Question

In: Accounting

A company uses activity-based costing to determine the costs of its three products: A, B, and...

A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:

A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:

Budgeted Activity
Activity Cost Pool Budgeted Cost Product A Product B Product C
Activity 1 $ 90,000 8,000 11,000 22,000
Activity 2 $ 65,000 9,000 17,000 10,000
Activity 3 $ 122,000 4,500 3,000 3,625


How much overhead will be assigned to Product B using activity-based costing?

Multiple Choice

  • $87,739.66

  • $106,101.05

  • $80,042.76

  • $277,000.00

  • $90,000.00


How much overhead will be assigned to Product B using activity-based costing?

Solutions

Expert Solution

--Correct Answer = Option #1: $ 87,739.66

Allocated to Product B
Activity 1 $                                          24,146.34
Activity 2 $                                          30,694.44
Activity 3 $                                          32,898.88
Total cost allocated $                                          87,739.66 Answer

--Working

Allocated to Product B
Activity 1 =90000*11000/(8000+11000+22000)
Activity 2 =65000*17000/(9000+17000+10000)
Activity 3 =122000*3000/(4500+3000+3625)

Related Solutions

A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 85,000 7,500 10,500 21,500 Activity 2 $ 60,000 8,500 16,500 9,500 Activity 3 $ 112,000 4,000 2,500 3,125 How much overhead will be assigned to Product B...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
1.) A company uses activity-based costing to determine the costs of its three products: A, B,...
1.) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 81,000 7,100 10,100 21,100 Activity 2 $ 56,000 8,100 16,100 9,100 Activity 3 $ 104,000 3,600 2,100 2,725 How much overhead will be assigned to Product...
2. A Plus Company uses activity-based costing to determine the costs of its three products: A,...
2. A Plus Company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 70,000 6,000 9,000 20,000 Activity 2 $ 45,000 7,000 15,000 8,000 Activity 3 $ 82,000 2,500 1,000 1,625 Which of the following statements is true...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A,...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 89,000 7,900 10,900 21,900 Activity 2 $ 64,000 8,900 16,900 9,900 Activity 3 $ 120,000 4,400 2,900 3,525 How much overhead will be assigned to...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B,...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown below. (Check: Activity 1 activity rate should be a number between $7 and $10). (3 points) Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $140,000 7,500 4,000 6,000 Activity 2 $54,000 2,500 2,000 1,500 Activity 3 $38,000 15,000 25,000...
Jennifer Company has two products: A and B. The company uses activity-based costing
Jennifer Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: The activity rate under the activity based costing system for Supporting customers is closest to:
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three acivity cot pools. Cost Pool Budgeted Cost Product A Product B Activity 1 $87,000 3,000 2,800 Activity 2 $62,000 4,500 5,500 Activity 3 $93,000 2,500 5,250 Annual Production and sales level of Product A is, 34,300 units, and the annual production and sales level of Product B is 69,550 Units. What is...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 200 units and of Product B is 400 units. There are three activity cost pools, with estimated costs and expected activity as follows: Expected ActivityActivity Cost PoolEstimated CostProduct AProduct BTotalActivity 1$16,660600100700Activity 218,4501,1007001,800Activity 39,7316016022022. The cost per unit of Product A is closest to which of the following? A. $27.91. B. $56.38. C. $141.04. D. $70.52.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT