In: Finance
Consider the following two mutually exclusive projects: |
Year | Cash Flow (A) | Cash Flow (B) |
0 | –$250,000 | –$35,000 |
1 | 15,000 | 17,000 |
2 | 40,000 | 11,000 |
3 | 55,000 | 20,000 |
4 | 340,000 | 15,000 |
The required return on these investments is 14 percent. |
Required: | |
(a) |
What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) |
Payback period | |
Project A | years |
Project B | years |
(b) |
What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g.,32.16).) |
Net present value | |
Project A | $ |
Project B | $ |
(c) |
What is the IRR for each project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) |
Internal rate of return | |
Project A | % |
Project B | % |
(d) |
What is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 3 decimal places (e.g., 32.161).) |
Profitability index | |
Project A | |
Project B | |
(e) | Based only on the projects' NPV and IRR, which project should you finally choose? |
a)
Project A:
Cumulative cash flow for year 0 = -250,000
Cumulative cash flow for year 1 = -250,000 + 15,000 = -235,000
Cumulative cash flow for year 2 = -235,000 + 40,000 = -195,000
Cumulative cash flow for year 3 = -195,000 + 55,000 = -140,000
Cumulative cash flow for year 4 = -140,000 + 340,000 = 200,000
140,000 / 340,000 = 0.41
Payback period of project A = 3 + 0.41 = 3.41 years
Project B:
Cumulative cash flow for year 0 = -35,000
Cumulative cash flow for year 1 = -35,000 + 17,000 = -18,000
Cumulative cash flow for year 2 = -18,000 + 17,000 = -1,000
Cumulative cash flow for year 3 = -1,000 + 11,000 = 10,000
1,000 / 11,000 = 0.09
Payback period of project B = 2 + 0.09 = 2.09 years
b)
Project A:
NPV = Present value of cash inflows - present value of cash outflows
NPV = -,250,000 + 15,000 / (1 + 0.14)1 + 40,000 / (1 + 0.14)2 + 55,000 / (1 + 0.14)3 + 340,000 / (1 + 0.14)4
NPV = -250,000 + 282,367.3236
NPV = $32,367.32
Project B:
NPV = Present value of cash inflows - present value of cash outflows
NPV = -,35,000 + 17,000 / (1 + 0.14)1 + 11,000 / (1 + 0.14)2 + 20,000 / (1 + 0.14)3 + 15,000 / (1 + 0.14)4
NPV = -35,000 + 45,757.058
NPV = $10,757.06
c)
Project A:
IRR is the rate of return that makes NPV equal to 0
NPV = -,250,000 + 15,000 / (1 + R)1 + 40,000 / (1 + R)2 + 55,000 / (1 + R)3 + 340,000 / (1 + R)4
Using trial and error method, i.e., after trying various values for R, lets try R as 18.04%
NPV = -,250,000 + 15,000 / (1 + 0.1804)1 + 40,000 / (1 + 0.1804)2 + 55,000 / (1 + 0.1804)3 + 340,000 / (1 + 0.1804)4
NPV = 0
Therefore , IRR of project A is 18.04%
Project B:
IRR is the rate of return that makes NPV equal to 0
NPV = -,35,000 + 17,000 / (1 + R)1 + 11,000 / (1 + R)2 + 20,000 / (1 + R)3 + 15,000 / (1 + R)4
Using trial and error method, i.e., after trying various values for R, lets try R as 28.20%
NPV = -,35,000 + 17,000 / (1 + 0.282)1 + 11,000 / (1 + 0.282)2 + 20,000 / (1 + 0.282)3 + 15,000 / (1 + 0.282)4
NPV = 0
Therefore , IRR of project B is 28.20%
d)
Project A:
Profitability index = Present value / initial investment
Present value was found during calculation of NPV
Profitability index = 282,367.3236 / 250,000
Profitability index = 1.13
Profitability index of project A is 1.13
Project B:
Profitability index = Present value / initial investment
Present value was found during calculation of NPV
Profitability index = 45,757.058 / 35,000
Profitability index = 1.31
Profitability index of project B is 1.31
e)
When projects are mutually exclusive, we should always choose the project with higher NPV.
Project A should be chosen