Question

In: Accounting

1.) A company uses activity-based costing to determine the costs of its three products: A, B,...

1.) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:

Budgeted Activity
Activity Cost Pool Budgeted Cost Product A Product B Product C
Activity 1 $ 81,000 7,100 10,100 21,100
Activity 2 $ 56,000 8,100 16,100 9,100
Activity 3 $ 104,000 3,600 2,100 2,725

How much overhead will be assigned to Product B using activity-based costing?

a.) $93,565.31 b.) $74,358.24 c.) $81,000.00 d.) $241,000.00 e.)71,514.24

2.) A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:

Budgeted Activity
Activity Cost
Pool
Budgeted
Cost
Product A1 Product B2
Activity 1 $ 57,000 2,100 5,700
Activity 2 $ 72,000 3,140 5,660
Activity 3 $ 98,000 8,100 1,700

Annual production and sales level of Product A1 is 9,380 units, and the annual production and sales level of Product B2 is 23,210 units. What is the approximate overhead cost per unit of Product A1 under activity-based costing?

a.) $4.52 b.) $10.00 c.) $8.18 d.) $7.31 e.)$13.01

Solutions

Expert Solution

Question 1

Correct answer------------(b.) $74,358.24

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Activity 1 Number of Activity $        81,000.00 38300 $               2.11 Per Activity
Activity 2 Number of Activity $        56,000.00 33300 $               1.68 Per Activity
Activity 3 Number of Activity $      104,000.00 8425 $             12.34 Per Activity

.

Cost assigned to Product B
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Activity 1 $                       2.11 10100 $         21,360.31
Activity 2 $                       1.68 16100 $         27,075.08
Activity 3 $                     12.34 2100 $         25,922.85
Total Overheads assigned $         74,358.24

Question 2

Correct answer------------(e) $13.01

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Activity 1 Number of Activity $        57,000.00 7800 $               7.31 Per Activity
Activity 2 Number of Activity $        72,000.00 8800 $               8.18 Per Activity
Activity 3 Number of Activity $        98,000.00 9800 $             10.00 Per Activity

.

Cost assigned to Product A1
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Activity 1 $                       7.31 2100 $         15,346.15
Activity 2 $                       8.18 3140 $         25,690.91
Activity 3 $                     10.00 8100 $         81,000.00
Total Overheads assigned $       122,037.06
Production               9,380.00
Overhead cost per unit $ 13.01

Related Solutions

A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 85,000 7,500 10,500 21,500 Activity 2 $ 60,000 8,500 16,500 9,500 Activity 3 $ 112,000 4,000 2,500 3,125 How much overhead will be assigned to Product B...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
2. A Plus Company uses activity-based costing to determine the costs of its three products: A,...
2. A Plus Company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 70,000 6,000 9,000 20,000 Activity 2 $ 45,000 7,000 15,000 8,000 Activity 3 $ 82,000 2,500 1,000 1,625 Which of the following statements is true...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A,...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 89,000 7,900 10,900 21,900 Activity 2 $ 64,000 8,900 16,900 9,900 Activity 3 $ 120,000 4,400 2,900 3,525 How much overhead will be assigned to...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B,...
4. Nationals Inc. uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown below. (Check: Activity 1 activity rate should be a number between $7 and $10). (3 points) Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $140,000 7,500 4,000 6,000 Activity 2 $54,000 2,500 2,000 1,500 Activity 3 $38,000 15,000 25,000...
Jennifer Company has two products: A and B. The company uses activity-based costing
Jennifer Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: The activity rate under the activity based costing system for Supporting customers is closest to:
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three acivity cot pools. Cost Pool Budgeted Cost Product A Product B Activity 1 $87,000 3,000 2,800 Activity 2 $62,000 4,500 5,500 Activity 3 $93,000 2,500 5,250 Annual Production and sales level of Product A is, 34,300 units, and the annual production and sales level of Product B is 69,550 Units. What is...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 200 units and of Product B is 400 units. There are three activity cost pools, with estimated costs and expected activity as follows: Expected ActivityActivity Cost PoolEstimated CostProduct AProduct BTotalActivity 1$16,660600100700Activity 218,4501,1007001,800Activity 39,7316016022022. The cost per unit of Product A is closest to which of the following? A. $27.91. B. $56.38. C. $141.04. D. $70.52.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT