costs of its three products: A,...

2.

A Plus Company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:

Budgeted Activity
Activity Cost Pool Budgeted Cost Product A Product B Product C
Activity 1 $ 70,000 6,000 9,000 20,000
Activity 2 $ 45,000 7,000 15,000 8,000
Activity 3 $ 82,000 2,500 1,000 1,625


Which of the following statements is true regarding this company's activity rates?

Multiple Choice

  • The activity rate under the activity-based costing system for Activity 2 is $2.81.

  • The activity rate under the activity-based costing system for Activity 2 is $16.00.

  • The activity rate under the activity-based costing system for Activity 2 is $19.50.

  • The activity rate under the activity-based costing system for Activity 2 is $1.50.

  • The activity rate under the activity-based costing system for Activity 2 is $2.00.

Solutions

Expert Solution

Correct answer-------The activity rate under the activity-based costing system for Activity 2 is $1.50.

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost Expected Activity (B) Activity rate (A/B)
Activity 1 Number of Activity $         70,000.00 35,000 $            2.00 Per Activity
Activity 2 Number of Activity $         45,000.00 30000 $            1.50 Per Activity
Activity 3 Number of Activity $         82,000.00 5125 $          16.00 Per Activity

As it can be seen $16 per activity is rate for Activity 3 not 2 and $ 2 is rate for activity 1.


Related Solutions

A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 85,000 7,500 10,500 21,500 Activity 2 $ 60,000 8,500 16,500 9,500 Activity 3 $ 112,000 4,000 2,500 3,125 How much overhead will be assigned to Product B...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
1.) A company uses activity-based costing to determine the costs of its three products: A, B,...
1.) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 81,000 7,100 10,100 21,100 Activity 2 $ 56,000 8,100 16,100 9,100 Activity 3 $ 104,000 3,600 2,100 2,725 How much overhead will be assigned to Product...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B,...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown below. (Check: Activity 1 activity rate should be a number between $7 and $10). (3 points) Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $140,000 7,500 4,000 6,000 Activity 2 $54,000 2,500 2,000 1,500 Activity 3 $38,000 15,000 25,000...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Lysiak Corporation uses an activity based costing system to assign overhead costs to products. In the...
Lysiak Corporation uses an activity based costing system to assign overhead costs to products. In the first stage, two overhead costs--equipment depreciation and supervisory expense-are allocated to three activity cost pools--Machining, Order Filling, and Other--based on resource consumption. Data to perform these allocations appear below: Overhead costs: Equipment depreciation $ 47,000 Supervisory expense $ 6,000 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Machining Order Filling Other Equipment depreciation 0.60 0.10 0.30 Supervisory expense 0.60 0.20 0.20...
Jung Company uses activity-based costing. It makes two products, X and Y. The company's overhead costs...
Jung Company uses activity-based costing. It makes two products, X and Y. The company's overhead costs are traced to two activity cost pools. The following data are given: Activity cost pool Activity measure Estimated Overhead Cost Activity For X For Y Total Design Number of parts $32,000 200 parts 800 parts 1,000 parts Inspection Production units $18,000 2,000 units 1,000 units 3,000 units For the design activity, its activity rate (predetermined overhead rate) is:
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has...
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has provided the following data concerning its activity-based costing system: Activity Cost Pool (and Activity Measure) Total Cost Machine related (machine-hours) $ 135,200 Batch setup (setups) $ 604,800 Order size (direct labor-hours) $ 121,500 Total Activity Activity Cost Pools Product X Product Y Total Machine related 1,400 6,600 8,000 Batch setup 2,900 5,100 8,000 Order size 6,400 2,600 9,000 The total amount of overhead cost...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT